CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Greater Manchester Combined Authority
Bee Network Committee, Thursday 24 September 2026

Transport and Net Zero

Noted Committee 1 paper

AI summaryGreater Manchester Bee Network Committee noted progress on the 2030 zero-emission transport target, including a proposed 15-year renewable energy deal and ongoing bus fleet electrification across the franchised network.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedEndorsed vPPA pathfinder and bus decarbonisation
Money15-year vPPA, price undisclosedCompared with £75/MWh current hedged rate
What happens nextSharston and Wythenshawe depots, 2027Contract award to VEV Services Ltd
Who it affectsBee Network buses and MetrolinkFranchised fleet and energy supply

What was decided

The Committee noted progress on the Greater Manchester Strategy 2025-2035 commitment to a greener city-region and the move towards a fully integrated, zero-emission public transport system by 2030.

Members noted the selection of a preferred supplier and the proposed signature of a 15-year Power Purchase Agreement to provide renewable energy at a level similar to Metrolink consumption for up to 20 years, acting as a pathfinder for future clean energy arrangements.

The Committee noted continued progress in decarbonising the Bee Network bus fleet through the franchised network, and that these measures support the 2038 carbon neutrality commitment.

Why

The vPPA operates as a contract for difference, securing TfGM a fixed electricity price regardless of market conditions and acting as a long-term hedge against price volatility. Report 3.1, P2, 3.3

The contractually secured strike price compares favourably to TfGM's current 26/27 hedged rate of £75/MWh, the Winter 2026 forwards of c£119/MWh and 2027/28 forwards of c£84/MWh. Report 3.2

TfGM is managing an ambitious bus decarbonisation programme aiming for a fully zero tail-pipe emission bus fleet by 2030, cutting over 76,000 tonnes of CO2 and 280 tonnes of NOx each year. Report 4.1, 4.2

What happens next

TfGM intends to award a contract to VEV Services Ltd to electrify other TfGM-owned bus depots, starting with Sharston and Wythenshawe in 2027, with a purpose-built electric depot planned in Stockport before the end of the decade.

Plans are in development to extend the trial of converting older diesel buses to zero emissions in Bolton, which may form part of the overall Fleet Strategy. Report 4.8

Subject to the success of this PPA pathfinder, TfGM intends to pursue further Power Purchase Agreements to meet growing electricity demand from an increasingly battery-electric bus fleet. Report 4.9

The money

  • £75/MWh TfGM current 26/27 average hedged electricity rate Report 3.2
  • c£119/MWh Winter 2026 electricity forwards Report 3.2
  • c £84/MWh 2027/28 electricity forwards Report 3.2

Implications

  • Financial: The vPPA is structured as a contract for difference, exposing TfGM to a fixed strike price but protecting it from short-term market volatility over a 15-year term. Report 3.1, P2, 3.2
  • Legal: External legal advice confirmed the vPPA is intra vires, as it is a prudent long-term hedge on operational energy requirements rather than a speculative or investment arrangement. Report 3.3
  • Climate: Full transition of the large franchise bus fleet to zero tail-pipe emissions by 2030 is expected to cut over 76,000 tonnes of CO2 and 280 tonnes of NOx each year. Report 4.1, 4.2
  • Other: The agreement is described as a pathfinder for future clean energy arrangements as electricity demand grows across the Bee Network. Report 4.9

Who and where

  • Greater Manchester bus passengers and Metrolink users Report 4.1
  • Franchised bus operators and TfGM Report 4.3, 4.4
  • Residents in areas near depots being electrified (Ashton, Bolton, Middleton, Oldham, Hyde Road, Sharston, Wythenshawe, Stockport) Report 4.4, 4.6

Timeline

  • May 2025: Ashton depot became the first fully electric bus depot in Greater Manchester Report 4.6
  • December 2025: Middleton depot became fully electric Report 4.6
  • End of this financial year: Almost 50% of the large franchise bus fleet expected to be electrified Report 4.5
  • 2027: Electrification of Sharston and Wythenshawe depots planned to commence, subject to contract finalisation with VEV Services Ltd
  • Before the end of the decade: Bee Network's first purpose-built fully electric bus depot planned for Stockport
  • By 2030: Target for a fully zero tail-pipe emission bus fleet and a fully integrated zero-emission public transport system Report 4.1
  • 15 years (PPA term): Proposed duration of the virtual Power Purchase Agreement with AGR Report 3.1
  • Up to 20 years: Period over which the renewable energy supply is to provide cover for demand similar to Metrolink
  • By 2038: Greater Manchester carbon neutrality commitment supported by these measures

Plain English for the jargon

  • vPPA (virtual Power Purchase Agreement): A financial contract for difference between a buyer and a renewable energy generator, fixing a strike price for electricity without the physical electricity changing hands.
  • Bee Network: Greater Manchester's integrated public transport network, covering buses, trams and other modes.
  • Franchising: The local-authority controlled bus model in Greater Manchester, under which TfGM sets routes, fares and standards and contracts operators to run services.
  • Strike price: The agreed price per megawatt-hour in the vPPA against which market prices are compared to determine payments between the parties.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

T hat the progress in delivering the Greater Manchester Strategy 2025–2035 commitment to a greener, fairer city-region, including the transition towards the UK’s first fully integrated, zero-emission public transport system by 2030 be noted; 2. That the selection of a preferred supplier and the proposed signature of a 15-year Power Purchase Agreement to provide renewable energy for a level of consumption similar to that of the Metrolink network for up to 20 years, acting as a pathfinder for future clean energy arrangements as electricity demand increases across the Bee Network be noted; 3. T hat the continued progress in decarbonising the Bee Network bus fleet through the franchised network be noted; and 4. That it be noted that the measures support Greater Manchester’s carbon neutrality commitment by 2038 and provide practical delivery of the Mayor’s Bee Network and net zero ambitions.
Word for word from the decision Greater Manchester Combined Authority published for this meeting. Source: democracy.greatermanchester-ca.gov.uk

Follow this further

Built from Greater Manchester Combined Authority's papers

What the report saysPro

Report to Bee Network Committee

Bee Network Committee Date: Thursday 24th September 2026

Subject: Transport and Net Zero

Report of: Steve Warrener, TfGM Managing Director

Purpose of Report To update on progress in delivering the Greater Manchester Strategy 2025–2035 commitment to a greener, fairer city-region through the transition towards the UK’s first fully integrated, zero-emission public transport system by 2030, including the use of long- term renewable energy to power Metrolink and progress in decarbonising the Bee Network bus fleet.

Recommendations: The Committee is requested to:

1. Note progress in delivering the Greater Manchester Strategy 2025–2035 commitment to a greener, fairer city-region, including the transition towards the UK’s first fully integrated, zero-emission public transport system by 2030; 2. Note the selection of a preferred supplier and the proposed signature of a 15-year Power Purchase Agreement to provide renewable energy for a level of consumption similar to that of the Metrolink network for up to 20 years, acting as a pathfinder for future clean energy arrangements as electricity demand increases across the Bee Network; 3. Note continued progress in decarbonising the Bee Network bus fleet through the franchised network; and 4. Note that these measures support Greater Manchester’s carbon neutrality commitment by 2038 and provide practical delivery of the Mayor’s Bee Network and net zero ambitions.

Contact Officers Frank Tudor, Commercial Services Director [email removed]

Rosalind O’Driscoll, Head of Policy and Public Affairs [email removed] Equalities Impact, Carbon and Sustainability Assessment: Impacts Questionnaire Impact Indicator Result Justification/Mitigation The proposals support delivery of a cleaner and more sustainable public transport network. Benef its are expected to be experienced by groups who are more reliant on public transport, including older people, disabled people and younger people, through impro ved air quality and continued investment in the Bee Network Af f ordable and reliable public transport is particularly important f or lower-income households and residents without access to a private vehicle. Continued investment in the Bee Network supports access to employment, education and services across Greater Manchester. A more resilient and sustainable public transport network helps Equality and Inclusion G residents access healthcare, education, employment and community f acilities across Greater Manchester. This report provides an update on programme delivery and does not introduce new mechanisms f or community participation in decision- making Improved public transport connectivity can support access to communities, employment and services, helping maintain social connectivity across Greater Manchester.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Transport and Net ZeroReport 318 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 15 attended
GM
GM Mayor Bev CraigChair, expected
CM
City Mayor Paul DennettCommittee Member, expected
GB
Councillor Grace BaynhamCommittee Member, expected
SH
Councillor Stephen HomerCommittee Member, expected
MW
Councillor Max WoodvineCo-Optee, expected
JB
Councillor Jon ByrneCo-Optee, expected
PC
Councillor Peter CrossenCo-Optee, expected
DV
Daniel VaughanCouncil Staff, expected
NR
Nick RobertsCouncil Staff, expected
NA
Councillor Nadeem AyubCommittee Member, expected
LS
Councillor Lucy SmithCommittee Member, expected
MS
Councillor Mandie Shilton GodwinCommittee Member, expected

All 15 on the meeting page

On this subject at Greater Manchester Combined Authority

Search all
  1. Transport and Net ZeroThis decision
  2. Transport & Net ZeroNoted
  3. Greater Manchester Transport Network PerformanceNoted
  4. The Bee Network - Improving Greater Manchester's Transport GovernanceApproved
  5. Transport Network Accessibility and InclusionNoted
  6. Transport Network PerformanceNoted

More from Greater Manchester Combined Authority Bee Network Committee

All decisions
MeetingDecisionOutcome
24 Sep 2026 ApologiesApologies were received and noted from Cllr Nazia Rehman (Wigan), City Mayor Paul Dennett (Salford), Cllr Stephen Hom... Noted Open
24 Sep 2026 Appointment UpdatesThat the update on the appointments made at the June meeting of the GMCA be noted. 2. That the appointments of the Ma... Noted Open
24 Sep 2026 Appointments to Outside BodiesThat the appointment of Cllr Barry Winstanley, Cllr Grace Baynham & Cllr Michael Welton to the Greater Manchester Acc... Noted Open
24 Sep 2026 Terms of Reference & Rules of ProcedureThat the terms of reference and rules of procedure be noted. Noted Open
24 Sep 2026 Declarations of InterestThere were none. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies