AI summaryHalton Council's Audit and Governance Board noted the March 2026 progress on the External Auditor's 2024/25 action plan, covering financial sustainability, governance and SEND reform, with a further update due in June 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedBoard noted the 2024/25 AAR Action Plan progress
Money£25m proposed government funding90% of accumulated DSG deficit
What happens nextFurther update in June 2026To be presented to the Board
Who it affectsCouncil, SEND families, residentsAcross financial planning and SEND services

What was decided

The Board noted the progress update on the 2024/25 AAR Action Plan as set out in the Appendix. Report P3

A further update will be presented to the Board in June 2026. Report P4

Why

Good progress has been made with addressing all of the External Auditor's recommendations. Report 3.4

The AAR recommendations, the 2024 Peer Review and the 2025 Cipfa Financial Resilience Review are being merged into a single Improvement Plan to avoid duplication and allow joined-up oversight. Report 3.5

What happens next

A further progress update will be presented to the Audit and Governance Board in June 2026. Report P4

A SEND Reform Plan is to be submitted to the Department for Education by June 2026. Report P53, P60

Recruitment is under way for a new Risk Management Officer to lead risk management for the Council. Report P63

The money

  • 90% (£25m) Proposed government grant funding of the Council's accumulated DSG deficit during 2026/27 Report P53

Implications

  • Financial: The Council faces significant financial challenges in balancing future year budgets and managing spending within budgets, including continued overspending on agency staff. Report 5.1, P32
  • Financial: Reliance on Exceptional Financial Support is being addressed through a Financial Recovery Plan aiming for a sustainable budget position by 2030/31. Report P36, P49
  • Legal: Three statutory recommendations from the Auditor were required to be approved by full Council on 22 October 2025. Report 3.3
  • Risk: A new risk management policy was approved by Executive Board on 11th September 2025, with a new corporate risk register and training being rolled out. Report P63
  • Staffing: The Transformation Delivery Unit is being restructured into a new Change and Innovation Group, with external subject matter experts to be engaged where needed. Report P40, P41
  • Other: SEND Reform Plan to be submitted to the DfE by June 2026, with a specialist Adviser provided by the DfE to support the Council; the statutory override on DSG expires 31st March 2028. Report P53, P54

Who and where

  • Council directorates and members responsible for delivering the action plan Report 3.4, P32, P38, P45, P50, P55, P57, P59, P62, P64, P72, P74, P76
  • Children and young people with SEND and their families Report P50, P51, P60
  • Council staff subject to cyber security and business continuity arrangements Report P55, P56
  • Members of the public benefiting from strengthened governance and contract management Report P72, P76

Timeline

  • September 2025: Assessment against the CIPFA Financial Management Code reported to the Audit and Governance Board. Report P69
  • 11th September 2025: New risk management policy approved by Executive Board. Report P63
  • 24 September 2025: The Auditor's Annual Report 2024/25 was presented to the Audit and Governance Board. Report 3.3
  • 22 October 2025: Three statutory recommendations from the AAR approved by full Council. Report 3.3
  • March 2026: Progress update on the AAR Action Plan presented to the Board (this meeting). Report 1.1, 2.0
  • June 2026: Further AAR Action Plan update to be presented to the Board, and SEND Reform Plan to be submitted to the DfE. Report P4, P53, P60
  • September 2026: Medium Term Financial Strategy 2026-2030 and Financial Recovery Plan reported to Executive Board, two months earlier than usual. Report P35, P36
  • 31st March 2028: Statutory override on DSG expires, with SEND funding expected to move under central control. Report P54

Plain English for the jargon

  • AAR: Auditor's Annual Report, the External Auditor's annual review of the Council's arrangements for economy, efficiency and effectiveness.
  • MTFS: Medium Term Financial Strategy, the Council's multi-year financial planning document.
  • DSG: Dedicated Schools Grant, government funding for schools and related services.
  • EFS: Exceptional Financial Support, exceptional government financial support for councils in difficulty.
  • SEND: Special Educational Needs and Disabilities.
  • SR / KR / IR / PYR: Statutory Recommendation, Key Recommendation, Improvement Recommendation, Previous Year Recommendation from the AAR.
  • S25 report: Section 25 statement on the robustness of budget estimates and adequacy of reserves.
  • PMO: Programme Management Office, the team overseeing the Transformation Programme.
  • MRWA: Merseyside Recycling and Waste Authority, a partner waste authority.
  • AGS: Annual Governance Statement.
  • CRR: Corporate Risk Register.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item34

Resolved

That 1) the progress update regarding the 2024/25 AAR Action Plan as presented in the Appendix be noted; and 2) a further update be presented to the Board in June 2026.
Word for word from the decision Halton published for this meeting. Source: moderngov.halton.gov.uk

Follow this further

Built from Halton's papers

What the report saysPro

Report to Audit and Governance Board, 11 pages

Purpose of report

1.1To consider a progress update regarding the actions being taken to address the recommendations arising from the External Auditor’s 2024/25 Annual Report (AAR).

2.0RECOMMENDED: That

(i) the progress update regarding the 2024/25 AAR Action Plan as presented in the Appendix, be noted; and

(ii) a further update be presented to the Board in June 2026.

3.0SUPPORTING INFORMATION

3.1The Council’s External Auditor, Grant Thornton UK LLP, is required to consider annually whether the Council has put in place proper arrangements to secure economy, efficiency and effectiveness in its use of resources. The Auditor’s Annual Report details the Council’s overall arrangements, as well as providing recommendations regarding any significant weaknesses identified during the review. In addition, improvement recommendations are made which the Council may also decide to implement.

3.2The External Auditor is required to report under three specific criteria, being:

 Financial Sustainability  Governance  Improving Economy, Efficiency and Effectiveness

3.3The Auditor’s Annual Report 2024/25 was presented to the Audit and Governance Board on 24 September 2025. The report included a number of key recommendations and improvement recommendations. It also included three statutory recommendations, which given their importance were required to be approved by Council on 22 October 2025. In addition, the External Auditor highlighted a number of recommendations made for the previous year which were still being addressed.

3.4An Action Plan was prepared to manage the work being undertaken in response to the External Auditor’s recommendations. Good progress has been made with addressing all of the recommendations and the Appendix presents details of progress in relation to the Action Plan.

3.5Given the many similarities, the recommendations from the Annual Auditor’s Report along with the recommendations from the 2024 Peer Review and the 2025 Cipfa Financial Resilience Review, are currently being brought together into a single “Improvement Plan” for the Council. This will avoid duplication and enable progress with implementing all aspects to be overseen, monitored and reported upon in a joined-up manner

4.0POLICY IMPLICATIONS

4.1None.

Financial implications

5.1The AAR 2024/25 provided an external viewpoint on the financial sustainability of the Council. As is now the case for many local authorities, there are significant financial challenges for the Council in balancing future year budgets and managing spending within budgets.

5.2The report identified a number of significant weaknesses regarding the arrangements the Council has in place to secure financial sustainability, governance, and improving economy, efficiency and effectiveness. A number of recommendations were made, for which the Action Plan is being used to manage their implementation.

6.0IMPLICATIONS FOR THE COUNCIL’S PRIORITIES

6.1Improving Health, Promoting Wellbeing and Supporting Greater Independence

6.2Building a Strong, Sustainable Local Economy

6.3Supporting Children, Young People and Families

6.4Tackling Inequality and Helping Those Who Are Most In Need

6.5Working Towards a Greener Future

6.6Valuing and Appreciating Halton and Our Community

There are no implications for any of the Council’s priorities listed above. 7.0 RISK ANALYSIS

7.1The risks that have been considered as part of the Council having in place arrangements to secure economy, efficiency and effectiveness, were detailed in the AAR 2024/25.

8.0EQUALITY AND DIVERSITY ISSUES

8.1None.

9.0CLIMATE CHANGE IMPLICATIONS

9.1None.

10.0LIST OF BACKGROUND PAPERS UNDER SECTION 100D OF THE LOCAL GOVERNMENT ACT 1972

10.1None under the meaning of the Act. 2024/25 ANNUAL AUDITOR’S REPORT – PROGRESS UPDATE MARCH 2026

SR - Statutory Recommendations KR – Key Recommendations IR – Improvement Recommendations PYR – Previous Year Recommendations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
External Auditor's Annual Report 2024/25: Action Plan UpdateReport 11 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 19 attended
RP
Councillor Rob PolhillChair, present
NC
Councillor Neil ConnollyVice-Chair, present
JA
Councillor John AbbottMember, present
VH
Councillor Valerie HillMember, apologies
CH
Councillor Colin HughesMember, present
MR
Councillor Margaret RatcliffeMember, present
ST
Councillor Sharon ThorntonMember, present
MG
Matt GuestCouncil Staff, expected
ED
Ed DawsonOfficer, present
MM
Mervyn MurphyOfficer, present
KK
Ken KeaneOfficer, expected
SB
Stephen BakerOfficer, expected

All 19 on the meeting page

On this subject at Halton

Search all
  1. External Auditor's Annual Report 2024/25 - Action Plan UpdateThis decision
  2. External Auditor's Annual Report 2024/25Noted
  3. External Auditor’s Annual Report 2024/25Noted
  4. External Auditor’s Annual Report 2023/24 – Action Plan UpdateNoted
  5. External Auditor's Annual Report 2023/24Noted
  6. External Auditor’s Annual Report 2023/24Noted

More from Halton Audit and Governance Board

All decisions
MeetingDecisionOutcome
18 Mar 2026 Standards UpdateThat the report be noted and referred to Council for information. Noted Open
18 Mar 2026 Anti-Fraud and Corruption Plan – 2026/27That the Annual Fraud Plan 2026/27 be approved. Approved Open
18 Mar 2026 Risk Management Progress UpdateThat the report and progress made be noted. Noted Open
18 Mar 2026 External Audit Plan – 2025/26 Year-EndThat the contents of the External Audit Plan for the 2025/26 financial year-end, be noted. Noted Open
18 Mar 2026 Informing the External Audit Risk AssessmentThat 1) the proposed responses shown in the Appendix be approved; and 2) the responses be provided to the Council’s E... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies