That the current progress relating to electromobility in the GM region be noted. 2. That it be noted that forecast growth and demand for charging infrastructure will be used to inform the emerging Local Transport Plan. 3. That the introduction of an indicator which will track GM’s progress in facilitating charging for households without off-street parking be endorsed. 4. That the introduction of a zero-emission journey tracker be endorsed, 5. That the update on the Electric Vehicle Infrastructure programmes of work be noted. 6. That committee members be provided with details of contacts within their own authorities collating site details for potential LEVI funding. 7. That the rates for GM owned charging assets be shared with members.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
Local Electric Vehicle Infrastructure (LEVI) fund is a significant programme of activity to significantly increase the deployment of local, primarily low power, on-street charging infrastructure within GM. Ensuring Local Authorities have resource to aid with this programme will mitigate delivery challenges. There are currently legal issues relating to the procurement approach that authorities can use, these are being discussed with Office for Zero Emission Vehicles. Legal Considerations
In addition to the procurement issue referenced above, there are legal considerations relating to the underpinning MoUs (between TfGM and LAs) and commercial arrangements (between the LAs and CPO). Localised permissions and consents including planning agreements, leases and/or licences with regard to land, street works licences and host agreements will be progressed and managed by the relevant LA(s).
Financial Consequences – Revenue
Commercial arrangements to be agreed with charge point operators.
Financial Consequences – Capital
90% of Local Electric Vehicle Infrastructure Fund (LEVI) received . 10% held by OZEV pending agreement of procurement submission. Proposals for LA’s CRSTS allocations to LAs need finalisation.
Number of attachments to the report: None
Comments/recommendations from Overview & Scrutiny Committee
N/A
Background Papers GMCA March 2022, Item 24 Electric Vehicle Charging Tariff
GMCA March 2023 Item 28b Electric Vehicle Charging Infrastructure
BNC March 2024, Item 8, Capital Programme
Tracking/ Process Does this report relate to a major strategic decision, as set out in the GMCA Constitution?
No
Exemption from call in Are there any aspects in this report which means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency?
N/A
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Bee Network Committee at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.