Greater Manchester Combined Authority noted this item on Friday 30 September 2022. Below is the council's own wording, with the papers it was decided on.
That the draft GM Local Area Energy Plan, its contents and the research undertaken to inform its development be noted. 2. That the GM Local Area Energy Plan for design & publication as included in Annex 1 to the report be approved. 3. That the next steps in delivering the city-regions Local Area Energy Plan(s) be approved. 4. That the GM Pension Fund Board be requested to consider further opportunities for investment in renewable energy schemes.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
Greater Manchester Local Area Energy Planning: Overview & Insight Version 0.4 Client review June 2022
Greater Manchester LAEP Overview & Insights 2022 1 Authors and contributors Authors
Ben Walters Consultant Energy Systems Modelling
Jenny Line Senior Project Manager
Contributors:
Richard Leach Local & Site Energy Transition Manager
DISCLAIMER
This document has been prepared by Energy Systems Catapult Limited for Greater Manchester Combined Authority. All information is given in good faith based upon the latest information available to Energy Systems Catapult Limited. No warranty or representation is given concerning such information, which must not be taken as establishing any contractual or other commitment binding upon the Energy Systems Catapult Limited or any of its subsidiary or associated companies. Contents
0. Executive summary 4 1. Introduction 11 2. The Vision 17 3. Fabric Retrofit 37 4. Heating Systems 44 5. Transport and EV Charging 52 6. Local Energy Generation and Storage 58 7. Energy Networks 64 8. Cost and Investment 76 9. Carbon budget 81 10. Roadmap and Conclusions 86 Technical Annex 96 ESC Modelling Tools and Approach 104 Data Sources Annex 111 0. EXECUTIVE SUMMARY
This report sets out an overview of the ten Local Area Energy Plans created for the ten districts in Greater Manchester (GM) and insights into what this means for GM to meet its carbon budget and 2038 carbon neutrality target. To meet the target, GM will need to lead the way with local action, with £65bn investment required.* This report sets out the current position and a roadmap towards that decarbonised future, whilst providing a significant focus on the identification of areas across GM to prioritise and target low regret near-term (over the next 5 years) action and align proposed activity with the carbon budget. This is provided through place-based illustration of several near-term priority zones and opportunity areas for different technologies for each of GM’s districts. The roadmap then also identifies key decision points that are needed to determine the longer-term decarbonisation pathway for the city region. For the near-term activity, the region will need to deliver the following additional measures over the next 5 years: 140,000 homes with fabric retrofit Nearly 2 GW of rooftop PV on homes 190,000 EVs† 8,000 homes newly connected to heat networks 116,000 heat pumps in homes. Similar levels of interventions in public, commercial and industrial buildings and fleets will also be needed, with public sector buildings making up over 7% of GM’s non- domestic building stock. This will include the opportunity for over 2.5 GW of non- domestic rooftop PV. These figures will need to rise dramatically over the coming fifteen years, with around a million heat pumps in homes (assuming a primarily electrified future for heating) and a million EVs needing charging by 2038, meaning work to enhance GM’s local electricity network and find options for flexibility on the grid will also be vital. This report considers two scenarios, that centre on one of the key decisions regarding the wide-scale decarbonisation of heat across GM: a primary scenario where GM leads the way with local actions, resulting in a predominantly electrified future, and a secondary scenario where hydrogen for heating becomes available as proposed by the HyNet project‡.
* Includes costs that would be spent even without decarbonisation to maintain the current system (figures
are for the primary scenario assuming a largely electrified future). When considered at an individual district level, this typically equates to in the region of 70% of the overall investment cost. † including plug-in hybrid. Domestic/personal vehicles only ‡ HyNet North West is being delivered by a consortium of partners, each of which will lead a different part
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Greater Manchester Combined Authority at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.