CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Guildford Borough Council
Council, Tuesday 9 December 2025 at 7.00pm

Extended Producer Responsibility (EPR) 2025/26

Approved Committee 5 papers

AI summaryGuildford Borough Council approves spending of £1,719,000 of Extended Producer Responsibility funding on a list of waste and recycling projects in 2025/26, from an expected total allocation of £2,410,000.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSpending on EPR project list and supplementary estimate
Money£1,719,000Initial supplementary estimate from EPR funding
What happens nextImplement as soon as practicableSubject to quotes for 3 workstream items and funds being received
Who it affectsWaste and recycling servicesPlus residents and businesses using council waste services

What was decided

The Council approved spending on the project list set out in Appendix 1 for implementation as soon as practicable. Report P10

The Council approved an initial supplementary estimate of £1,719,000 to be funded from Extended Producer Responsibility funding. Report P11, P12

The approval is pending the receipt of quotes relating to 3 workstream items and subject to funds being received. Report P12

Why

To use EPR funding to improve the efficiency and effectiveness of waste management and recycling services. Report 3.1, 6.3, 1.2

To modernise the digital offering to Guildford Borough residents and businesses. Report 3.2, 7.2, P29

To enable positive change without using existing revenue budgets or borrowing additional funds, and with no impact on general fund reserves. Report 3.3, P44

What happens next

Full Council approval was sought on 9 December 2025, with projects to be implemented as soon as practicable. Report 4.1, P17

Finance will work with the service throughout the year to ensure the funding requirements are adhered to, to mitigate the risk of future funding reductions. Report P43, 10.2

Further approvals will be needed to spend the remaining EPR funding, which is to be transferred to a reserve. Report P45

The money

  • £2,410,000 Total anticipated EPR funding for 2025/26 Report 1.1, P45
  • £1,719,000 Initial supplementary estimate from EPR funding Report P11, P12
  • £1.2m First EPR funding tranche due November 2025 Report P41
  • £1,356,000.00 Government guaranteed EPR amount for 2025 to 2026 per November 2024 provisional Notice of Assessment Report P50

Options considered

  • Chosen: Approve the recommendations to use the available funding for the proposed projects. To enable the Waste Strategy Lead Officer to improve the effectiveness and efficiency of waste services Report 11.1, 2.1, P10, P11
  • Rejected: Do nothing Report 11.2

Implications

  • Financial: The budget is fully funded from Extended Producer Responsibility funding, with no impact on general fund reserves. Report P44
  • Financial: EPR funding is paid in three tranches, the first of £1.2m due in November 2025, with two further equal payments in January 2026 and March 2026. Report P41
  • Legal: Funding must cover chargeable disposal costs under the Producer Responsibility Obligations (Packaging and Packaging Waste) Regulations 2024; PackUK may recalculate and reduce future funding if used for other purposes. Report P42, P49
  • Risk: 2026/27 funding will be received before all listed projects are delivered, so careful financial monitoring is needed to assign costs to the correct funding year. Report 10.1
  • Risk: Funding not used to improve the efficiency and effectiveness of services could be deducted from the 2026/27 funding allocation. Report 10.2, P47
  • Equalities: The Public Sector Equality Duty has been considered and no equality and diversity implications arise directly from this report. Report 12.3, P54, P57
  • Climate: Increased recycling rates are expected to minimise the volume of general waste disposal and encourage a circular economy. Report 12.4, P59, 7.1, P27
  • Other: Some projects will result in small ongoing licence costs, reflected in the 2026/27 budget process, and are expected to be covered by existing software licence costs as online forms are replaced. Report P46

Who and where

  • Guildford Borough Council residents and businesses using waste and recycling services Report 3.2, 7.2, P29
  • Council waste operations, waste strategy, street cleaning and customer services teams Report 7.2, P29, 9.1
  • Waverley Borough Council and the future unitary authority, through a matched service change item that could provide yearly savings to the disposal authority Report 8.1, 8.2
  • Council taxpayers, as the projects are intended to provide best value Report 1.4

Timeline

  • November 2024: Provisional Notice of Assessment received from PackUK, guaranteeing £1,356,000.00 for 2025 to 2026 Report P50
  • November 2025: First EPR funding tranche of £1.2m due Report P41
  • 6 November 2025: Executive considered the report and resolved to support the spending and supplementary estimate Report 1.5, P6, P7
  • 1 December 2025: Letter received from PackUK confirming the grant amount and purposes Report 1.3
  • 9 December 2025: Full Council decision to approve the spending and supplementary estimate Report 4.1, P17
  • January 2026: Second EPR funding tranche due Report P41
  • March 2026: Third EPR funding tranche due Report P41
  • 2026/27: Further EPR funding expected and ongoing licence costs reflected in budget Report 10.1, P46

Plain English for the jargon

  • Extended Producer Responsibility (EPR): A government scheme that requires producers of packaging to pay for the cost of managing that packaging waste, administered by PackUK.
  • PackUK: The body set up to manage the EPR scheme and to calculate and pay funding to local authorities.
  • DEFRA: Department for Environment, Food and Rural Affairs, the UK government department that set out the intended use of EPR funding.
  • Supplementary estimate: Additional budget approval sought by the Council for spending not included in the original budget.
  • Chargeable disposal costs: Net efficient costs incurred in the efficient management of household packaging waste, as defined in the Producer Responsibility Obligations (Packaging and Packaging Waste) Regulations 2024.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCO78

Resolved

(1) To approve the spending on the project list as set out in Appendix 1 to the report submitted to the Council, for implementation as soon as practicable. (2) To approve an initial supplementary estimate of £1,719,000 to be funded from Extended Producer Responsibility funding, in line with the project list detailed in Appendix 1, pending the receipt of quotes relating to 3 workstream items and subject ... view the full minutes text for item CO78
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Council

Executive summary

1.1Guildford Borough Council has been notified that it will receive up to £2,410,000 in Extended Producer Responsibility (EPR) payments in the 2025/26 financial year.

1.2These funds should be used to improve the efficiency and effectiveness of waste management and recycling.

1.3A letter has recently been received from PackUK (1 December 2025) which confirms the grant amount to be received and outlines the purposes for which the grant may be used (see Appendix 4).

1.4This report seeks approval to spend these funds on several projects that will meet this aim while providing tangible benefits and best value to taxpayers.

1.5At its meeting held on 6 November 2025, the Executive considered this report and resolved:

(1) To support the spending on the project list as set out in Appendix 1, for implementation as soon as is practicable;

(2) To support the approval of an initial supplementary estimate of £1,719,000 to be funded from Extended Producer Responsibility funding, to spent in line with the project list detailed in Appendix 1, pending the receipt of quotes relating to 3 workstream items.

1.6The Executive also endorsed the recommendation to Council below.

Recommendation

2.1That the Council resolves:

2.1.1 To approve the spending on the project list as set out in Appendix 1 to this report, for implementation as soon as practicable.

2.1.2 To approve an initial supplementary estimate of £1,719,000 to be funded from Extended Producer Responsibility funding, in Extended Producer Responsibility (EPR) 2025/26

line with the project list detailed in Appendix 1, pending the receipt of quotes relating to 3 workstream items and subject to funds being received.

3. Reason(s) for recommendation:

3.1To utilise EPR funding to improve waste management and recycling.

3.2To modernise the digital offering to Guildford Borough residents and businesses.

3.3To enable positive change without the need to use existing revenue budgets or borrow additional funds.

4. Next steps

4.1Approval by Full Council on 9 December 2025.

5. Exemption from publication

5.1None of this report is exempt from publication.

6. Background and Proposal

6.1The government’s Extended Producer Responsibility (EPR) scheme started providing funding to Councils in the 2025/26 financial year. The scheme is managed by PackUK and collects funding from manufacturers of products based on the amount and type of packaging they are using as set out in Appendix 2.

6.2Funds allocated to each Council are calculated with consideration to deprivation, rurality, waste collection method, number of flats and the tonnes of recycling collected per household as set out in Appendix 3.

6.3Funding should be used to drive improvements in the efficiency and effectiveness of services.

7. Links to our Strategic Priorities

7.1A more sustainable borough Extended Producer Responsibility (EPR) 2025/26

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Extended Producer Responsibility (EPR) 2025/26Report 122 KB DownloadRead as text
PDF
Item 13 (1): Extended Producer Responsibility 2025-26: App 1: EPR Fund SpendingAppendix 46 KB Download
PDF
Item 13 (2): Extended Producer Responsibility 2025-26: App 2: June 2025 Letter From DEFRAAppendix 213 KB Download
PDF
Item 13 (3): Extended Producer Responsibility 2025-26: App 3: July 2025 Letter From DEFRAAppendix 107 KB Download
PDF
Item 13 (4): Extended Producer Responsibility 2025-26: App 4: Pack UK Grant LetterAppendix 70 KB Download

At this meeting

Whole meeting

Who was there

37 of 50 attended
TM
The Mayor, Councillor Howard SmithMayor, present
TD
The Deputy Mayor, Councillor Jane TysonDeputy Mayor, present
BA
Councillor Bilal AkhtarCommittee Member, apologies
SB
Councillor Sallie Barker MBECommittee Member, present
PB
Councillor Phil BellamyCommittee Member, present
DB
Councillor Dawn BennettCommittee Member, present
JB
Councillor Joss BigmoreCommittee Member, present
DB
Councillor David BilbeCommittee Member, present
HB
Councillor Honor BrookerCommittee Member, present
JB
Councillor James BrookerCommittee Member, present
PB
Councillor Philip BrookerCommittee Member, present
RB
Councillor Ruth BrothwellCommittee Member, apologies

All 50 on the meeting page

On this subject at Guildford

Search all
  1. Extended Producer Responsibility (EPR) 2025/26This decision
  2. Extended Producer Responsibility (EPR) 2025/26Approved

More from Guildford Council

All decisions
MeetingDecisionOutcome
15 Sep 2026 Appointment of an Interim Monitoring OfficerThat Deborah Davies, Joint Head of Governance, be appointed as the Council’s interim Monitoring Officer until the Str... Decided Open
15 Sep 2026 Proposed Changes to the Scheme of Officer Delegations & Proper Officer Scheme(1) That the proposed changes to the Scheme of Delegation and Proper Officer Scheme, as set out in Appendices 1 and 2... Approved Open
15 Sep 2026 Overview and Scrutiny Annual Report(1) To approve the attached at Appendix 1 to the report submitted to the Council. (2) To not amend the current O&S wo... Approved Open
15 Sep 2026 Freedom of the BoroughThat a meeting of the Council be arranged specially convened for the purpose of admitting The Ranger Regiment to the ... Decided Open
15 Sep 2026 Councillor Ruth Brothwell - Review of Attendance at MeetingsThat, in accordance with Section 85 of the Local Government Act 1972, the Council agrees that Councillor Ruth Brothwe... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies