AI summaryHalton Executive Board approved the Children's Services Asset Masterplan, adding up to £2,156,250 of capital funding to prioritise in-borough placements and cut costly external providers.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCapital funding included in Capital Programme; delegated authority given
Moneyup to £2,156,250Capital cost for sufficiency strategy, phased 2026 to 2028
What happens nextImplementation starts immediatelyEach project to go to Management Team as a business case
Who it affectsNot stated
What was decided
The Executive Board noted the Children's Services Asset Masterplan and agreed to add the required capital funding, up to £2,156,250, to the Capital Programme for the Invest to Save sufficiency project. Report P3, P4
The Executive Director of Children's Services, with the Children and Young People portfolio holder and the Section 151 Officer, was given delegated authority to bring separate business cases to Management Team to draw down funding for each element. Report P5
The Council agreed to include the office space and service delivery requirements from the masterplan within the wider corporate accommodation and assets review. Report P6
Why
Following the May 2024 ILACS inspection, the Council identified that existing assets do not support future service models, placement sufficiency or community based, multidisciplinary delivery, and a strategic review was commissioned. Report 1.1, P8, P9, 3.2, P22
The Council wants to expand high quality in-borough residential and supported accommodation, reduce reliance on high cost out of borough placements, and meet the needs of children, families and care leavers locally. Report P11, P12, 3.3, P15
Officers judged that not investing would hamper the pace of improvement required by inspecting bodies and could create financial, operational and reputational risks for the Council. Report P81, P82, P83
What happens next
Each phase of the sufficiency programme will be brought forward as a separate business case for Management Team approval to release capital funding, with order of delivery able to flex over the three year period. Report 5.1, P18, P51
Delivery will be managed through the Children's Services Transformation Programme governance, with tight financial controls, project assurance, risk management and benefits tracking. Report P20, 3.7, P31, P32, P33
An annual review will check ongoing demand and value for money, and the office and service delivery requirements will feed into the corporate accommodation and assets review. Report P34, P6
The money
up to £2,156,250 Total capital cost of sufficiency strategy to be added to Capital Programme Report P4, P41
£1.475m Investment for Project 1: four homes in partnership with We Are Juno CIC, 12 beds Report P37
£0.331m Investment for Project 2: Park House or Appleton Village replacement, 5 care leaver beds Report P38
£0.206m Investment for Project 3: 16 plus supported accommodation, 10 places Report P39
£0.144m Investment for Project 4: 18 plus supported independent living, 10 flats Report P40
£0.185m per annum for 20 years Estimated borrowing cost across the whole sufficiency programme Report P41
Circa £2.008m cost reduction per annum recurring Forecast annual revenue benefit from reduced external placement costs Report P41
up to £185,322 per year Projected cost of borrowing over 20 year term, including 25 percent contingency Report P51
Options considered
Chosen: Approve the masterplan and add up to £2,156,250 capital funding to the Capital Programme. Supports corporate plan priorities, ILACS improvement, financial sustainability and the Families First Partnership approach Report P4, P5, P78
Rejected: Continue the improvement journey without the required capital funding. Pace and impact would be severely hampered by time, cost and resource constraints, with financial, operational and reputational risks Report P79, P80, P81, P82, P83
Implications
Financial: Borrowing of about £0.185m per year against a forecast recurring revenue saving of about £2.0m per year, based on a worst case cost model with 25 percent contingency. Report P17, P41, P51
Legal: Officers warn that without the investment, the Council may fail its statutory duty under the Children and Family Act 2004 and may not meet Ofsted recommendations from the May 2024 inspection. Report 4.1
Equalities: The Council has noted its Public Sector Equality Duty under the Equality Act 2010 and will keep equalities considerations under review as the masterplan progresses. Report 8.0, 8.1, P74
Risk: Key risks include slow improvement, demand and complexity growth, property and construction cost changes, interest rate changes, and the risk that the partner places children from outside the borough, reducing local savings. Report 7.0, 7.1, P68, P44, P45, P46, P47, P48, P49
Climate: No direct planned climate impact, but the works may bring indirect benefits through reduced travel, online meetings and lower printing. Report 6.5, 9.0, 9.1, P63
Staffing: Office and service delivery changes aim to improve workforce wellbeing, retention, hybrid working, multidisciplinary working and reduced social worker travel time. Report P14, P29
Other: The Council is entering a collaborative partnership with We Are Juno CIC to co-design and share risk on four new children's homes across Runcorn and Widnes. Report P16, 5.1, P37
Who and where
Children in care in Halton needing residential placements Report P12, 3.3, P19
Care leavers aged 16 to 18 and those moving to independence at 18 plus Report P12, P38, P39, P40
Children's Services staff and their managers Report P14, P29
Families of Halton receiving early help and family support Report 3.4, 6.3, P58, P60
Partners in the Families First Partnership, including health, police, education and the voluntary sector Report 3.4, P24
We Are Juno CIC as delivery partner for four children's homes Report 5.1, P37
Timeline
February 2026 to August 2026: Family Help pilot team runs as first multidisciplinary test of the Families First Partnership Report 3.4
Autumn 2026: Park House or Appleton Village replacement and 16 plus supported accommodation due online Report P38, P39
2026 through to 2028: Four children's homes in partnership with We Are Juno CIC phased online Report P16, P37
Summer 2028: 18 plus supported independent living provision due online Report P40
Annual review: Each year the programme checks ongoing demand and value for money Report P20, P34
16th April 2026: Executive Board decision; implementation programme commences with immediate effect if approved Report P84, P85
Plain English for the jargon
ILACS: Inspection of Local Authority Children's Services, the Ofsted framework used to judge children's services
CSAM: Children's Services Asset Management Masterplan, the strategic review of property and capital needs
Invest to Save: Capital spending that is expected to be recovered through lower running costs, here reduced external placement costs
Families First Partnership: Government programme for partner wide, community based, multidisciplinary support to families
We Are Juno CIC: Community interest company partnering with the Council to deliver four children's homes in Runcorn and Widnes
PSED: Public Sector Equality Duty under the Equality Act 2010
Section 151 Officer: The Council officer with statutory responsibility for proper financial administration
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item119
Resolved
That 1) the Children’s Services Asset Masterplan be noted; 2) Council include the capital funding required to meet the objectives of the Children’s Social Care Placement and Sufficiency Invest to Save Project within the Capital Programme at an estimated cost of up to £2,156,250 as outlined in paragraph 5.1; 3) the Executive Director of Children’s Services, in consultation with the Portfolio Holder for Children and Young People and the Section 151 Officer, is given delegated authority to present a full business case to Management Team for approval to draw down capital funding for each element of the sufficiency strategy as outlined in paragraph 5.1; and Council include requirements for the Children’s Services Asset Masterplan relating to ‘Office Space and Service Provision’ within the overall Corporate Strategy for Halton’s Accommodation and Assets review.
Word for word from the decision Halton published for this meeting.Source: moderngov.halton.gov.uk
1.1Following the recent ‘Children’s Services Asset Review’, this report provides a strategic overview of capital funding required to align Children’s Services assets with the needs of children and families in Halton.
2.0RECOMMENDATION: That
1) The Children’s Services Asset Masterplan be noted.
2) Council include the capital funding required to meet the objectives of the Children’s Social Care Placement and Sufficiency Strategy Invest to Save project within the Capital Programme at an estimated cost of up to £2,156,250 as outlined in paragraph 5.1.
3) The Executive Director of Children’s Services, in consultation with the Lead Member for Children & Young People and the Section 151 Officer, is given delegated authority to present a full business case to Management Team for approval to draw down capital funding for each element of the sufficiency strategy as outlined in paragraph 5.1.
4) Council include requirements for the Children’s Services Asset Masterplan relating to ‘Office Space and Service Provision’ within the overall Corporate Strategy for Halton’s Accommodation & Assets review. 3.0 SUPPORTING INFORMATION
Executive summary
This report presents the Children’s Services Asset Management Masterplan (CSAM) and seeks Executive Board support to progress the capital investment required to align Children’s Services assets with service redesign, statutory improvement requirements, and the needs of children and families in Halton.
Context Following the ILACS inspection (May 2024), Children’s Services has delivered significant stabilisation and improvement activity, underpinned by: The Children’s Services Improvement Plan Workforce stabilisation and service redesign The Children’s Social Care Placement and Sufficiency Strategy The Families First Partnership Programme
As this work progressed, it became clear that existing assets do not adequately support future service models, placement sufficiency, or community based, multidisciplinary delivery. ICENI Projects were therefore commissioned in October 2025 to undertake a strategic asset review, culminating in the CSAM.
The Asset Masterplan The CSAM identifies two core asset requirements:
1. Placement Sufficiency Assets (Priority)
Expanding high quality, in-borough residential and supported accommodation to reduce reliance on high cost, out of borough placements.
2. Office and Service Delivery Space
Ensuring fit for purpose accommodation to support Families First delivery, redesigned services, workforce wellbeing and multiagency working (to be aligned with the Council’s wider corporate accommodation strategy).
Given inspection expectations, financial pressures and service risk, placement sufficiency is the immediate priority.
Proposed Capital Programme – Invest to Save The sufficiency element of the CSAM proposes a phased Invest to Save programme (2026–2028) comprising: Four children’s homes (12 beds) delivered through a partnership with We Are Juno CIC Replacement and expansion of care leaver provision (Park House / Appleton Village) New 16+ supported accommodation 18+ supported independent living provision
Capital investment required: up to £2.156m Estimated borrowing cost: c. £0.185m per annum Forecast recurring revenue benefit: c. £2.0m per annum through reduced external placement costs
The cost model applies a worst case scenario to avoid overstating return on investment. Each phase will be brought forward as separate business cases for approval.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Highway Asset Management Plan (HAMP)That 1) approves the Highway Asset Management Plan (HAMP) 2026-2029 (contained in Appendix A) for adoption and public...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.