Woodlands Heights, Vanbrugh Hill, Blackheath, London, SE3 7EL - Ref: 25/1700/F
DecidedPlanning3 papers
AI summaryGreenwich planning committee grants full planning permission for an extra floor at Woodlands Heights, Vanbrugh Hill, with eight new flats and changes to the construction management plan.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedExtension to existing 5-storey building
MoneyNo specific sum statedCommunity Infrastructure Levy may apply
What happens nextConditions to be dischargedDevelopment to begin within 3 years
Who it affectsConservation area settingsWestcombe Park and Greenwich Park
What was decided
Full planning permission granted for an additional floor of 2 two-bedroom and 6 one-bedroom flats, with cycle and waste storage, new loading bays, pedestrian access and landscaping. Report P5, P6
Condition 4 amended so the Construction Management Plan must include specific details on scaffolding to avoid blocking access and must locate staff welfare facilities, including portaloos, away from existing homes.
Assistant Director (Planning and Building Control) authorised to make minor changes to the wording of recommended conditions before issuing the decision notice.
Why
The scheme was assessed against the National Planning Policy Framework, the London Plan 2021 and the Royal Greenwich Local Plan Core Strategy 2014, together with relevant supplementary planning guidance. Report P66, P67, P68, P69, P70, P71, P72, P73, P74
Conditions address design quality, construction impacts on neighbours, tree protection, ecology, biodiversity net gain, sustainable transport, water use, air quality, cycle parking, waste, replacement planting, deliveries and fire safety. Report P8, P9, P15, P18, P21, P30, P36, P41, P44, P45, P46, P48, P50, P53, P56
What happens next
Development must begin within three years of the date permission is granted, under section 91 of the Town and Country Planning Act 1990. Report P5
Before starting, the applicant must submit and gain approval for a Construction Management Plan, Tree Protection Plan, bat survey results and a Biodiversity Gain Plan. Report P9, P15, P21, P30, P31
Before first occupation, the applicant must deliver a Habitat Management and Monitoring Plan, agreed cycle parking, waste bins, replacement trees, bird boxes, bat boxes, a Traffic Order amendment preventing residents' parking permits, and a Delivery and Servicing Plan. Report P24, P27, P36, P41, P46, P48, P50, P53
Options considered
Chosen: Grant full planning permission with amended Condition 4
Rejected: Refuse planning permission. Not set out in the supplied papers
Implications
Legal: Permission granted under planning controls with 19 conditions and 6 informatives, including the three-year time limit under section 91 of the Town and Country Planning Act 1990. Report P5, P58, P59, P60, P61, P62, P63, P64
Equalities: Inclusive design is required under London Plan Policy D5 and the applicant is advised to consider additional sprinkler systems and security devices raised by the Health and Safety Executive. Report P64, P69
Climate: Boilers must have dry NOx emissions not exceeding 40 mg/kWh (0%) and new homes must meet Building Regulations Part G2 water efficiency of 105 litres per person per day. Report P44, P45
Environment and climate: A Biodiversity Gain Plan and 30-year Habitat Management and Monitoring Plan are required to deliver a minimum 10% Biodiversity Net Gain, supported by bat and bird boxes. Report P21, P24, P27, P30, P35, P36, P39
Risk: Construction must safeguard neighbouring residents from dust, noise and vibration, and the site must be assessed for built-over gas mains before any digging or building work. Report P9, P12, P59, P60
Who and where
Existing residents of the 5-storey Woodlands Heights building and neighbouring homes on Vanbrugh Hill Report P9, P12
Future residents of the 8 new flats Report P41
Westcombe Park and Greenwich Park Conservation Areas, whose settings may be affected Report P74
Surrounding public highway users and the Council's Transport and Highways Department Report P10, P41
Bats and birds using the site, with survey and mitigation required Report P21, P27
Timeline
Within 3 years of the date permission is granted: Development must be begun Report P5
Before commencement of the development: Construction Management Plan, Tree Protection Plan, bat survey results and Biodiversity Gain Plan must be submitted and approved Report P9, P15, P21, P30
Before first occupation: Cycle parking, waste bins, replacement trees, bird and bat boxes, Habitat Management and Monitoring Plan, Traffic Order amendment and Delivery and Servicing Plan must be in place Report P24, P27, P36, P41, P46, P48, P50, P53
For 30 years from completion of the development: Created or enhanced habitat must be managed and monitored under the approved Habitat Management and Monitoring Plan Report P36, P38
For 5 years from first occupation of the new dwellings: Any replacement tree that dies must be replaced with a similar species at the developer's expense within 6 months Report P51
Plain English for the jargon
BNG: Biodiversity Net Gain, a measurable improvement in biodiversity for a development
CMP: Construction Management Plan, setting out how demolition and construction impacts will be controlled
CIL: Community Infrastructure Levy, a charge that some developments must pay to fund local infrastructure
EPSL: European Protected Species Licence, needed before works can start if bat roosts are confirmed
HMMP: Habitat Management and Monitoring Plan, setting out long-term care of created or enhanced habitat
LCDS: London Cycle Design Standards, the design standards for cycle parking and facilities in London
TPP: Tree Protection Plan, showing how trees will be protected during building works
TCPA 1990: Town and Country Planning Act 1990, the main law governing planning decisions in England
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5
Resolved
Resolved that full planning permission be granted for the extension to existing 5-storey building to provide an additional floor of residential floorspace comprising of 2 x 2 bedroom and 6 x 1 bedroom units with respective private amenity spaces, provision of additional cycle and waste storage, new loading bays, new pedestrian access from Vanbrugh Hill, associated landscaping and tree removal, and all associated works. (This application may affect the setting of the Westcombe Park and Greenwich Park Conservation Areas). That consent be granted with the amendment to Condition 4, that the Construction Management Plan include specific details in relation to scaffolding so as to not block access and site staff welfare facilities, including portoloos, be located away from existing residential homes. That the Assistant Director (Planning & Building Control) is authorised to make any minor changes to the detailed wording of the recommended conditions as set out at Appendix 2 of the report, where the Assistant Director (Planning & Building Control) considers it appropriate, before issuing the decision notice.
Word for word from the decision Greenwich published for this meeting.Source: committees.royalgreenwich.gov.uk
Condition 1 The development to which this permission relates must be begun not later than the expiration of three (3) years beginning with the date on which the permission is granted. Reason: As required by Section 91 of the Town and Country Planning Act 1990.
Condition 2 The development shall be carried out strictly in accordance with the application plans, drawings and documents hereby approved and as detailed below: 000WO-A-01-001, 000WO-A-01-002, 000WO-A-02-001, 000WO-A-02-002, 000WO-A-03-001, 000WO-A-03-002, 000WO-A-03-003, 000WO-A-03-004, 000WO-A-03-005, 000WO-A-03-006, 000WO-A-03-007, 000WO-A-03-008, 000WO-A-05-001, 000WO-A-05-002, 000WO-A-06-001, 000WO-A-06-002, 000WO-A-06-003, 000WO-A-06-004, 000WO-A-01-001 Rev 1 [Proposed Location Plan], 000WO-A-01-003 Rev 2, 000WO-A-02-101 Rev 1, 000WO-A- 02-102 Rev 1, 000WO-A-02-103, 000WO-A-03-101 Rev 1, 000WO-A-03-102 Rev 1, 000WO-A-03-103 Rev 1, 000WO-A-03-104 Rev 1, 000WO-A-03-105 Rev 1, 000WO-A-03-106 Rev 1, 000WO-A-03-107 Rev 1, 000WO-A-05-101 Rev 1, 000WO-A-05-102, 000WO-A-05-103 Rev 1, 000WO-A-06-101, 000WO-A-06-102 Rev 1, 000WO-A-06-103 Rev 1, 000WO-A-06-104 Rev 1, WOO/VAN/25/010 Rev3, “Arboricultural Impact Assessment Method Statement & Tree Protection Plan” (dated 19/11/2024), Biodiversity Net Gain Assessment (dated 21/04/2025), BNG Metric, Outline Construction Management and Logistics Plan (dated 15/01/2025), Daylight/ Sunlight Assessment (dated 21/11/2024), Fire Statement Form (dated 02/05/2025), Planning Fire Safety Statement (Rev. 1, dated 02/05/2025), “Planning, Design and Access Statement” [Revised], “Preliminary Ecological Appraisal and Roost Assessment” (dated 21/11/2025), Transport Statement (dated April 2025)
ITEM NO: 6 ITEM NO: 5 - Appended appendices PAGE NO: 2 Appendices Reason: In the interests of good planning and to ensure that the development is carried out in accordance with the approved documents, plans and drawings submitted with the application and is acceptable to the local planning authority.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.