Noted Finance 2 papers

AI summaryRoyal Greenwich's Audit and Risk Management Panel noted the status of its action log, with most items completed. One item, fraud training awareness, remains in progress pending a development plan report to this meeting.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedStatus of all actions in Appendix 1 recorded
MoneyNot stated
What happens nextFraud training plan reportDue at 21 January 2026 meeting
Who it affectsInternal Audit and council servicesFleet, Housing, Digital and other departments

What was decided

The Panel noted the current status of actions set out in Appendix 1.

Why

The action log is a standing item used to track completion of actions agreed at previous Panel meetings. Report P1

What happens next

A report on the development plan for Internal Audit and Anti-Fraud, covering fraud training awareness, was due at the 21 January 2026 meeting and the item remains in progress. Report P2

All other items in the log are recorded as completed, with responses sent to Members and trendlines to be included in future performance reporting. Report P1, P24

Implications

  • Risk: Internal Audit commissioned advisory work on cyber security through a cross-council framework, and progress will be reported in the internal audit service performance report. Report P9
  • Other: A final Internal Audit report on the Carbon Neutral Plan was issued in January 2025 with a Moderate assurance level; the risk remains under review as part of the usual audit cycle. Report P11
  • Other: A follow-up on No Recourse to Public Funds found 12 of 17 recommendations addressed, with a further follow-up scheduled for 2025/26. Report P23

Who and where

  • Members of the Panel receiving responses and updates by email Report P2, P3, P4, P5, P6, P7, P8, P10, P14, P24
  • Fleet and Repairs staff subject to vehicle mileage and usage checks Report P15, P16
  • Officers in Housing, Financial Governance, Procurement and Digital services named as responsible parties Report P2, P3, P6, P9, P16, P23

Timeline

  • 05 September 2023: Final report of the latest full No Recourse to Public Funds review Report P23
  • 30 October 2024: Follow-up exercise completed on No Recourse to Public Funds audit recommendations Report P23
  • January 2025: Final Internal Audit report issued on the Carbon Neutral Plan Report P11
  • 03.09.2025: Digital team presentation to the Panel on cyber risk preparations Report P9
  • 21st January 2026: ARM Panel meeting at which the action log status was noted Report P2

Plain English for the jargon

  • ARM Panel: Audit and Risk Management Panel
  • NRPF: No Recourse to Public Funds
  • RTB: Right to Buy
  • CORPGMT 07: Cross Council Assurance Risk Register reference for Cyber Security and Data Breaches
  • CTS/HB: Council Tax Support and Housing Benefit
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

Resolved – That the current status of actions, as set out in Appendix 1, be noted.
Word for word from the decision Greenwich published for this meeting. Source: committees.royalgreenwich.gov.uk

Follow this further

Built from Greenwich's papers

What the report saysPro

Report to Audit and Risk Management Panel

Meeting Report Item (action No.): Financial Year Responsible Party Update (Target Date) Status Date Agreed Action(s)

Item 6 Members expressed concern about the current provision This will incorporated as part of the development plan 2025/26 of fraud training in that were grey areas and staff might not be Director of Resourcesfor Internal Audit and Anti Fraud outlined in a report to In progress the 21st January 2026 ARM Panel meeting. aware something was fraud and not know to report it. Digital and Customer Item 6 (restricted) Response emailed to Members Completed Services

We can add the list to the performance report. As each performance report Item 7 is by Directorate, we will provide the Direct Awards for that specific Consideration to be given as to whether a list of Direct Awards Head of Procurement Directorate each time. It will just be the list though, not a comprehensive Completed could be attached to the new annual report on contract review. Members can then look at the list and decide if they would like 2025/26 03-Sep-25 performance going to Scrutiny further information which we can then provide. Item 10 Head of Financial Clarification to be provided as to details of “non-audit” work Governance, Insurance & Response emailed to Members Completed

undertaken (bar chart, section 4.9) Risk Item 11 Scrutiny / Committee Link or date to be sent on when Scrutiny next takes report on Response emailed to Members Completed Services workforce (Human Resources Performance)

Item 5 (1) Head of Financial Governance, Response emailed to Members Completed Granularity required on low client satisfaction scores Insurance & Risk

