Performance Management Reports for Quarter 2 of 2025/26

Noted Committee 2 papers

AI summaryHalton Borough Council's Environment and Regeneration Policy and Performance Board received and noted its quarter 2 report. Economy, Enterprise and Property, Community and Greenspaces, and Planning, Provision and Transportation forecast £0.163 million, £0.72m and £0.364m under budget respectively.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedObjectives, milestones, indicators and financial statements.
MoneyThree departmental forecasts under budgetEconomy £0.163 million; Greenspaces £0.72m; Planning £0.364m.
What happens nextRegeneration plan due December 2025Place strategy and food waste work continue.
Who it affectsEnvironment and regeneration servicesRegeneration, housing, transport, waste, parks and planning.

What was decided

The Environment and Regeneration Policy and Performance Board received and noted the quarter 2 performance management report.

What happens next

Submit the Runcorn Regeneration Plan by December 2025. Report P8

Complete the final place strategy by March 2026. Report P42

Prepare weekly food waste collection rounds and resident communications for April 2026. Use service redesign, planned new recycling services, communication and behaviour change to improve recycling. Report P135, P142, P143

The money

  • £0.163 million Forecast underspend for Economy, Enterprise and Property Report P154
  • £0.72m Forecast underspend for Community and Greenspaces Report P205
  • £0.364m Forecast underspend for Planning, Provision and Transportation Report P232
  • £1,080,500 Combined value of 8 grant bids submitted in Qtr. 2 Report P37
  • £0.259 million Projected agency staffing costs for this financial year Report P157
  • £0.136 million Vacant property costs as of the end of July Report P158
  • £73,844.86 Cost of disposing of contaminated recycling material in Q2 Report P139
  • £300k External funding target by March 2026 Report P44

Options considered

  • Chosen: Receive and note the quarter 2 performance management report

Implications

  • Financial: All three service areas forecast spending below their approved budgets. Report P154, P205, P232
  • Financial: Inflation has increased costs, with Community and Greenspaces supplies and services forecast £0.249m over budget. Report P207
  • Risk: Recruitment difficulties for surveyors and other key roles create a risk of project delays. Report P157
  • Staffing: Agency staffing is projected at £0.259 million, with some costs recovered through capital budgets and external funding. Report P157
  • Financial: Vacant properties cost £0.136 million as of the end of July, rising to £0.154 million over two months. Report P158
  • Climate: Q2 recycling was 38.5%, and the 2025/26 national recycling target is unlikely to be met. Report P134, P135
  • Risk: The leisure centre solar connection is unlikely to be completed by 31st March, although the scheme may be on site. Report P48
  • Legal: Grant conditions must be maintained throughout delivery, with staff time allocated to keep projects aligned. Report P156

Who and where

  • Halton residents Report P76, P114, P142
  • People needing new homes in Halton Report P15, P17, P20
  • Local businesses and start ups Report P22, P26, P28
  • Bus passengers across Halton Report P76, P77, P78
  • Households covered by weekly food waste collections Report P142
  • People using parks, playgrounds and cemeteries Report P114, P119, P125
  • People using council transport services Report P82, P87
  • Council staff and regeneration delivery partners Report P34, P156, P157

Timeline

  • November 2025: Housing pipeline site submissions should conclude. Report P17, P18
  • December 2025: Submit the Runcorn Regeneration Plan. Report P8
  • March 2026: The final place strategy is due. Report P42
  • 31st March 2026: Picow Farm Depot decarbonisation works are due to complete. Report P49
  • April 2026: Food waste vehicle and caddy deliveries are due to begin. Report P142
  • May 2026: First completed Foundry Lane homes are anticipated for handover. Report P20
  • November 2026: All Foundry Lane homes are due to be completed. Report P20
  • March 2027: Government extended the Runcorn Town Deal funding spend deadline. Report P7

Plain English for the jargon

  • Q2: Quarter 2.
  • APSE: Association for Public Service Excellence.
  • LAMS: Land Audit Management System.
  • LCR: Liverpool City Region.
  • UKSPF: UK Shared Prosperity Fund.
  • Town Deal: Programme funding Runcorn regeneration projects.
  • CPO: Process used to secure land for the Daresbury masterplan.
  • TCR: Five year Capital Programme from April 2027 to March 2032.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item27

Resolved

That the quarter 2 performance management report be received and noted.
Word for word from the decision Halton published for this meeting. Source: moderngov.halton.gov.uk

Follow this further

Built from Halton's papers

What the report saysPro

Report to Environment and Regeneration Policy and Performance Board, 29 pages

Appendices

Appendix 1: Progress Against Objectives / Milestones Appendix 2: Explanation of Symbols Appendix 3: Progress Against Performance Indicators Appendix 4: Financial Statement Appendix 1: Progress Against Objectives / Milestones

Corporate Priority 2 – Building a strong sustainable local economy. Priority Regeneration

Deliver key regeneration programmes and work with partners to increase social and financial ERD 01 investment.

Progress Milestone Supporting Commentary Q2

Deliver Widnes Town Centre UKSPF funded by Spend has started slowing in Q2, we are March 2026. expecting most of the spend to be in Q4. New Street art project – First round selection completed, round 2 underway to select winning commission. Music Trail – in house work continues and external contract in place.

Environment & Regeneration Directorate Page 2 of 29 Enhancement Study – team appointed and work has started. Widnes Road Public Realm – new street furniture selected.

The following Runcorn Town Deal funded projects Health and Education Hub is due to complete to be completed or in contract by March 2026 – later this year with commissioning to follow. Creative and Digital Skills Centre, Health and Creative and Digital Skills Centre 57 59 due to Education Hub, Unlock Runcorn, Rutland Street, complete March 26 Connectivity Project, Enterprise Centre. Creative and Digital Skills Centre 63 65 not yet in contract Unlock Runcorn not yet in contract Rutland Street planning due for submission by March 26 Connectivity not yet in contract Enterprise centre not yet in contract Deadline for spend has been extended to March 2027 by Government

Submit Runcorn Regeneration plan by December Work is ongoing, a paper is going to Executive 2025 following further guidance from government Board in October and the Board is on track to being signed off by Runcorn Neighbourhood Board, approve and submit The Regeneration Plan by Stakeholders and Executive Board. the deadline.

Corporate Priority 2 – Building a strong sustainable local economy Priority Regeneration

ERD 02 Support development & growth at Sci-tech Daresbury

Progress Milestone Supporting Commentary Q2

Assist JV to secure £9.5m funding from the CA by The CA Investment Panel approved the Full July 2025 for Project Violet Phase 2 and commence Business Case for the Lab Building, and the delivery by March 2026 grant funding agreement is currently being drafted. The Strategic Outline Case for the second building has also been approved and will now proceed to a Full Business Case.

Make the CPO to bring forward circa 30 acres of Documentation for the CPO is being future development land by January 2026 progressed.

Environment & Regeneration Directorate Page 3 of 29 Corporate Priority Six – Valuing and Appreciating Halton and our Community Priority Regeneration

Providing new homes that meet Halton’s needs. ERD 03

Progress Milestone Supporting Commentary Q2

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Environment & Regeneration PPB Q2 Report.docxReport 29 pages DownloadRead as text
PDF
Performance Management Reports for Quarter 2 of 2025/26Report 2 pages Download

At this meeting

Whole meeting

Who was there

9 of 18 attended
BW
Councillor Bill WoolfallChair, present
PL
Councillor Peter Lloyd JonesVice-Chair, present
VH
Councillor Valerie HillMember, present
NH
Councillor Noel HutchinsonMember, apologies
KL
Councillor Kath LoftusMember, expected
TM
Councillor Tony McDermottMember, present
SN
Councillor Stef NelsonMember, present
LN
Councillor Louise NolanMember, present
CP
Councillor Carol Plumpton WalshMember, expected
GS
Councillor Gareth StocktonMember, expected
KW
Councillor Kevan WainwrightMember, apologies
TG
Tim GibbsOfficer, expected

All 18 on the meeting page

On this subject at Halton

Search all
  1. Performance Management Reports for Quarter 2 of 2025/26This decision
  2. Performance Management Framework and Risk Management FrameworkApproved
  3. Performance Management Reports for Quarter 3 of 2025/26Noted
  4. Performance Management Reports for Quarter 3 of 2025/26Noted
  5. Performance Management Report - Quarter 3 2025/26Noted
  6. Performance Management Reports for Quarter 2 of 2025/26Noted

More from Halton Environment and Regeneration Policy and Performance Board

All decisions
MeetingDecisionOutcome
17 Jun 2026 Executive Board MinutesThat the Minutes be received. Decided Open
17 Jun 2026 Local Nature Recovery Strategy and Biodiversity Duty updateThat the Local Nature Recovery Strategy and Biodiversity Duty Update be noted. Noted Open
17 Jun 2026 Annual Report 25/26That the report be noted. Noted Open
11 Feb 2026 Executive Board MinutesThat the Minutes be received. Decided Open
11 Feb 2026 Contaminated and Brownfield Land in HaltonThat the presentation be noted. Noted Open