Additional Highway Grant allocations

Approved Executive 1 paper

AI summaryHalton Executive Board approves delegation to accept £190,000 confirmed Active Travel Fund 5 grant, with £577,000 Consolidated Active Travel Fund and £564,556.12 Pre-Development funding also expected from the Liverpool City Region Combined Authority.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved
Money£190,000 confirmed; £577,000 and £564,556.12 expected
What happens nextGrant Funding Agreements to be finalisedCA approvals ongoing; Pre-Development GFA expected imminently
Who it affectsNot stated

What was decided

The Director of Planning and Transportation, in consultation with the Portfolio Holder Environment and Urban Renewal, is delegated to accept the Grant Funding Agreement and enable timely delivery. Report P3

The same Director and Portfolio Holder are delegated to handle any matters relating to procurement and operation of these agreements. Report P4

Why

Approval enables the quickest start to expenditure once funding is received, and avoids failure to complete the funded works. Report 7.1

Active travel and well maintained highways support healthier travel choices, access to jobs, lower carbon transport, and safer options for people on low incomes. Report 6.1, 6.2, 6.4, 6.5

Acceptance is needed to comply with Council Standing Orders and future procurement requirements. Report 1.1, 4.0, 4.1

What happens next

Accept the Grant Funding Agreements and progress scheme delivery, with Pre-Development works to be completed or committed by 31st March 2026. Report 3.5, P3

Spend the Active Travel Fund 5 grant by March 2027 on three named schemes.

Spend the Consolidated Active Travel Fund allocation by Summer 2027 on East Runcorn Connectivity active travel schemes at the Runcorn High Street interface. Report 3.3, 3.4

The money

  • £190,000 Active Travel Fund 5 grant received by Halton Report 3.1
  • £577,000 Consolidated Active Travel Fund (CATF) allocation expected to Halton Report 3.1
  • £564,556.12 Pre-Development Work funding for Transport Pipeline projects Report 3.1
  • £100,000 ATF5 contribution to North Albert Road pedestrian improvements
  • £50,000 ATF5 for Runcorn High Street Phase 2 detailed design
  • £40,000 ATF5 for Runcorn busway Active Travel Route maintenance and amendments
  • £50,000 Pre-Development options appraisal for potential A558 improvements Report 3.5
  • £515,000 Pre-Development detailed design for three Runcorn Active Travel schemes Report 3.5

Options considered

  • Chosen: Approve delegation to the Director of Planning and Transportation, with the Portfolio Holder, to accept grants and handle procurement. Enables the quickest start to grant expenditure and compliance with Standing Orders Report P3, P4, 4.1, 7.1

Implications

  • Financial: Works are covered entirely by the capital grants; no Halton Borough Council match funding is required. Report 5.1
  • Legal: Acceptance is required to comply with Standing Orders, with future procurement under Council Procurement Standing Orders. Report 4.0, 4.1, 1.1
  • Risk: If delegation is not approved, none of the grant funds can be spent and the funded works will not proceed. Report 7.1
  • Climate: Highway works may use high carbon materials such as bituminous products, but the service aims to use lower carbon options such as warm mix asphalt and carbon neutral proprietary materials. Report 9.1
  • Equalities: No direct equality and diversity issues are identified. Report 8.1

Who and where

  • Residents and road users across Halton using the highway network Report 6.1, 6.4
  • People walking or cycling in Runcorn, including along the busway active travel route and Runcorn High Street Report 3.3
  • Local workforce needing access to jobs and amenities Report 6.2
  • People on low incomes looking for safe, viable travel options Report 6.4

Timeline

  • 31st March 2026: Pre-Development works to be completed or committed Report 3.5
  • March 2027: Active Travel Fund 5 grant to be spent
  • Summer 2027: Consolidated Active Travel Fund allocation to be spent Report 3.4

Plain English for the jargon

  • ATF5: Active Travel Fund 5, a grant programme from Active Travel England
  • CATF: Consolidated Active Travel Fund, the rebranded Active Travel Fund 6
  • LCRCA: Liverpool City Region Combined Authority
  • HBC: Halton Borough Council
  • GFA: Grant Funding Agreement
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item87

Resolved

That 1) the Board approves the Director of Planning and Transportation, in consultation with the Portfolio Holder Environment and Urban Renewal, be delegated to accept the Grant Funding Agreement and enable timely delivery of the agreements; and 2) the Director Planning and Transportation, in consultation with the Portfolio Holder Environment and Urban Renewal, be delegated to deal with any matters relating to procurement and operation of these agreements.
Word for word from the decision Halton published for this meeting. Source: moderngov.halton.gov.uk

Follow this further

Built from Halton's papers

What the report saysPro

Report to Executive Board, 3 pages

Purpose of the report

1.1This report seeks Executive Board approval to accept capital funding from the Liverpool City Region Combined Authority in compliance with Standing Orders

2.0RECOMMENDED: That

1. the Board approves the Director Planning and Transportation, in consultation with the Portfolio Holder Environment and Urban Renewal be delegated to accept the Grant Funding Agreement and enable timely delivery of the agreements; and

2. the Director Planning and Transportation in consultation with the Portfolio Holder Environment and Urban Renewal be delegated to deal with any matters relating to procurement and operation of these agreements.

3.0SUPPORTING INFORMATION

3.1In addition to previous capital funding arrangements through the Liverpool City Region Combined Authority (LCRCA), Halton has now received a grant of £190,000 as part of Active Travel Fund 5. We have also received notification of an imminent Active Travel Fund 6 Grant which has been rebranded Consolidated Active Travel Fund (CATF). Internally, Combined Authority approvals on the allocation of the CATF Liverpool City Region wide funding are ongoing but are currently expected to allocate £577,000 to Halton. Finally, we have been allocated £564,556.12 for Pre-Development Work of the Transport Pipeline projects that are due to be constructed with the future funding from the Transport for City Regions Capital allocation to the City Region. We are currently awaiting the final Grant Funding Agreement for this. 3.2 The ATF5 funding is to be invested in three schemes, £100,000 towards North Albert Road pedestrian improvements, £50,000 for Detailed Design works for the Runcorn High Street Phase 2 detailed design and £40,000 for maintenance works / amendments identified by Active Travel England when they audited the Active Travel Route along Runcorn busway. Funding is due to be spent by March 2027.

3.3CATF is to be invested in the construction of the East Runcorn Connectivity Active Travel Schemes prioritised at their interface with the Runcorn High Street scheme itself paid for by the allocation to Runcorn from the Local Government Town’s Fund.

3.4The LCRCA have requested we seek Grant acceptance for the CATF in advance to ensure funding expenditure can start as soon as possible in the new financial year. Funding is due to be spent by Summer 2027.

3.5The Pre Development Funding is to be invested in three broad schemes, £50,000 in the options appraisal for the potential A558 improvements, £515,000 for the three Runcorn Active Travel schemes to have detailed design development completed including the Runcorn Old Town/Shopping City route and Runcorn East/Red Brow Lane. All works completed with this Fund are to be completed or committed by 31st March 2026. The Grant Funding Agreement is expected imminently from the CA and has been seen by Officers at Draft status.

4.0POLICY IMPLICATIONS

4.1Approval will comply with Standing Orders and enable compliance with the Council Procurement Standing Orders for the future works.

Financial implications

5.1The work to be covered entirely by these Capital grant funding agreements have no requirement for HBC match funding.

6.0IMPLICATIONS FOR THE COUNCIL’S PRIORITIES

6.1Improving Health, Promoting Wellbeing and Supporting Greater Independence Well maintained Highways ensure that the public can travel quickly and easily on the Highway network. The construction of cycleways enables a health choice for the public when determining travel options not only for commuting but leisure.

6.2Building a Strong, Sustainable Local Economy Workforce accessibility to jobs and amenities supports the local economy. 6.3 Supporting Children, Young People and Families None identified.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Additional Highway Grant allocationsReport 3 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 20 attended
MW
Councillor Mike WhartonChair, present
LB
Councillor Laura BevanMember, present
AB
Councillor Angela BallMember, present
MD
Councillor Mark DennettMember, present
PH
Councillor Phil HarrisMember, present
TM
Councillor Tom McInerneyMember, present
PN
Councillor Paul NolanMember, present
DT
Councillor Dave ThompsonMember, apologies
AW
Councillor Andrea WallMember, present
MW
Councillor Marie WrightMember, present
GC
Gill CookOfficer, present
MR
Mark ReaneyOfficer, present

All 20 on the meeting page

On this subject at Halton

Search all
  1. Additional Highway Grant allocationsThis decision
  2. Additional Highway Grant AllocationsAgreed
  3. Additional Highway Maintenance AllocationsApproved

More from Halton Executive Board

All decisions
MeetingDecisionOutcome
22 Oct 2026 Halton Housing Trust Annual ReportThe Board thanked Halton Housing for the presentation and noted the report. Noted Open
22 Oct 2026 Highway Asset Management Plan (HAMP)That 1) approves the Highway Asset Management Plan (HAMP) 2026-2029 (contained in Appendix A) for adoption and public... Approved Open
22 Oct 2026 Waste Management and Recycling Contract - Key DecisionThat 1) Members approve the continued delegation of defined elements of the Council’s Waste Disposal Authority functi... Approved Open
22 Oct 2026 Waste Strategy and Household Waste Collection PolicyThat 1) Members approve the draft Waste Management Strategy and the draft Household Waste & Recycling Collection Poli... Approved Open
22 Oct 2026 Specialist DA Therapeutic Support for Children: Request for Waiver of Standing OrdersThat the Board 1) are advised of the Domestic Abuse Board mapping work of the domestic abuse system and support offer... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies