Treasury Management Annual Report 2025-26

Agreed Executive 1 paper

AI summaryHalton Executive Board agreed the 2025/26 Treasury Management Annual Report, which shows investment income £1.691m over target and total treasury costs £1.810m under budget.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedTreasury Management Annual Report 2025/26 reviewed and agreed
Money£1.810m under budgetTotal treasury management costs for 2025/26 came in under budget
What happens nextNo reschedulingNo debt rescheduling undertaken in the period
Who it affectsCouncil financesRevenue budget and capital programme support all council priorities

What was decided

The Executive Board reviewed and agreed the Treasury Management Annual Report for 2025/26, covering borrowing and investment activity on the money market during the year. Report 2.0, 1.1

Why

The Council has a statutory duty to determine and keep under review affordable borrowing limits, with Treasury and Prudential Indicators set in the Treasury Management Strategy Statement. Report 3.15, P34

Investment returns exceeded the majority of benchmark rates for investments of one month and over during the second half of the year, helped by holding longer-duration investments and taking advantage of higher local authority market rates. Report 3.10, P25

What happens next

Treasury management will continue to operate within the Treasury Management Policy and annual strategy, with security of capital, liquidity and yield as investment priorities. Report 3.13, 3.14, 7.1

Short-term borrowing taken in 2024/25 has had to be replaced in early 2026/27 at higher rates, which will feed into higher borrowing costs in 2026/27. Report 3.12

The money

  • £1.810m Total treasury management underspend against budget in 2025/26 Report 3.11, P29
  • £50m Borrowed from the Public Works Loans Board in February and March 2025 Report 3.12
  • £4.7m Increase in PFI liability for The Grange School after IFRS16 restatement Report 3.17
  • £46.1m Increase in PFI liability for the Mersey Gateway Bridge after IFRS16 restatement Report 3.17

Implications

  • Financial: Treasury management costs came in £1.810m under budget overall in 2025/26, with £1.691m of that from investment income. Report 3.11, P29
  • Financial: Replacement of short-term borrowing in early 2026/27, after rates rose due to the Middle East conflict, will push up borrowing costs in 2026/27. Report 3.12
  • Legal: The Council has a statutory duty to determine and keep under review affordable borrowing limits, set out through the Treasury and Prudential Indicators. Report 3.15
  • Risk: Main treasury management risks are security of investment and volatility of return, managed through the Treasury Management Policy and annual strategy. Report 7.1
  • Other: Adoption of IFRS16 increased PFI liabilities and required updates to the Operational Boundary and Authorised Limit, including a recorded breach at the end of 2024/25. Report 3.16, 3.17
  • Equalities: No equality and diversity implications identified. Report 8.0
  • Climate: No climate change implications identified. Report 9.0, 9.1

Who and where

  • The Council's revenue budget and capital programme, which support all of the Council's stated priorities Report 6.1, 6.2, 6.3, 6.4, 6.5, 6.6
  • The Council's PFI counterparties for The Grange School and the Mersey Gateway Bridge, through restated liabilities Report 3.17
  • Treasury management counterparties on the local authority money market Report 3.10, 3.12

Timeline

  • February and March 2025: Council borrowed £50m from the Public Works Loans Board as rates fell Report 3.12
  • 5th March 2025: Treasury Management Strategy Statement 2025/26 approved by the Council Report 3.13
  • April 2025: Bank of England base rate starts the year at 4.50% Report 3.7, P13
  • May 2025: Base rate cut by 0.25% Report 3.7
  • August 2025: Base rate cut by 0.25% Report 3.7
  • July to September 2025: CPI inflation peaks at 3.8% Report 3.2
  • December 2025: Base rate cut to 3.75%, where it has remained since Report 3.7
  • January and February 2026: CPI inflation dips to 3%; core inflation 3.2% in February Report 3.2
  • March 2026: Operational Boundary and Authorised Limit updated to reflect IFRS16 PFI restatements Report 3.17
  • 9 July 2026: Executive Board meeting agrees the Treasury Management Annual Report 2025/26

Plain English for the jargon

  • TMSS: Treasury Management Strategy Statement, the Council's annual borrowing and investment strategy
  • PWLB: Public Works Loan Board, a UK government body that lends to local authorities
  • CFR: Capital Financing Requirement, a measure of the Council's underlying need to borrow for capital purposes
  • PFI: Private Finance Initiative, a form of public-private partnership used to fund infrastructure
  • IFRS16: International Financial Reporting Standard 16 on leases, which changed how PFI liabilities are calculated
  • Operational Boundary: Self-imposed limit on expected maximum debt level, used as an early warning
  • Authorised Limit: Statutory ceiling beyond which external debt must not go
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14

Resolved

That the report be reviewed and agreed.
Word for word from the decision Halton published for this meeting. Source: moderngov.halton.gov.uk

Follow this further

Built from Halton's papers

What the report saysPro

Report to Executive Board, 8 pages

Purpose of report

1.1The report provides an update regarding borrowing and investment activities undertaken on the money market during 2025/26 as required by the Treasury Management Policy.

2.0RECOMMENDATION: That the report be reviewed and agreed.

3.0SUPPORTING INFORMATION

Economic Outlook

3.1The following analysis of the economic situation has been provided by MUFG Asset Services, the Council’s treasury management advisors.

3.2UK inflation has proved somewhat stubborn throughout 2025/26. Having started the financial year at 3.5% in April, the CPI measure of inflation peaked at 3.8% from July to September, before dipping to 3% in January and February. Core inflation picked up to 3.2% in February, from 3.1%, and the recent upward pressure on energy costs could see CPI inflation breach 4.5% later this year.

3.3Against this backdrop, the continued lack of progress in ending the Russian invasion of Ukraine, and the potentially negative implications for global growth as a consequence of the implementation of US tariff policies, Bank of England base rate reductions look limited for the remainder of 2026. The base rate currently stands at 3.75%.

3.4Borrowing became increasingly expensive during 2025/26 and into early 2026/27. Gilt yields rose materially in March 2026, more than reversing the falls earlier in the financial year. Additionally, the public finances have remained under pressure. The higher-than-expected public net sector borrowing of £14.3bn in February was £2.2bn above last February’s outturn. The combination of some energy price support and pressures from higher inflation amid the ongoing energy price shock, higher interest rates and a weaker economy will ultimately put borrowing on an upward trend. With the rise in energy prices possibly pushing the Retail Prices Index inflation up to a peak of 5.7%, debt interest repayments will increase by about £10bn. A weaker growth profile, higher inflation, higher interest rates and gilt yields could erode about £11bn of the Chancellor’s £23.6bn headroom.

3.5The loosening in the labour market continues to bear down on wage growth. The growth rate of average earnings including bonuses slowed from 4.2% in December to 3.9% in January. Meanwhile, excluding bonuses, private earnings growth continued to fall from 3.4% to 3.3%.

3.6The FTSE 100 experienced another volatile quarter, surging to an all-time high of around 10,900 in late February, leaving it up 10% from the start of 2026, before giving back most of those gains in March after the outbreak of the Middle East conflict. That pullback leaves the index at around 10,176 at the end of the quarter. For context it was at 8,582 at the start of April. The £ has stayed relatively resilient at $1.33, strengthening from $1.29 back in April.

Interest Rate Forecast

3.7The following forecast has been provided by MUFG Asset Services for the following three years.

During the 2025/26 financial year, the base rate was reduced three times. From 4.50% in April 2025, the rate dropped 0.25% in May 2025 and August 2025, before dropping to 3.75% in December 2025. The rate has remained unchanged between December 2025 and May 2026. Treasury Management Annual Report 2025/26

3.8The borrowing rates from September 2025 to March 2026 are shown below:

Short-Term Borrowing Rates

Sep Oct Nov Dec Jan Feb Mar % % % % % % % Base Rate 4.00 4.00 4.00 3.75 3.75 3.75 3.75 Call Money (Market) 3.95 3.90 3.90 3.65 3.70 3.65 3.80 1 Month (Market) 3.95 3.95 3.95 3.75 3.70 3.70 3.75 3 Month (Market) 4.05 4.05 3.90 3.85 3.75 3.65 3.95

Longer-Term Borrowing Rates

Sep Oct Nov Dec Jan Feb Mar % % % % % % % 1 Year (PWLB) 4.58 4.46 4.44 4.37 4.37 4.25 5.04 10 Year (PWLB) 5.53 5.26 5.29 5.34 5.38 5.14 5.72 25 Year (PWLB) 6.23 5.92 5.91 5.95 6.01 5.80 6.29

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Treasury Management Annual Report 2025-26Report 8 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 13 attended
AB
Councillor Angela BallChair, present
ED
Councillor Eddie DourleyMember, apologies
RL
Councillor Rosie LeckMember, present
TM
Councillor Tom McInerneyMember, present
PN
Councillor Paul NolanMember, present
DT
Councillor Dave ThompsonMember, apologies
AW
Councillor Andrea WallMember, present
MW
Councillor Mike WhartonMember, apologies
MR
Mark ReaneyOfficer, expected
ED
Ed DawsonOfficer, expected
TG
Tim GibbsOfficer, expected
ZF
Zoe FearonOfficer, expected

All 13 on the meeting page

On this subject at Halton

Search all
  1. Treasury Management Annual Report 2025-26This decision
  2. Treasury Management Strategy Statement 2026/27 (EXB95 refers)Approved
  3. Treasury Management Strategy Statement 2026/27Approved
  4. Treasury Management 2025-26 Half Year UpdateNoted
  5. Treasury Management Annual Report 2024-25Noted
  6. Treasury Management Strategy Statement 2025/26Approved

More from Halton Executive Board

All decisions
MeetingDecisionOutcome
22 Oct 2026 Halton Housing Trust Annual ReportThe Board thanked Halton Housing for the presentation and noted the report. Noted Open
22 Oct 2026 Highway Asset Management Plan (HAMP)That 1) approves the Highway Asset Management Plan (HAMP) 2026-2029 (contained in Appendix A) for adoption and public... Approved Open
22 Oct 2026 Waste Management and Recycling Contract - Key DecisionThat 1) Members approve the continued delegation of defined elements of the Council’s Waste Disposal Authority functi... Approved Open
22 Oct 2026 Waste Strategy and Household Waste Collection PolicyThat 1) Members approve the draft Waste Management Strategy and the draft Household Waste & Recycling Collection Poli... Approved Open