That the contents of the paper be noted. 2. That endorsement be given to the development of a robust, evidence-based GM Rail Vision and programme for the future of rail across Greater Manchester in conjunction with GM Local Authorities; 3. That endorsement be given to the ambition and tranche-based approach to the integration of the 8 priority rail corridors in to the Bee Network Rail by 2028; 4. That endorsement be given to the development of an Outline Business Case for Rail Reform, to assess and develop a preferred way forward for meeting the objectives set out in this paper, and identify the legislative and funding reforms, required to deliver GM’s growth agenda; 5. That endorsement be given to the proactive engagement with Government in relation to the English Devolution and Rail Reform Bills, with particular regard to finalising the statutory role for the Combined Authority in the specification of services, fares and customer standards; 6. That endorsement be given to the development of further work to unlock the benefits of the Old Trafford Regeneration scheme through the relocation of the freight terminal at Trafford Depot; and 7. That endorsement be given to the development of the Spending Review submission, working with Government, to ensure the opportunities set out in this report are prioritised and delivered. 8. That concerns around access issues at stations such as Hattersley would be taken away and addressed appropriately. 9. That thanks be expressed to Nathanial Yates for his contributions to TfGM in working towards full accessibility at all rail stations. 10. That future updates on rail reform also include progress around the unlocking of land for homes.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
Bee Network Committee Date: Thursday 30th January 2025
Subject: GM Rail Reform and Devolution – The Vision and Delivery Programme for Rail in Greater Manchester
Report of: Steve Warrener, Managing Director, TfGM
Purpose of Report The purpose of this report is to provide an overview of the strategic context for rail reform, the case for change, the vision for GM Rail, and the outline programme of activity and milestones to deliver GM’s ambitions for rail as part of the Bee Network.
Recommendations Bee Network Committee is requested to note the contents of this paper; and endorse: • the development of a robust, evidence-based GM Rail Vision and programme for the future of rail across Greater Manchester in conjunction with GM Local Authorities; • the ambition and tranche based approach to the integration of the 8 priority rail corridors in to the Bee Network Rail by 2028; • the development of an Outline Business Case for Rail Reform, to assess and develop a preferred way forward for meeting the objectives set out in this paper, and identify the legislative and funding reforms, required to deliver GM’s growth agenda; • the proactive engagement with Government in relation to the English Devolution and Rail Reform Bills, with particular regard to finalising the statutory role for the Combined Authority in the specification of services, fares and customer standards; • the development of further work to unlock the benefits of the Old Trafford Regeneration scheme through the relocation of the freight terminal at Trafford Depot; and • the development of the Spending Review submission, working with Government, to ensure the opportunities set out in this report are prioritised and delivered. Contact Officers Martin Lax TfGM Transport Strategy Director [email removed]
Simon Elliott TfGM Head of Rail [email removed] Equalities Impact, Carbon and Sustainability Assessment: Not applicable at this stage. A detailed EQIA, Carbon and Sustainability assessment will be undertaken as part of the Rail Integration and Reform business case.
Risk Management Risks will be considered as detailed proposals and plans are further developed and considered. However, the opportunities afforded by rail reform and integration are set out within the report.
Legal Considerations Not specifically applicable at this stage but the TfGM Head of Legal is considering legal and legislative considerations with the GMCA Group Solicitor.
Financial Consequences – Revenue GM’s emerging Rail Reform and Integration proposition does not, at this stage, result in any material revenue (income and / or expenditure) implications. Current and subsequent year financial consequences are, at this stage, limited to development costs which will be managed within existing, and future year, budgets. Any subsequent revenue consequences will be detailed in future reports to GMCA.
Financial Consequences – Capital
The capital funding requirements to develop and deliver the emerging proposals for integrating an initial eight rail corridors (comprising 64 stations) into the bee Network by 2028 amount to c£114m in the period to FY 2028/29. The estimated expenditure in the period to March 2027 is £34m. The separate Transport Infrastructure Pipeline report on the agenda for this meeting requests approval for an allocation of £34m from CRSTS1 to support development and approval an indicative allocation of £80m from CRSTS2 to enable the full programme of works to be developed.
Number of attachments to the report: N/A
Background Papers • Rail Integration and Reform Programme: Emerging Rail Reform Policy Position and Next Steps report to GMCA, 27 th September 2024 • Transport Infrastructure Pipeline report to GMCA, 31 st January 2025 Tracking/ Process Does this report relate to a major strategic decision, as set out in the GMCA Constitution ?
No
Exemption from call in
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Bee Network Committee at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.