Resolved - 1. That the update on the Better Care Fund be noted. 2. That the Better Care Fund Steering Group and the Better Care Fund project boards be dissolved and made the Joint Commissioning Executive the Programme Board for the Better Care Fund. 3. That the Terms of Reference for the Joint Commissioning Executive be agreed and signed-off. 4. That the Health and Wellbeing Board were expected to sign off the section 75 agreement by the 30 July 2016 be noted and that the Board delegated sign-off to the Royal Borough of Greenwich’s Director of Health and Adult Services.
Word for word from the decision Greenwich published for this meeting.Source: committees.royalgreenwich.gov.uk
HEALTH AND WELLBEING BOARD DATE 18 July 2016 TITLE ITEM NO. Better Care Fund update 9 CHIEF OFFICER WARDS Director of Adults and Older Peoples’ Services All
1. Decision
The Health and Well Being Board is requested to:
1.1To note the update on the Better Care Fund (BCF).
1.2To agree to dissolve the Better Care Fund steering group and the Better Care Fund project boards and make the Joint Commissioning Executive (JCE) the Programme Board for the Better Care Fund.
1.3To agree and sign off the enclosed terms of reference for the Joint Commissioning Executive (JCE) – Appendix 1.
1.4To note that the Health and Wellbeing Board will be expected to sign off the section 75 agreement by the 30 July 2016.
2. Introduction
2.1The Joint Commissioning Executive (JCE) to date has been a board that has had strategic oversight of Adults and other commissioned services.
2.2KPMG as part of an internal audit reviewed the existing governance of the Better Care Fund (BCF) in May 2016. KPMG noted that between September 2015 and February 2016 no BCF steering groups took place and subsequently there was no reporting on BCF performance from the BCF project boards to the BCF steering groups and to the JCE.
2.3As a result of the KPMG report, the recommendation is to dissolve the BCF steering group and the BCF project boards and make the JCE the Programme Board for the BCF. This will provide leadership at a Programme Board level. Both the Directors from Royal Borough of Greenwich and Greenwich Clinical Commissioning Group (GCCG) attend and Co-Chair the JCE. The membership will also include the Chief Finance Officer from GCCG. This will address the recommendation from KPMG; ‘There is also a requirement to ensure ITEM NO: 9 PAGE NO: 1 there is accountability and ownership of the schemes at a senior level across both GCCG and RBG.’
2.4The JCE will move to monthly meetings to provide Programme Board Level oversight of schemes; this will enable reports to be received by exception where issues and risks to delivery against the metrics are raised. The draft terms of reference are attached (appendix 1). The JCE will provide updated reports both to the Greenwich Executive Group and the Health and Wellbeing Board (HWB).
3. Assurance to NHS England on the Better Care Fund
3.1An Interim Programme Manager for the BCF has been appointed and took up post on the 9 May 2016.
3.2The final assurance dates for the Narrative and the section 75 agreement have been highlighted below in the Timeline.
3.3Submission of the BCF Narrative on the 3 May 2016 received ‘Approved with support’ from NHS England (NHSE). The Regional final submission date of the 15 June was met. The aim is to achieve ‘Approved’ by the 30 June.
Timeline
ITEM NO: PAGE NO: 2 4. Section 75 Agreement
4.1ELS (Essex Legal Services) were commissioned in April 2016 By Greenwich Clinical Commissioning Group to review the section 75 agreement for 2015/16 with a view to provide; ‘A legal contractual arrangement is required for the management of a joint pooled fund, and also understand the terms and conditions with regards to risk associated with the pooled funding arrangements for all parties that are involved’,
4.2ELS provided a gap analysis checklist on 20 May 2016 which was reviewed at the JCE on 24 May 2016. ELS are tasked with redrafting the section 75 agreement for 2016/17.
4.3GCCG has been notified by ELS that they will provide a draft copy of the section 75 agreement by the first week in July. Following this the Royal Borough of Greenwich will require their legal team to review the revised document. Both the CCG and RBG understand that it is important to get the section 75 agreement right, as opposed to fast delivery.
4.4The original date of submission for the section 75 agreement outlined above was the 30 June; however NHS England has now moved this date to the 30 July 2016.
4.5The Health and Wellbeing Board will be expected to sign off the section 75 agreement by the 30 July 2016.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.