Item73
Resolved
Approve subject to conditions relating to the following: Standard condition for time limits of commencement (BE1); Condition listing the approved plans; Condition specifying that this is a phased development, and that any pre-commencement conditions shall be met prior to the commencement of either stage; Restrict use to ancillary with the existing factory (E1); Materials condition, requiring the submission and approval of the materials to be used (BE2); Submission, agreement and implementation of site and finished floor levels (BE1); Requiring submission and implementation of an updated Travel Plan (TP16); Site investigation, including mitigation to be submitted and approved in writing (PR14); and Conditions relating to the submission of foul and surface water drainage, to be submitted and approved in writing prior to commencement.
Word for word from the decision Halton published for this meeting.