Transport Capital Programme

Noted Committee 1 paper

Bee Network Committee noted this item on Thursday 21 March 2024. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

RESOLVED/- 1. That the current position in relation to CRSTS1 and CRSTS2 be noted. 2. That the drawdown and reallocation of CRSTS funding and associated scheme for progression be approved as follows: • Access for All: £4.71m CRSTS funding; • Rapid Transit Integration Programme: Stop Improvements and New Stops Package. £1.28m CRSTS funding; • Future Rapid Transit Programme: Extensions Package. £3.3m CRSTS funding; • Electric Vehicle Charging Infrastructure (EVCI): £1.09m CRSTS funding; • Manchester: Ancoats Streets for All. Full Business Case approval and £1.36m CRSTS funding; • Manchester: Transforming Deansgate: £2.15m CRSTS funding; • Stockport: Queens Road Bridge (Strategic Maintenance). Reallocation of £0.5m and drawdown of a further £2.6m CRSTS funding; • Zero Emission Bus (ZEB) Programme: Depot Electrification: total of £37.8m CRSTS funding £25.3m and match funding £12.5m; • ZEB Programme: Reallocation of £1.57m of ZEB Programme Tranche 1 funding; • Improving Journeys – Orbital Bus Routes (QBT) – Traffic Signal Upgrades. Full Business Case approval and £0.21m CRSTS funding; and • Core Highways, Strategic Highways and Local Safety & Minor Works Maintenance funding for 2024/25, totalling £57.85m. 3. That the drawdown of and variations to Active Travel funding be approved as follows: • £1.025m of MCF funding for Tameside’s Active Neighbourhoods, Phase 2; • £3.59m of MCF funding for Manchester’s Levenshulme Active Neighbourhood; • £1.8m of Active Travel Fund Round 4 (ATF4) funding for Salford Chapel Street East, Phase 1; and • Agree formal MCF scheme budget variations for Manchester City Council as set out in paragraph 3.12. 4. That the release of £0.994m from previously approved funding to facilitate the replacement of the Public Switched Telephone Network (PSTN) with a digital solution be noted. 5. That it be noted that a decision in relation to Access for All funding was expected early May. However, should no decision on next round of funding be forthcoming in the near future it was agreed that a letter be issued to Government on behalf of the Bee Network Committee requesting an update on progress.
Word for word from the decision Greater Manchester Combined Authority published for this meeting. Source: democracy.greatermanchester-ca.gov.uk

Follow this further

Built from Greater Manchester Combined Authority's papers

What the report saysPro

Report to Bee Network Committee

Bee Network Committee Date: Thursday 21 March 2024

Subject: Transport Capital Programme Report

Report of: Chris Barnes, Infrastructure Pipeline Programme Director, TfGM

Purpose of Report This report asks members to note the current position on the Greater Manchester Transport Capital Programme and consider a number of recommendations in order to support the continued development and delivery of the programme.

Recommendations: The Committee are requested to:

1. Note the current position in relation to CRSTS1 and CRSTS2; 2. Approve the drawdown and reallocation of CRSTS funding and associated scheme progression as follows: • Access for All: £4.71m CRSTS funding; • Rapid Transit Integration Programme: Stop Improvements and New Stops Package. £1.28m CRSTS funding; • Future Rapid Transit Programme: Extensions Package. £3.3m CRSTS funding; • Electric Vehicle Charging Infrastructure (EVCI): £1.09m CRSTS funding; • Manchester: Ancoats Streets for All. Full Business Case approval and £1.36m CRSTS funding; • Manchester: Transforming Deansgate: £2.15m CRSTS funding; • Stockport: Queens Road Bridge (Strategic Maintenance). Reallocation of £0.5m and drawdown of a further £2.6m CRSTS funding; • Zero Emission Bus (ZEB) Programme: Depot Electrification: total of £37.8m CRSTS funding £25.3m and match funding £12.5m; • ZEB Programme: Reallocation of £1.57m of ZEB Programme Tranche 1 funding; • Improving Journeys – Orbital Bus Routes (QBT) – Traffic Signal Upgrades. Full Business Case approval and £0.21m CRSTS funding; and • Core Highways, Strategic Highways and Local Safety & Minor Works Maintenance funding for 2024/25, totalling £57.85m. 3. Approve the drawdown of and variations to Active Travel funding as follows: • £1.025m of MCF funding for Tameside’s Active Neighbourhoods, Phase 2; • £3.59m of MCF funding for Manchester’s Levenshulme Active Neighbourhood; • £1.8m of Active Travel Fund Round 4 (ATF4) funding for Salford Chapel Street East, Phase 1; and • Agree formal MCF scheme budget variations for Manchester City Council as set out in paragraph 3.12. 4. Note the release of £0.994m from previously approved funding to facilitate the replacement of the Public Switched Telephone Network (PSTN) with a digital solution.

Contact Officers

Chris Barnes Infrastructure Pipeline [email removed] Programme Director, TfGM Dave Abdy Infrastructure Pipeline Deputy [email removed] Programme Lead, TfGM Claire Butler Infrastructure Pipeline Senior [email removed] Programme Manager, TfGM Richard Nickson Network Director, Active [email removed] Travel, TfGM Equalities Impact, Carbon and Sustainability Assessment:

Recommendation - Key points for decision-makers The GMCA is requested to approve the funding draw down requests.

Impacts Questionnaire Impact Indicator Result Justification/Mitigation Equality and Inclusion G Health G Resilience and G Adaptation Housing Economy G Mobility and G Connectivity Carbon, Nature and G Environment Consumption and Production

Schemes are being developed to promote greater use of public transport and sustainable Contribution to achieving the travel modes, and to incorporate other carbon reduction measures where possible (for GM Carbon Neutral 2038 example, Bury Interchange). target

Further Assessment(s): Equalities Impact Assessment and Carbon Assessment Positive impacts overall, Mix of positive and Mostly negative, with at G whether long or short A negative impacts. Trade- R least one positive aspect. RR Negative impacts overall. term. offs to consider. Trade-offs to consider.

Carbon Assessment Overall Score 0.88

Buildings Result Justification/Mitigation New Build residential N/A Residential building(s) N/A renovation/maintenance New build non- residential (including N/A public) buildings Transport Active travel and public 0.71 transport Roads, Parking and 1 Vehicle Access Access to amenities 1 Vehicle procurement N/A Land Use Land use #####

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Transport Capital ProgrammeReport 406 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 20 attended
DV
Daniel VaughanCouncil Staff, in attendance
NR
Nick RobertsCouncil Staff, expected
GM
GM Mayor Andy BurnhamChair, present
EO
Councillor Eamonn O'BrienVice-Chair, present
HS
Councillor Howard SykesCommittee Member, present
DM
Councillor David MellerCommittee Member, apologies
DC
Councillor Dan CostelloCommittee Member, absent
JG
Councillor James GartsideCommittee Member, present
HK
Councillor Hamid KhurramCommittee Member, apologies
TR
Councillor Tracey RawlinsCommittee Member, present
AQ
Councillor Alan QuinnCommittee Member, present
ET
Councillor Elaine TaylorCommittee Member, apologies

All 20 on the meeting page

On this subject at Greater Manchester Combined Authority

Search all
  1. Transport Capital ProgrammeThis decision
  2. Transport Capital ProgrammeNoted
  3. Transport Capital ProgrammeNoted
  4. Transport Capital ProgrammeNoted
  5. Transport Capital ProgrammeNoted
  6. Transport Capital ProgrammeNoted

More from Greater Manchester Combined Authority Bee Network Committee

All decisions
MeetingDecisionOutcome
24 Sep 2026 ApologiesApologies were received and noted from Cllr Nazia Rehman (Wigan), City Mayor Paul Dennett (Salford), Cllr Stephen Hom... Noted Open
24 Sep 2026 Appointment UpdatesThat the update on the appointments made at the June meeting of the GMCA be noted. 2. That the appointments of the Ma... Noted Open
24 Sep 2026 Appointments to Outside BodiesThat the appointment of Cllr Barry Winstanley, Cllr Grace Baynham & Cllr Michael Welton to the Greater Manchester Acc... Noted Open
24 Sep 2026 Terms of Reference & Rules of ProcedureThat the terms of reference and rules of procedure be noted. Noted Open
24 Sep 2026 Declarations of InterestThere were none. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies