Item39
Resolved
That the application be approved subject to the following conditions: 1. Standard 3 year permission; 2. Approved plans; 3. Site levels; 4. Materials; 5. Landscape scheme; 6. Boundary details; 7. Electric vehicle charging provision; 8. Cycle storage; 9. Highways/pedestrian connection works; 10. Travel plan; 11. Contaminated land remediation strategy; 12. Contaminated land verification report; 13. Piling risk assessment; 14. Environment Agency unidentified contamination; 15. Drainage strategy; 16. SUDS verification report; 17. Waste audit or a similar mechanism ( eg . a site waste management plan); 18. MEAS โ Construction Environmental Management Plan to include Reasonable Avoidance Measures (RAMs); 19. Mitigation of habitat loss and enhancement as in approved report (section 6); 20. Ecology lighting scheme; 21. Breeding birds; 22. Hours of construction; and 23. Access, service and parking areas.
Word for word from the decision Halton published for this meeting.
Source: moderngov.halton.gov.uk