(1) That the updated capital programme, as set out in Appendix 1 to the report submitted to the Council, be approved. (2) That the proposed treatment of the new capital bids, as set out in paragraphs 6.10 to 6.17 of the report, be approved. Reasons: · The financing of the approved Capital Budget has direct implications on borrowing costs within the General Fund revenue budget and other funding sources such as Reserves and Balances. · Setting a balanced budget is a statutory requirement.
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
3.1The financing of the approved Capital Budget has direct implications on borrowing costs within the General Fund revenue budget and other funding sources such as Reserves and Balances.
3.2Setting a balanced budget is a statutory requirement.
4. Status of Report
4.1This report is ‘open’.
5. Strategic Priorities
5.1The revised Corporate Strategy was approved by Council on 23 July 2024.
5.2Titled ‘A Greener, Fairer, Thriving Guildford’, the new Strategy has five core priorities which form the overarching focus for the Council over the next ten years.
These are: • Priority 1: A more sustainable borough • Priority 2: A more prosperous borough • Priority 3: A more inclusive borough • Priority 4: Decent and affordable homes • Priority 5: A resilient and well-managed council
5.3Throughout the budget process, these revised priorities have been considered. This has included both existing budget allocations and prioritisation of the growth bids received. 6. Background
6.1The capital strategy was approved by Council in December 2024 which set out the overall strategy for the Medium-Term Financial Plan (MTFP) period and the prudential indicators to be adhered to in terms of affordability and financing.
6.2Significant work has been done to update the existing capital budget. This has brought the existing approved schemes into a single capital programme and updated the timing, costs and financing of each project.
6.3This has allowed the future borrowing requirements to be fully understood, so that the treasury management requirements can be planned and borrowing undertaken in the most efficient way.
6.4Programmes of work are being agreed for areas such as vehicle replacement, ICT and Car Park maintenance so that the assets can be maintained efficiently, the procurement pipeline is understood and sufficient funding set aside in earmarked reserves to meet the costs.
6.5During 2024-25, the Ash Road Bridge project is due to complete. This will mean that MRP will become payable on the project and interest can no longer be capitalised as part of the scheme. These additional costs have been allowed for in the capital financing budget.
6.6The largest scheme remains the Weyside Urban Village (WUV) project. The main elements of this project currently are re-locating the Thames Water Sewerage Plant and providing the infrastructure across the site. Further phases will deal with building a new Council depot, decontamination, demolition of the old Sewerage plant and Council depot, and then sale of various plots of land for housing. The scheme may also involve Surrey County Council relocating their waste disposal site to a new facility.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Overview and Scrutiny Annual Report(1) To approve the attached at Appendix 1 to the report submitted to the Council. (2) To not amend the current O&S wo...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.