RESOLVED/- 1. That the recommendations to be considered by the GMCA at their meeting on 27 October 2024 be noted, as comprising of as below: a) Approve that a floor and a ceiling price cap of 30% above and below the current EV tariff (set out in paragraph 1.10 of the report) is introduced; and b) Delegate to the Chief Executive of the GMCA and TfGM approval of tariff changes within those limits. 2. That a price comparison of the EV charging network be circulated to members following the meeting with the view to understanding the rates offered by each provider.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
Tariff increases may result in complaints/reduction in usage. A communications plan will be implemented to help mitigate this.
Legal Considerations
Set out in the report.
Financial Consequences – Revenue
The ability to be agile in changing the Be.EV tariff will allow Greater Manchester to ensure that the tariff is covering operational costs.
Financial Consequences – Capital
Not applicable.
Number of attachments to the report: None
Comments/recommendations from Overview & Scrutiny Committee
Not applicable. Background Papers GMCA 25 March 2022 Greater Manchester Electric Vehicle Charging Tariff
GMCA 29 November 2019 Greater Manchester Electric Vehicle Charging Proposal
GMCA 26 January 2018 Transport Budget for 2018/19
Tracking/ Process Does this report relate to a major strategic decision, as set out in the GMCA Constitution?
Yes
Exemption from call in Are there any aspects in this report which means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency?
No 1. Introduction & Background
1.1As of September 2023, there are 720 publicly accessible electric vehicle charging devices in Greater Manchester. Of these, 200 are branded as part of the Be.EV network, 151 of these are owned by TfGM (with Iduna Infrastructure Ltd owning the remainder). The Be.EV brand is owned by Iduna Infrastructure Ltd1 who have a contract with TfGM to operate and maintain TfGM units. A programme of 60 additional TfGM-owned taxi charging points is currently being implemented.
1.2The current contract term is 7 years from December 2019 i.e., to December 2026 with two optional 3-year extensions available from December 2029 and December 2032.
1.3Whilst there are contractual arrangements about tariff setting, in that both parties can set their own, there is a non-binding agreement to have a unified rate so that there is a Be.EV tariff, rather than different rates depending on ownership – this is intended to improve the customer experience.
1.4The tariff is primarily driven by the cost of electricity that is being supplied to the consumer through the unit, with a small percentage to cover the operation and maintenance costs. Effectively, in setting an EV tariff, TfGM is trying to cover its costs without a subsidy from the Transport Levy.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Bee Network Committee at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.