Highways Asset Management Plan

Approved Committee 2 papers

AI summaryHalton Borough Council's Environment and Urban Renewal Policy and Performance Board endorsed the Highway Infrastructure Asset Management Plan 2026 to 2029, covering a 1,400km network valued at about £2.3 billion, and sent it to the Executive Board for approval.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedEndorsed for submission to the Executive Board
MoneyNot stated
What happens nextSubmission to Executive BoardPlan goes to the Executive Board for approval
Who it affects1,400km highway networkCovers 606km of roads and 838km of footpaths

What was decided

The Board endorsed the Highway Asset Management Plan and its submission to the Executive Board for approval.

Delegated authority was granted to the appropriate Director and Portfolio Holder to approve any necessary updates.

The plan sets out the strategic approach for 2026 to 2029, covering Halton's highway network. Report P3

Why

The highway network is one of Halton's most valuable assets, spanning over 1,400km and valued at approximately £2.3 billion. Report P4, P13

The plan uses a data-driven, risk-based approach to maximise value for money, reduce whole-life costs, and ensure every pound spent delivers tangible benefits. Report P6, P14

Adopting the HIAMP demonstrates best practice and supports the council's ability to access Department for Transport funding, affecting Halton and other LCRCA councils. Report P16

What happens next

The plan will be submitted to the Executive Board for approval.

Any necessary updates to the plan can be approved under delegated authority by the appropriate Director and Portfolio Holder.

Moving forward, after 2026 Halton will be part of the LCR's new Local Transport Plan (LTP4), due for publication in 2026. Report P76, P92

The money

  • £2.3 billion Approximate value of Halton's highway network Report P4, P13
  • 2.31Bn Gross Replacement Cost of highway assets 2023-24 Report P150
  • 21.065 Total capital funding allocation 2023-24 to 2026-27 (£M) Report P143
  • £8.3b Previous government's Network North road resurfacing funding over 11 years, no longer certain Report P144
  • £500m Government commitment for local highway maintenance in 2025/26 Report P144
  • £900M LCR devolution deal funding over 30 years from November 2015 Report P26

Options considered

  • Chosen: Endorse the HIAMP and submit it to the Executive Board for approval. The plan provides a data-driven, risk-based framework to manage the highway network, support funding bids, and meet legal duties. Report P6, P16

Implications

  • Financial: The plan aims to maximise value for money and secure future Department for Transport funding through the LCRCA's Single Sustainable Transport Settlement. Report P6, P142, P16
  • Climate: Climate change is identified as a key risk, with adaptation to be built in at planning, upgrade, and review stages for highway infrastructure. Report P117, P120, P123
  • Risk: A risk-based approach covers strategic, tactical, and operational risks, including future demand, network resilience, and legal liability. Report P104, P105, P114, P125
  • Legal: The plan supports the council's legal duties under the Highways Act 1980, Environment Protection Act 1990, Equality Act 2010, and other legislation. Report P101
  • Staffing: The Highways and Transportation management team is planned but not yet formed, with its meeting schedule to be confirmed. Report P21
  • Other: The plan covers 606km of roads and 838km of footpaths, but excludes motorways, trunk roads (National Highways), and the Mersey Gateway network (DBFO contract). Report P12, P22

Who and where

  • Halton residents and highway network users Report P5, P131
  • Local businesses and visitors to Halton Report P5
  • Liverpool City Region Combined Authority and its six member local authorities Report P5, 2.2, P16
  • National Highways (responsible for motorways and trunk roads) Report P22
  • Mersey Gateway network (maintained under DBFO contract) Report P22

Timeline

  • 2026-2029: Period the HIAMP covers Report P3
  • 2026: LCR Local Transport Plan (LTP4) due for publication Report P76
  • 2025/26: Government committed £500m for local highway maintenance Report P144
  • 2023-24: Latest Gross Replacement Cost data of £2.31Bn for highway assets Report P150
  • 2021-22: Highways reported at £2.3 billion Report P13
  • 2021: NHT Public Satisfaction Survey: Halton ranked 1st nationally for Highways and Transport overall (out of 111 authorities) Report P138
  • April 2014: Halton became part of the Liverpool City Region Combined Authority Report P23
  • 2007: First Transport Asset Management Plan published Report P17
  • November 2015: Initial LCR devolution deal secured £900M over 30 years Report P26
  • 2017: Previous Highway Asset Management Plan published Report P17

Plain English for the jargon

  • HIAMP: Highway Infrastructure Asset Management Plan
  • LCRCA: Liverpool City Region Combined Authority
  • WGA: Whole of Government Accounts
  • DRC: Depreciated Replacement Cost
  • GRC: Gross Replacement Cost
  • DBFO: Design, Build, Finance and Operate contract
  • CRSTS: Single Sustainable Transport Settlement
  • NHT: National Highways and Transport Public Satisfaction Survey
  • LTP: Local Transport Plan
  • KRN: Key Route Network
  • UKRLG/HMEP: United Kingdom Roads Liaison Group / Highway Maintenance Efficiency Programme
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item34

Resolved

That the Board endorse the Highway Asset Management Plan and its submission to the Executive Board for approval, and granted delegated authority to the appropriate Director and Portfolio Holder to approve any necessary updates.
Word for word from the decision Halton published for this meeting. Source: moderngov.halton.gov.uk

Follow this further

Built from Halton's papers

What the report saysPro

Report to Environment and Regeneration Policy and Performance Board, 84 pages

Halton Borough Council Highway Infrastructure Asset Management Plan (HIAMP) 2026

1 Foreword

As the Portfolio Holder for Environment and Urban Renewal, I am proud to present Halton Borough Council’s Highway Infrastructure Asset Management Plan (HIAMP) for 2026–2029.

Our highway network is one of Halton’s most valuable assets, spanning over 1,400km and valued at approximately £2.3 billion. It plays a vital role in connecting communities, supporting economic growth, and enabling safe and sustainable travel across the borough. This plan outlines our strategic approach to maintaining and improving this essential infrastructure in the face of evolving challenges, including climate change, financial constraints, and increasing demand.

Since our last plan, Halton has become a key member of the Liverpool City Region Combined Authority (LCRCA), aligning our ambitions with regional and national priorities. This HIAMP reflects our commitment to delivering a resilient, safe, and accessible network that meets the needs of our residents, businesses, and visitors—now and into the future.

Through a data-driven, risk-based approach, we aim to maximise value for money, reduce whole-life costs, and ensure that every pound spent delivers tangible benefits. Our focus on preventative maintenance, stakeholder engagement, and environmental responsibility will help us maintain high standards and secure future funding opportunities.

I commend the dedication of our officers and partners in developing this comprehensive plan. It is a testament to Halton’s commitment to transparency, accountability, and continuous improvement in the stewardship of our highway infrastructure.

Councillor Paul Nolan (Portfolio Holder for Environment and Urban Renewal)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highway Infrastructure Asset Management Plan (HIAMP) 2026 ConsultationReport 84 pages DownloadRead as text
PDF
Highways Asset Management PlanReport 6 pages Download

At this meeting

Whole meeting

Who was there

9 of 13 attended
BW
Councillor Bill WoolfallChair, present
PL
Councillor Peter Lloyd JonesVice-Chair, present
VH
Councillor Valerie HillMember, apologies
NH
Councillor Noel HutchinsonMember, apologies
KL
Councillor Kath LoftusMember, present
TM
Councillor Tony McDermottMember, present
SN
Councillor Stef NelsonMember, present
LN
Councillor Louise NolanMember, present
CP
Councillor Carol Plumpton WalshMember, present
GS
Councillor Gareth StocktonMember, apologies
KW
Councillor Kevan WainwrightMember, present
TG
Tim GibbsOfficer, present

All 13 on the meeting page

On this subject at Halton

Search all
  1. Highways Asset Management PlanThis decision
  2. Highways Asset Management PlanApproved
  3. Highways Asset Management PlanApproved
  4. Highways Asset Management PlanApproved
  5. Highways Asset Management PlanApproved

More from Halton Environment and Regeneration Policy and Performance Board

All decisions
MeetingDecisionOutcome
17 Jun 2026 Executive Board MinutesThat the Minutes be received. Decided Open
17 Jun 2026 Local Nature Recovery Strategy and Biodiversity Duty updateThat the Local Nature Recovery Strategy and Biodiversity Duty Update be noted. Noted Open
17 Jun 2026 Annual Report 25/26That the report be noted. Noted Open
11 Feb 2026 Executive Board MinutesThat the Minutes be received. Decided Open
11 Feb 2026 Contaminated and Brownfield Land in HaltonThat the presentation be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies