Rethinking the Riverside - Response to Scrutiny recommendations following the review of the Thames Path

Noted Executive 1 paper

AI summaryGreenwich Cabinet agrees to develop a new Thames Path and Riverfront Strategy, with a budget envelope of up to £140,000, in response to scrutiny review recommendations.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet agreed to bring forward a new Thames Path and Riverfront Strategy
MoneyUp to £140,000One-off funding to develop the strategy, including specialist input
What happens nextDevelop new strategyStrategy will incorporate scrutiny review findings and officer responses
Who it affectsThames Path users and residentsParticularly disabled people, older residents, and carers

What was decided

Cabinet noted the officer responses to the recommendations of the Thames Path Connectivity and Upgrade Review.

Cabinet agreed to bring forward a new Thames Path and Riverfront Strategy, incorporating the review's findings and the responses to its recommendations. Report 8.1

Cabinet agreed a budget envelope of up to £140,000 to deliver the strategy. Report P9, P12

Why

The scrutiny recommendations are wide-ranging and cross-cutting, with some carrying significant financial implications, so a dedicated strategy is needed to formulate a fully considered, prioritised and funded response. Report 8.1

A strategy will provide a structured framework to ensure the Thames Path is safeguarded, enhanced and sustainably managed as an important asset for the borough. Report 8.1

What happens next

The Cabinet decision will be reported back to the Overview and Scrutiny Committee, and the agreed responses will be implemented. Report 10.1, P4

The £140,000 cost of preparing the strategy will be met from one-off funding, supplemented by existing departmental resources for coordination. Report P12

Any future decisions on implementing the strategy or specific projects arising from it will require separate legal advice and will be identified as part of the annual budget development. Report P10, P13

The money

  • up to £140,000 Budget envelope to deliver the new Thames Path and Riverfront Strategy, including specialist input and evidence base data gathering Report P9, P12

Options considered

  • Chosen: Agree to develop a new multi-year Thames Path and Riverfront Strategy with a budget envelope of up to £140,000. Recommendations are wide-ranging and cross-cutting, with significant financial implications requiring a structured, prioritised response. Report 8.1, P9, P12

Implications

  • Financial: Agreeing to develop the strategy does not commit the council to any revenue or capital expenditure beyond the initial development work; future recommendations may have material financial implications for the council and developers. Report P11
  • Legal: The report is submitted to Cabinet in accordance with the Council's constitution, Part 4 B5, following Overview and Scrutiny Committee deliberations. Report P8
  • Equalities: If implemented, the recommendations could have a positive and differential impact on disabled people, older residents, and carers by improving accessibility, safety, and inclusion along the Thames Path; Cabinet is advised to have due regard to the Public Sector Equality Duty under s149 of the Equality Act 2010. Report P14
  • Climate: The strategy contributes to the Greenwich Carbon Neutral Plan, promotes active travel and modal shift from car use, increases tree canopy cover, enhances biodiversity, and explores floodable public realm design for tidal risk. Report P16, P17, P19
  • Risk: Key risks have been considered and detailed; these will continue to be monitored and managed in line with the Council's risk management toolkit. Report P20

Who and where

  • Residents and visitors using the Thames Path in the borough Report 8.1
  • Disabled residents, older residents, and carers, who could benefit from improved accessibility, safety and inclusion Report P14
  • Community organisations including Metro GAD, Advocacy in Greenwich, and local heritage and environmental groups Report P22
  • Developers, as some recommendations may have financial implications for them Report P11

Timeline

  • November 2020: Greenwich Carbon Neutral Plan agreed by Cabinet Report P16
  • 2024-25: Scrutiny work programme during which the Thames Path Connectivity and Upgrade Review was commissioned Report P7
  • 24 July 2024: Date of the Community Engagement Pledge underpinning the review's engagement activities Report P21
  • 27/02/2026: Sign-off dates by Head of Legal Services and Accountancy Business Change Manager Report P7, P11

Plain English for the jargon

  • Section 106: Planning obligation under which developers contribute to infrastructure or community needs
  • CIL: Community Infrastructure Levy, a charge on development to fund infrastructure
  • Public Sector Equality Duty: Duty under s149 of the Equality Act 2010 requiring public bodies to consider how decisions affect people with protected characteristics
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

Noted the responses made by officers in relation to the recommendations of the Thames Path Connectivity and Upgrade Review. Agreed to bring forward a new Thames Path and Riverfront Strategy (as per recommendation 26 of the Review) which will incorporate the finding of the review and the responses to the recommendations found in this report. Agreed a budget envelope of up to £140,000 to deliver the strategy.
Word for word from the decision Greenwich published for this meeting. Source: committees.royalgreenwich.gov.uk

Follow this further

Built from Greenwich's papers

What the report saysPro

Report to Cabinet

CABINET DATE ITEM NO 18 March 2026 13 TITLE WARD (S) Rethinking the Riverside – Response to All Scrutiny recommendations following the review of the Thames Path CHIEF OFFICER CABINET MEMBER Interim Director for Place and Growth Leader of the Council (Planning, Estate Renewal and Development) DECISION CLASSIFICATION IS THE FINAL DECISION ON THE RECOMMENDATIONS Non-Key IN THIS REPORT TO BE Not exempt MADE AT THIS MEETING?

Yes

1. Decision required

This report makes the following recommendations to the decision-maker:

1.1To note the responses made by officers in relation to the recommendations of the Thames Path Connectivity and Upgrade Review.

1.2To agree to bring forward a new Thames Path and Riverfront Strategy (as per recommendation 26 of the Review) which will incorporate the finding of the review and the responses to the recommendations found in this report.

1.3To agree a budget envelope of up to £140,000 to deliver the strategy.

2. Links to Our Greenwich missions

2.1This report relates to the Council’s agreed missions as follows:

• Mission 1: People’s health supports them in living their best life The Thames Path is a vital green corridor that promotes physical activity, mental wellbeing, and access to nature. The review highlights how improved lighting, surfacing, and accessibility can make the path safer and more inclusive for all users, including older residents, disabled

ITEM NO: 13 PAGE NO: 1 people, and families, thereby supporting healthier lifestyles across the borough.

• Mission 7: It is easier, safer and greener to move around the borough and the rest of London The Thames Path is a key active travel route, forming part of the National Trail and National Cycle Network. The review identifies barriers to movement such as inconsistent surfacing, poor signage, and fragmented access, and recommends strategic upgrades to improve connectivity, safety, and wayfinding. These changes will make walking and cycling along the river a more viable and attractive option for residents and visitors.

• Mission 8: Development delivers positive change to an area for existing and new communities The review recognises the Thames Path as a catalyst for inclusive regeneration. It recommends embedding the path into planning policy and ensuring new riverside developments contribute to public access, biodiversity, and placemaking. By doing so, the path can become a shared asset that reflects local identity, supports economic growth, and enhances the public realm for all communities along the river.

3. Purpose of Report and Executive Summary

3.1This report presents Officers’ response to the recommendations of the Thames Path Connectivity and Upgrade Review, a scrutiny-led investigation commissioned by the Overview and Scrutiny Committee as part of its 2024–25 work programme. The review was initiated in response to the strategic importance of the Thames Path as a key piece of green and active travel infrastructure, and its potential to support regeneration, climate resilience, and inclusive access across the Royal Borough of Greenwich.

3.2The review was chaired by Councillor Maisie Richards Cottell, Chair of the Transport and Place Scrutiny Panel, and brought together a group of councillors representing riverfront and adjacent wards. The group worked in collaboration with academic experts, council officers, community organisations, and external stakeholders to assess the current condition of the Thames Path and identify opportunities for improvement.

ITEM NO: 13 PAGE NO: 2 3.3 The resulting report sets out a bold and evidence-based vision for the Thames Path, structured around five core themes: Experience, Enhancement, Engagement, Economy, and Strategic Delivery. It proposes a comprehensive set of recommendations to improve accessibility, safety, biodiversity, community involvement, and economic activation along the riverfront.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Rethinking the Riverside: Response to Scrutiny recommendations following the review of the Thames PathReport 191 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 19 attended
AO
Councillor Anthony OkerekeChair, present
AL
Councillor Averil LekauCommittee Member, present
SB
Councillor Sandra BauerCommittee Member, present
DH
Councillor Denise HylandCommittee Member, present
AK
Councillor Adel KhairehCommittee Member, apologies
ML
Councillor Mariam LolavarCommittee Member, apologies
CO
Councillor Calum O'Byrne MulliganCommittee Member, present
PS
Councillor Pat SlatteryCommittee Member, present
JS
Councillor Jackie SmithCommittee Member, present
RT
Councillor Rachel Taggart-RyanCommittee Member, present
CE
Chief ExecutiveOfficer, in attendance
DO
Director of ResourcesOfficer, in attendance

All 19 on the meeting page

More from Greenwich Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Royal Greenwich Safeguarding Adults Board Annual Report 2025-26Noted the 2025/26 Royal Greenwich Safeguarding Adults Board Annual Report Noted Open
23 Sep 2026 Private Housing Enforcement Policy 2026 to 2029Agreed to adopt the amended Private Sector Housing Enforcement Policy in Appendix 1 including the revised schedule of... Agreed Open
23 Sep 2026 Approval to publish the Local Flood Risk Management StrategyApproved the publication of the completed Greenwich’s Local Flood Risk Management Strategy (LFRMS). Approved Open
23 Sep 2026 2025/26 OutturnNoted the Council’s revenue outturn position for 2025/26 as at the end of March 2026 Noted Open
23 Sep 2026 Draft Statement of Accounts 2025/26Considered the authority’s draft Statement of Accounts for the year ended 31 March 2026 (including the Pension Fund A... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies