Resolved
That information regarding the shorter-term marketing strategy relating to the Spectrum roof replacement project be provided to Committee members.
Corporate Improvement Scrutiny Committee decided this item on Thursday 12 November 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That information regarding the shorter-term marketing strategy relating to the Spectrum roof replacement project be provided to Committee members.
The Council entered into a 10 year Leisure Partnership Agreement (LPA) with Greenwich Leisure Ltd (GLL) with effect from 1 November 2011, to deliver leisure services throughout the borough at Guildford Spectrum, Guildford Lido and Ash Manor Sports Centre. GLL has sub-contracted elements of the service to Wealden Leisure Limited trading as Freedom Leisure (FL).
A very detailed and complex contractual agreement, the Leisure Partnership Agreement (LPA), is in place between GLL and the Council. GLL and FL have a contractual agreement that mirrors the contents of the LPA.
The LPA is a substantial document which includes as one of its component elements a detailed service specification specific to each site covering all aspects of service delivery e.g. opening and closing hours, water and air temperatures, maintenance regimes, health and safety compliance requirements, staffing levels and qualifications. It also sets out the objectives for the service provision.
This report reviews the fourth contract period from 1 April 2014 to 31 March 2015. The performance of the contractor has been monitored across the sites over a number of criteria. Operationally the performance of the contractor has been acceptable during the period.
In respect of specific performance measures, FL is on target with the majority of the measures. There are some changes to the methods of measurement of customer complaints and as such these cannot be directly compared against previous periods. These changes have been made to drive improvements in customer satisfaction. FL made a shortfall of £307,701 against their management fee bid for the period. This shortfall does not affect the Council’s payment from FL, but it does mean there is no additional payment to be made to the Council. The phasing of projects is always a challenge in such a busy building and there have been some delays with the projects due to this. Phase one of the Spectrum steelwork repairs is now complete and resolved the columns and other structural steelwork that had suffered the most corrosion in the Pools Hall. A report on phase two and phase three of the steel repairs and the replacement Spectrum roof programme and other maintenance work is being prepared for the November committee cycle.
A project to replace the existing Combined Heat and Power (CHP) engine, which uses gas to generate heat and electricity, is also underway.
Recommendation to Committee:
The Committee is asked to consider:-
(1) whether, in light of the report, it wishes to comment on the performance of the leisure operator; (2) whether, in the light of the report, it wishes to make any comments relating to the focus of the service objectives referred to in paragraph 3.10; (3) whether it wishes to set up a task group to look at the template for the annual report; and (4) whether any of the issues raised in the operator’s annual report (Appendix 2) give cause for concern or particular comment.
Reasons for Recommendation: (1) The available supporting evidence indicates Freedom Leisure is largely meeting the expectations within the Leisure Partnership Agreement. (2) The service objectives must be considered annually to ensure they remain consistent with the Council’s objectives and priorities.
1.1To provide an overview of performance of the leisure contractor operating Guildford Spectrum, Guildford Lido and Ash Manor Sports Centre for the contract year period 1 April 2014 to 31 March 2015.
1.2To provide councillors with an opportunity to comment on the current and future service provision and/or the monitoring arrangements for the contract.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Item 04 (1): Leisure Management Contract: App 1 -Appendix | 101 KB | Download |
PDF |
Item 04 (2): Leisure Management Contract: App 2Appendix | 2.4 MB | Download |
PDF |
Item 04 (3): Leisure Management Contract Scrutiny: App 3Appendix | 41 KB | Download |
PDF |
Operation of Leisure Management Contract 2014-15Report | 188 KB | DownloadRead as text |
Follow Corporate Improvement Scrutiny Committee at Guildford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Nov 2015 | Promoting Social EnterpriseThat the progress in developing social enterprise projects in Guildford be welcomed . | Decided | Open |
| 12 Nov 2015 | Overview and Scrutiny Work ProgrammeRESOLVED to approve the work programme as outlined in the report. | Approved | Open |
| 15 Sep 2015 | Burpham Neighbourhood PlanTo recommend to full Council that officers be authorised to make the modifications to the as specified in the report ... | Decided | Open |
| 15 Sep 2015 | Work programmeRESOLVED to approve the work programme as outlined in the report. | Approved | Open |
| 25 Jun 2015 | Asset Review: Farms, farmland, allotments and fishingRESOLVED to endorse the outcome of the asset review programme following completion of the review of farms, farmland, ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.