Resolved
That the audit plan for 2018-19 as set out in Appendix 1 to the report submitted to the Committee be approved . Reason: To ensure an adequate level of audit coverage.
Corporate Governance and Standards Committee (up to May 2025) approved this item on Thursday 14 June 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That the audit plan for 2018-19 as set out in Appendix 1 to the report submitted to the Committee be approved . Reason: To ensure an adequate level of audit coverage.
1.1To present the draft audit plan for 2018-19. This report also gives an update on the changes for the delivery of the audit plan in 2018-19.
2. Strategic Priorities
2.1The audit of Council services supports the priority of providing efficient, cost effective and relevant quality public services that give the community value for money.
3.1Internal Audit is a statutory function. Under S.151 of the Local Government Act 1972, councils are required to have a current Internal Audit function. However, the Act does not specify how Internal Audit should be provided. Over the last few years, Internal Audit has been delivered through a mixed service provision with internal resources supported by an external contractor.
3.2For the last 18 months there has been real pressures on the Internal Audit team because of the long-term absence of a senior auditor and the retirement during the year of the another senior member of staff. Our attempts to cover the vacancies with either, agency or permanent staff were unsuccessful because of the suitability of the candidates or the inability to match London Authority or private sector salaries. 3.3. As a result, we became increasingly reliant on our contractor to deliver the work in the audit plan and this provided an opportunity to consider alternative delivery models, which would provide a more sustainable internal audit solution for the future.
3.4Following an internal review we decided to outsource the internal audit function with effect from 1 April 2018. A contractor will now be responsible for completing the Audit Plan over the coming year. The Audit and Business Improvement Manager will act as the client-side officer.
3.5The Council is fortunate in that the Business Improvement Team includes staff with Internal Audit experience including an officer who has 10 years audit experience and a trainee who is doing both audit and change management professional qualifications. Therefore, the new structure will have multi-skilled staff with both audit and business improvement experience within the same team. The proposed structure will produce year on year savings of approximately £90,000 for a similar level of audit coverage.
3.6The contract for internal audit went out to tender and we have appointed KPMG as our audit contractors. We will expect them to work with our services in the same manner as an internal member of staff but we retain the in-house capability and skills for projects and the more sensitive work.
3.7This solution will provide the Council with the assurance, experience and flexibility that is needed while, still retaining in-house audit expertise within the Business Improvement Team. The proposed structure will not only fulfil the governance and assurance obligations of the internal audit function, but is practical and sustainable and value for money.
4. Audit Plan 2017-2018
4.1We always base the plan on risk assessments in line with best practice. We aim to audit the majority of services at least once every three years although we review the major systems annually. We update the risk assessment after each audit. The planning process is an assessment of the areas of risk and the resources available. The audit plan is a balance between supply and demand and is affected by unplanned events even though there is a contingency budget.
4.2The audit resources on the establishment in 2017-18 were:
In-house resources (1 vacant post) 2.67 FTE
Senior Auditor (Temp) and Contractor 0.75 FTE (vacant post)
Total resources 3.42 FTE
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Plan 2018-19Report | 427 KB | DownloadRead as text |
Follow Corporate Governance and Standards Committee (up to May 2025) at Guildford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Apr 2025 | Planning Committee: Public Speaking, Terms of Reference and Protocols(1) That the recommendation to full Council to approve the suggested amendments set out in the table in Appendix 1 to... | Approved | Open |
| 30 Apr 2025 | Dispensations ProcedureThat, subject to the amendment requested, the procedure for dispensations set out in Appendix 1 to the report submitt... | Approved | Open |
| 30 Apr 2025 | Proposed Guidance for Members on Gifts and HospitalityThat the recommendation to full Council to adopt into the Constitution the Guidance for Councillors on Gifts and Hosp... | Approved | Open |
| 30 Apr 2025 | Employee Code of ConductThat the recommendation to full Council that the Employee (Staff) Code of Conduct should no longer be contained in th... | Decided | Open |
| 20 Feb 2025 | Amendments to Annual Governance Statement 2023-24(1) That the amendments to the Council’s adopted Annual Governance Statement for 2023-24, as set out in Appendix 1 to... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.