CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Guildford Borough Council
Council, Tuesday 12 May 2026 at 7.00pm

Local Authority Housing Fund Round 4

Decided Committee 3 papers

AI summaryGuildford Borough Council approved a £3,297,300 budget to buy six homes using Local Authority Housing Fund Round 4 grant, with the balance from the Housing Revenue Account.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedfor acquiring six homes under LAHF Round 4
Money£3,297,300 total£1,387,000 grant, £1,910,300 HRA borrowing
What happens nextSign Memorandum of Understanding with MHCLGfirst grant tranche expected July 2026
Who it affectsHomeless families and Afghan Resettlement householdssix homes to be acquired locally

What was decided

Full Council approved adding £3,297,300 to the capital programme, of which £1,387,000 is LAHF Round 4 capital grant, with the balance from the Housing Revenue Account. Report P10

The Executive had already resolved on 23 April 2026 to accept the £1,387,000 grant and forward finance acquisition of six properties. Report 1.6, P7

Total LAHF Round 4 funding allocated to the Council is £1,396,048, comprising £1,387,000 capital and £9,048 revenue. Report 1.3, 3.2

Why

The project supports the Council's Corporate Strategy 2024 to 2034 aim of providing decent and affordable homes by enabling acquisition of properties for temporary accommodation and for families on the Afghan Resettlement Programme. Report 1.1, 3.1, 7.1

Officers found that the Council funded element is recoverable from rental income, with a positive net revenue position over the 60 year asset life, and a payback of 33 years on Council investment. Report 3.3, P69

Accepting the grant reduces pressure on the Council's reserves, leaving funds available for other new build or acquisition schemes. Report P59

What happens next

The S151 Officer will sign the Memorandum of Understanding with MHCLG, subject to Council approval of the scheme. Report P74

MHCLG will release the first tranche of grant funding in July 2026, with further tranches over the four year programme. Report 4.2

The Council will acquire six properties from the local market: two in 2026 to 27, none in 2027 to 28, four in 2028 to 29, and none in 2029 to 30. Report 4.3, 6.4, P32, P34, P36, P38

The money

  • £3,297,300 Total scheme cost to be added to capital programme Report P10, P70, P71
  • £1,387,000 LAHF Round 4 capital grant Report 1.3, P10, P71
  • £1,910,300 Borrowing from the Housing Revenue Account Report P71
  • £1,396,048 Total LAHF Round 4 funding allocation to the Council Report 1.3, 3.2
  • £9,048 LAHF Round 4 revenue grant Report 1.3, P61
  • £430,000 Year 1 capital allocation (2026 to 27) Report P64
  • £957,000 Year 3 capital allocation (2028 to 29) Report P66

Options considered

  • Rejected: Do not accept the LAHF Round 4 funding allocation. The Council would lose the chance to subsidise the acquisition of six additional homes during the funding period and the subsidy would be returned to MHCLG. Report 11.1, P57, 10.1
  • Chosen: Accept the LAHF Round 4 funding allocation (recommended). Enables the Council to acquire six homes with subsidy, reducing pressure on existing reserves and supporting the Corporate Strategy. Report 11.2, P59

Implications

  • Financial: Scheme is modelled on internal borrowing at this stage; using reserves instead would improve viability by removing interest costs. Report P72
  • Financial: Payback period is 33 years on the Council's direct investment and 45 years when the LAHF grant is included; net revenue position is positive over 60 years. Report P69
  • Legal: Property purchases rely on Section 9(1)(b) of the Housing Act 1985; the Council may deviate from its Allocations Scheme to allocate to the LAHF cohort. Report P75, P77
  • Equalities: Public Sector Equality Duty applies; Equalities Comprehensive Impact Assessment found no disproportionately adverse impact on any protected characteristic. Report P80, P84
  • Climate: Energy efficiency and improving the Energy Performance Certificate rating will be prioritised when assessing acquired properties. Report P88
  • Staffing: An interim specialist consultant will support the Affordable Housing Delivery Team for year one, funded from the £9,048 revenue grant. Report 10.2, P79
  • Risk: If grant conditions are not met, the Council would have to repay the grant to MHCLG. Report P74

Who and where

  • Families owed a homelessness duty by the Council (temporary accommodation use) Report 6.2, P28, P91
  • Households on the Afghan Resettlement Programme (resettlement element) Report 6.2, P28, P92
  • Housing Revenue Account and General Fund (as scheme funder and leaseholder of the temporary accommodation unit) Report P73
  • Affordable Housing Delivery Team in the Council (delivery responsibility) Report 10.2, P79
  • Local property market (acquisitions drawn from it) Report 6.7

Timeline

  • 10 April 2026 (extension requested): Original MHCLG deadline for returning signed Memorandum of Understanding Report 1.4
  • 23 April 2026: Executive resolved to accept LAHF Round 4 funding, subject to full Council budget approval Report 1.6, P7
  • 12 May 2026: Full Council considered the budget
  • July 2026: MHCLG expected to release first tranche of grant funding Report 4.2
  • Year 1 (2026 to 27): Two properties to be acquired: one temporary accommodation and one resettlement Report 6.4, P32, P34, P38
  • Year 2 (2027 to 28): No property acquisitions scheduled Report 6.4, P38
  • Year 3 (2028 to 29): Four properties to be acquired: two resettlement and two large resettlement Report 6.4, P34, P36, P38
  • Year 4 (2029 to 30): No property acquisitions scheduled Report 6.4, P38
  • 30 year HRA Business Plan: Appraisal shows the scheme is positive in cost terms over this period Report 3.3
  • 60 year asset life: Appraisal shows a positive net revenue position over this period Report P69

Plain English for the jargon

  • LAHF: Local Authority Housing Fund, a government programme run by MHCLG to fund temporary and settled accommodation
  • MHCLG: Ministry of Housing, Communities and Local Government
  • HRA: Housing Revenue Account, the ringfenced account landlords keep for rental income and spend on council housing
  • ARP: Afghan Resettlement Programme, the UK scheme for resettling eligible Afghan families
  • MoU: Memorandum of Understanding, the agreement with MHCLG required to receive the grant
  • EPC: Energy Performance Certificate, a rating of a property's energy efficiency
  • PSED: Public Sector Equality Duty, the legal duty to consider equality when making decisions
  • ECIA: Equalities Comprehensive Impact Assessment
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCO15

Resolved

That a budget of £3,297,300 be added to the capital programme, of which ? £ 1,387,000 ? is LAHF Round 4 capital grant funding, with the balance being funded from the Housing Revenue Account. ? Reasons: · The project would facilitate the acquisition of homes that would be used for temporary accommodation for homeless families or for families on the Afghan Resettlement Programme (ARP). This aligned with the Council’s objective of using the means available to it to deliver decent and affordable homes for our residents as set out in its Corporate Strategy 2024-2034. · The Council had been allocated a total of £1,396,048 LAHF Round 4 funding. · Whilst the Council would be required to commit its own funds to deliver the project, the initial financial appraisal demonstrated that the Council-funded element of the budget was recoverable via the rental income streams within an acceptable period and was positive in terms of the cost to the HRA Business Plan over 30 years.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Council

Executive summary

1.1Delivery of decent and affordable homes is one of the Council’s Corporate Priorities. This report provides detail of a funding allocation the Council has secured from the Ministry of Housing, Communities and Local Government (MHCLG) via the Local Authority Housing Fund (LAHF) Round 4.

1.2LAHF Round 4 is a £950 million government programme aimed at expanding high‑quality temporary accommodation and supporting housing for Afghan resettlement families while reducing reliance on costly B&Bs and hotels.

1.3The Council has secured an allocation comprising a capital grant of £1,387,000 and a revenue grant of £9,048.

1.4To receive the funding, the Council must enter into a Memorandum of Understanding (MoU) with MHCLG. MHCLG had requested that the MoU be signed and returned them by 10 April, but we have requested an extension to align with the proposed approval timetable for this matter to which they have agreed.

1.5The Council must also commit to providing match funding to deliver the scheme outputs. The LAHF funding allocation is based on a contribution of 40% or 50% (depending on property type) of the property acquisition cost based on the median property price within a Council area.

1.6At its meeting held on 23 April 2026, the Executive considered this report and resolved, subject to the full Council’s approval of the necessary budget contained in the recommendation below:

(1) To accept £1,387,000 of LAHF Round 4 grant funding and agree to the forward financing of the acquisition of six properties under this scheme.

(2) To approve the scheme delivery profile as set out in Exempt Appendix 1 to this report.

Recommendation

2.1That full Council resolves to: Local Authority Housing Fund Round 4

2.1.1 Approve a budget of £3,297,300 to be added to the capital programme, of which £1,387,000 is LAHF Round 4 capital grant funding, with the balance being funded from the Housing Revenue Account.

Reasons for recommendation

3.1The project will facilitate the acquisition of homes that will be used for temporary accommodation for homeless families or for families on the Afghan Resettlement Programme (ARP). This aligns with the Council’s objective of using the means available to it to deliver decent and affordable homes for our residents as set out in its Corporate Strategy 2024-2034.

3.2The Council has been allocated a total of £1,396,048 LAHF Round 4 funding.

3.3Whilst the Council will be required to commit its own funds to deliver the project, the initial financial appraisal demonstrates that the Council-funded element of the budget is recoverable via the rental income streams within an acceptable period and is positive in terms of the cost to the HRA Business Plan over 30 years.

4 Next steps

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 08 (2): Local Authority Housing Fund R4: App 2: MoUAppendix 745 KB Download
PDF
Item 08 (3): Local Authority Housing Fund R4: App 3: EIAAppendix 375 KB Download
PDF
Local Authority Housing Fund Round 4Report 271 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

32 of 50 attended
TD
The Deputy Mayor, Councillor Jane TysonMayor, present
DW
Councillor Dominique WilliamsDeputy Mayor, present
BA
Councillor Bilal AkhtarCommittee Member, present
SB
Councillor Sallie Barker MBECommittee Member, present
PB
Councillor Phil BellamyCommittee Member, present
DB
Councillor Dawn BennettCommittee Member, apologies
JB
Councillor Joss BigmoreCommittee Member, present
DB
Councillor David BilbeCommittee Member, apologies
HB
Councillor Honor BrookerCommittee Member, present
JB
Councillor James BrookerCommittee Member, present
PB
Councillor Philip BrookerCommittee Member, present
RB
Councillor Ruth BrothwellCommittee Member, apologies

All 50 on the meeting page

On this subject at Guildford

Search all
  1. Local Authority Housing Fund Round 4This decision
  2. Local Authority Housing Fund Round 4Approved
  3. Code of Practice on Good Governance for Local Authority Statutory OfficersApproved
  4. Local Government Collaboration - Approval of Inter-Authority Agreement and Establishment of a Joint Governance CommitteeAgreed
  5. Establishment of North Downs Housing Ltd: a Local Authority Wholly Owned Housing CompanyNoted
  6. Establishment of North Downs Housing Ltd: a Local Authority Wholly Owned Housing CompanyAgreed

More from Guildford Council

All decisions
MeetingDecisionOutcome
15 Sep 2026 Appointment of an Interim Monitoring OfficerThat Deborah Davies, Joint Head of Governance, be appointed as the Council’s interim Monitoring Officer until the Str... Decided Open
15 Sep 2026 Proposed Changes to the Scheme of Officer Delegations & Proper Officer Scheme(1) That the proposed changes to the Scheme of Delegation and Proper Officer Scheme, as set out in Appendices 1 and 2... Approved Open
15 Sep 2026 Overview and Scrutiny Annual Report(1) To approve the attached at Appendix 1 to the report submitted to the Council. (2) To not amend the current O&S wo... Approved Open
15 Sep 2026 Freedom of the BoroughThat a meeting of the Council be arranged specially convened for the purpose of admitting The Ranger Regiment to the ... Decided Open
15 Sep 2026 Councillor Ruth Brothwell - Review of Attendance at MeetingsThat, in accordance with Section 85 of the Local Government Act 1972, the Council agrees that Councillor Ruth Brothwe... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies