Mayoral General Budget & Precept Proposals 2024/25
ApprovedCommittee1 paper
Greater Manchester Combined Authority approved this item on Friday 9 February 2024. Below is the council's own wording, with the papers it was decided on.
That the Mayor’s General budget for 2024/25, as set out in this report together with the calculation of the precepts and Council Tax rates set out in Appendix 2, be approved. 2. That the Mayoral General Precept to £112.95 (Band D) comprising of £81.20 for functions previously covered by the Fire and Rescue Authority precept and £31.75 for other Mayoral General functions be approved. 3. That the following be approved: i . the overall budget for the Fire and Rescue Service for 2024/25 covered by the Mayoral precept. ii. the medium-term financial position for the Fire and Rescue Service. 4. That approval be given to the use of reserves, as set out in section 3 of the report, and the assessment by the Treasurer that the reserves as at March 2025 were adequate. 5. That it be noted that in accordance with legal requirements, the minutes will record the names of those Members voting for or against the Mayor’s budget and precept proposals. 6. That the feedback from the GMCA Overview and Scrutiny Committee be received and noted.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
The report sets out the Mayor’s proposals for the Mayoral General Budget (including Fire and Rescue) and seeks approval for the Mayoral General Precept for 2024/25.
The report recommends the setting of the Revenue Budget for 2024/25 as required under Section 42A of the Local Government Finance Act 1992 (updated in the Localism Act 2011) and the precepts and relevant levels of Council Tax required under sections 40, 42B and 47 of the Act.
Recommendations
The GMCA is requested to:
1. Approve the Mayor’s General budget for 2024/25 set out in this report together with the calculation of the precepts and Council Tax rates set out in Appendix 2.
1 2. Approve the Mayoral General Precept to £112.95 (Band D) comprising of £81.20 for functions previously covered by the Fire and Rescue Authority precept and £31.75 for other Mayoral General functions.
3. Approve: i. the overall budget for the Fire and Rescue Service for 2024/25 covered by the Mayoral precept iii. the medium term financial position for the Fire and Rescue Service
4. Approve the use of reserves as set out in section 3 of the report and the assessment by the Treasurer that the reserves as at March 2025 are adequate.
5. Note that in accordance with legal requirements, the minutes will record the names of those Members voting for or against the Mayor’s budget and precept proposals.
Climate Change Impact Assessment and Mitigation Measures: N/A
2 Risk Management – An assessment of the potential budget risks faced by the authority are carried out quarterly as part of the monitoring process. Specific risks and considerations for the budget 2024/25 insofar as they relate to the Fire Service are detailed in Appendix 2.
Legal Considerations – See Appendix 1 of the report.
Financial Consequences – Revenue – The report sets out the planned budget strategy for 2024/25 and future years.
Financial Consequences – Capital – Proposals for Fire and Rescue Services capital spend are set out within Part 2 of the report.
Background papers
GMCA – Mayoral General Budget and Precept Proposals 2023/24 – 10 February 2023 GMCA - Mayoral General Budget and Precept Proposals 2024/25 – 26 January 2024
TRACKING/PROCESS Does this report relate to a major strategic decision, as set out in the GMCA Constitution? Yes
EXEMPTION FROM CALL IN Are there any aspects in this report which means it should be considered to be exempt from call in? N/A
Overview & Scrutiny Committee - 7th February 2024
3 1. INTRODUCTION
1.1The purpose of this report is to set out for the Greater Manchester Combined Authority (GMCA) the Mayor’s budget for 2024/25, to meet the costs of Mayoral general functions. The functions of the GMCA which are currently Mayoral General functions are: • Fire and Rescue • Compulsory Purchase of Land • Mayoral development corporations • Development of transport policies • Preparation, alteration and replacement of the Local Transport Plan • Grants to bus service operators • Grants to constituent councils • Decisions to make, vary or revoke bus franchising schemes
1.2The sources of funding for Mayoral costs, to the extent that they are not funded from other sources, are a precept or statutory contribution (not Fire). A precept can be issued by the Mayor to GM Councils as billing authorities. The precept is apportioned between local authorities on the basis of Council Tax bases and must be issued before 1st March.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Greater Manchester Combined Authority at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.