Resolved
That the current 2025/26 forecast of £652.9m compared to the 2025/26 budget of £598.3m be noted.
Greater Manchester Combined Authority noted this item on Friday 26 September 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
That the current 2025/26 forecast of £652.9m compared to the 2025/26 budget of £598.3m be noted.
An assessment of major budget risks faced by the Authority is carried out quarterly as part of the reporting process – at the present time a significant proportion of the capital budget is funded through grant. In order to mitigate the risk of monetary claw back the full programme is carefully monitored against the grant conditions and further action would be taken as necessary.
Legal Considerations
There are no specific legal implications contained within the report.
Financial Consequences – Revenue
There are no specific revenue considerations contained within the report.
Financial Consequences – Capital
The report sets out the forecast capital expenditure for 2025/26.
Number of attachments to the report: None
Background Papers GMCA Capital Programme 2024/25 - 2027/28 - GMCA 7 February 2025 meeting
Transport Infrastructure Pipeline - GMCA 31 January 2025 meeting
CRSTS Reprioritisation Strategy - GMCA 27 June 2025 meeting
Tracking/ Process Does this report relate to a major strategic decision, as set out in the GMCA Constitution?
No
Exemption from call in
Are there any aspects in this report which means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency?
No Bee Network Committee
N/A
Overview and Scrutiny Committee
N/A 1. Introduction/Background 1.1 The Greater Manchester Combined Authority approved the 2025/26 capital programme at its meeting on 7 February 2025. This report provides the first in a series of updates throughout 2025/26.
1.2The Authority’s capital programme funded from a number of sources and grants, includes Greater Manchester Fire and Rescue Services (GMFRS), Economic Development & Regeneration programmes, Waste & Resources Service and the continuation of the programme of activity currently being delivered by the Authority, Transport for Greater Manchester (TfGM) and GM Local Authorities (LA) including the following elements:
a) Metrolink schemes;
b) Rapid Transit schemes;
c) Rail schemes;
d) Interchange schemes;
e) Clean Air schemes;
f) Active Travel schemes;
g) Bus Infrastructure schemes;
h) Bus Franchising schemes;
i) Local Authority Highways schemes;
j) Other capital projects and programmes; and
k) Capital Highways Maintenance, Traffic Signals and Full Fibre.
1.3The 2025/26 Capital Programme is summarised in Appendix A and the major variances are described in this report.
2. Transport Schemes
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Budget Update: Quarter 1Report | 333 KB | DownloadRead as text |
Follow Greater Manchester Combined Authority at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Sep 2026 | ApologiesThat apologies be received from Councillor Eleanor Wills (Tameside), with Councillor Andrew Mclaren attending as subs... | Decided | Open |
| 25 Sep 2026 | Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities... | Decided | Open |
| 25 Sep 2026 | Declarations of InterestThat it be noted that no declarations of interest were received. | Noted | Open |
| 25 Sep 2026 | GMCA Minutes - 10 July 2026That the minutes of the GMCA meeting held on 10 July 2026 be approved. | Approved | Open |
| 25 Sep 2026 | Bee Network Committee - 25 June 2026That the proceedings of the Bee Network Committee held on 25 June 2026 be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.