Resolved
That 1) the Grange Nursery, Infant and Junior School buildings are demolished once they are vacated, following the completion of the new Grange All Through School being constructed under the BSF programme; and 2) in respect of the above, in order to reduce risk with regards the existing buildings once they become vacant, a tender process be undertaken through the Chest, in order to obtain competitive quotes for the demolition of the buildings to ensure that a contractor is in place to commence the works as soon as the Authority has vacant possession.