Noted the Treasury Management Outturn Report for 2023/24 (Sections 4-10) Noted the Capital Outturn Report for 2023/24 (Sections 11-14), which shows a substantial increase in investment from £177m in the previous year to £318m in 2023/24, which included; · £171m on the delivery of new homes via the Councils Greenwich Builds Programme: o £104m on the construction of new homes o £67m on the acquisition of new homes · £56m investment in existing Council homes. · £20m acquiring properties to meet Temporary Accommodation, Rough Sleeping and Refugee pressures. Noted the recommended additional allocation of £1.3m of approved contingency within the Priority Investment Programme, as a match funding contribution towards the £17.2m Future High Streets Fund programme (11.5-11.6). Noted that comments were sought from Cabinet (24 July 2024) and Audit and Risk Management Panel (22 July 2024) with respect to decisions 1.1 and 1.2.
Word for word from the decision Greenwich published for this meeting.Source: committees.royalgreenwich.gov.uk
FULL COUNCIL DATE ITEM NO 24 July 2024 14 TITLE WARD (S) Treasury Management and Capital All Outturn 2023-24 CHIEF OFFICER CABINET MEMBER Director of Finance Finance, Resources and Social Value DECISION CLASSIFICATION IS THE FINAL DECISION ON THE RECOMMENDATIONS IN Non-Key THIS REPORT TO BE MADE Non-Exempt from call-in AT THIS MEETING? Report – Non-Exempt Yes - Full Council 24 July 2024 Appendices – Non-Exempt (1.1,1.2 &1.4) No Cabinet - (1.3) 24 July 2024
1. Decision required This report makes the following recommendations to the decision-maker:
1.1To note the Treasury Management Outturn Report for 2023/24 (Sections 4-10) and comments from Cabinet and Audit & Risk Management Panel.
1.2To note the Capital Outturn Report for 2023/24 (Sections 11-14), which shows a substantial increase in investment from £177m in the previous year to £318m in 2023/24, which included; • £171m on the delivery of new homes via the Councils Greenwich Builds Programme: o £104m on the construction of new homes o £67m on the acquisition of new homes • £56m investment in existing Council homes. • £20m acquiring properties to meet Temporary Accommodation, Rough Sleeping and Refugee pressures.
ITEM NO. 14 PAGE NO: 1 And comments from Cabinet and Audit & Risk Management Panel.
1.3To note the recommended additional allocation of £1.3m of approved contingency within the Priority Investment Programme, as a match funding contribution towards the £17.2m Future High Streets Fund programme (11.5-11.6).
1.4To note that comments were sought from Cabinet (24 July 2024) and Audit and Risk Management Panel (22 July 2024) with respect to decisions 1.1 and 1.2.
2. Links to Our Greenwich missions 2.1 This report relates to the Council’s agreed missions as follows: • Our Council works in the most efficient and effective ways possible.
An effective Treasury Management function helps to facilitate the running of Council services and the safeguarding of the Council’s investments, whilst monitoring of the capital programme ensures resources are used efficiently, effectively and economically whilst delivering the Council’s strategic objectives across a diverse range of capital projects.
3. Purpose of Report and Executive Summary 3.1 The report comprises of two sections, Treasury Management Outturn 2023/24 and Capital Outturn 2023/24. Treasury Management
3.2This report summarises the Council’s treasury management activities during 2023/24, as required to ensure compliance with the Chartered Institute of Public Finance and Accountancy’s (CIPFA) Treasury Management code, which requires the Council to approve a treasury management annual report.
3.3The Council’s Treasury team ensures adequate liquidity for revenue and capital activities, security for investments and manages risk within all treasury management activities. Procedures and controls to achieve these objectives are well established both ITEM NO. 14 PAGE NO: 2 through member reporting, and through officer activity detailed in the Council’s Treasury Management Practices.
Capital Programme
3.4Section two of the report sets out the Capital outturn position for 2023/24 and forms part of the Corporate Capital Strategy governance framework.
4. Introduction and Background 4.1 This Treasury Management Outturn Report covers: Part 5 - Borrowing Position as at 31 March 2024 Part 6 – Borrowing Strategy for 2023/24 Part 7 – Debt Rescheduling Part 8 – Investment Rates in 2023/24 Part 9 – Investment Outturn for 2023/24 Part 10 – Compliance with Treasury Limits 5 Borrowing Position as at 31 March 2024
5.1The Council’s treasury position at 31 March 2024 is presented in Table 1 below and shows £67m of additional borrowing from Public Works Loans Board (PWLB) and a repayment of £23.518m on historical debt. Table 1 – Treasury Position as at 31/03/24 (comparator as at 31/03/23) Position Principal £m Rate 5 % Maturity 6 (yrs) 23/24 22/23 23/24 22/23 23/24 22/23 PWLB 1 340.907 280.817 4.15 4.07 Banks (Fixed) 2 52.500 52.500 4.11 4.11 Banks (LOBO`s) 3 60.500 76.500 4.23 4.23
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.