Head of Financial Governance, Item 5 (2) Insurance & Risk / Assistant 2025/26 ######### At a future date Housing to return to Panel to update about RTB Response emailed to Members Completed Director for Housing Needs fraud and Tenancy

Item 6 Accountancy Business Change Data to be provided on spread of numbers buying the Green Bond Response emailed to Members Completed Manager in each round

Item 7 (6) Head of Financial Governance, To provide feedback on Bromley’s client satisfaction with Satisfaction survey emailed to Members Completed Insurance & Risk Greenwich’s provision of a fraud investigation service Meeting Report Item (action No.): Financial Year Responsible Party Update (Target Date) Status Date Agreed Action(s)

Digital team presenting to Panel during the 03.09.2025 meeting. In addition, Item 8 (9) working with external partners (PwC) via the Cross Council Assurance Risk Register - CORPGMT 07 - Cyber Security & Data Breaches Head of Financial Governance, framework, internal audit has commissioned an audit advisory work. In the When was it last reviewed? Is it now a greater risk? Completed Insurance & Risk usual way, progress on this advisory work will be reported as part of the Suggestion was could they have a presentation from Digital on internal audit service performance report. preparations for risk of successful cyber attack on Greenwich

Item 10 (11) Additional information emailed to Members Forvis Mazars to share their quality control review scores with Forvis Mazars Completed 2025/26 ########### Members

Item 8 (7) Internal Audit issued a final report on the Carbon Neutral Plan – Monitoring Head of Financial Governance, Officers to consider if there is a role for audit reviewing the in January 2025. The overall assurance level was Moderate. The risk remains Completed Insurance & Risk progress of Carbon Neutral in meeting its target under review as part of the usual audit cycle.

Item 8 (8) Head of Financial Governance, The risk remains under review as part of the usual audit cycle. Completed Will there be any audit consideration of the ‘Green Bond’ Insurance & Risk

Item 9 (10) Head of Financial Governance, Training scheduled to be provided at July Panel meeting Completed Could Members be given online training on the Charter Insurance & Risk

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ARM Panel: Action LogReport 123 KB DownloadRead as text
PDF
Action LogReport 55 KB Download

At this meeting

Whole meeting

Who was there

7 of 12 attended
DG
Councillor David GardnerChair, present
SB
Dr Susan BlackallVice-Chair, present
CM
Councillor Christine MayCommittee Member, present
‘H
Councillor ‘Lade Hephzibah OlugbemiCommittee Member, present
DS
Councillor Dave SullivanCommittee Member, present
NW
Councillor Nick WilliamsCommittee Member, present
MH
Councillor Matt HartleyCommittee Member, apologies
TT
Thomas TysonCommittee Member, present
CM
Cabinet Member Finance, Resources and Social ValueGuest, in attendance
DO
Director of ResourcesOfficer, in attendance
IA
Interim Assistant Director of Finance & Deputy s151 OfficerOfficer, in attendance
IC
Integrated Commissioning Director for Adult ServicesOfficer, in attendance

On this subject at Greenwich

Search all
  1. Action LogThis decision
  2. Action LogNoted
  3. Action LogNoted
  4. Action LogNoted

More from Greenwich Audit and Risk Management Panel

All decisions
MeetingDecisionOutcome
24 Jun 2026 Declarations of InterestResolved - That the list of Councillors’ memberships as Council appointed representatives on outside bodies, joint co... Noted Open
24 Jun 2026 Audit & Risk Management Panel Terms of Reference and Draft Work Programme 2026/27Resolved – 1. That the Terms of Reference for the Audit & Risk Management Panel at Appendix A of the report be noted ... Noted Open
24 Jun 2026 Action LogResolved – That the current status of actions, as set out in Appendix 1 of the report, be noted. Noted Open
24 Jun 2026 Internal Audit Plan 2026/27Resolved – That the Internal Audit Plan 2026/27 be noted and approved Noted Open
24 Jun 2026 Head of Audit Annual Report 2025/26Resolved – 1. That the Head of Audit annual report for the year 2025/26 be noted 2. That the Anti-Fraud Service perfo... Noted Open