Executive Board, Thursday 17 September 2026

2026/27 Spending as at 31 July 2026

Approved Executive 1 paper

AI summaryHalton Executive Board noted 2026/27 net spending is forecast to come in £3.608m under budget, with spend £0.656m below profile at 31 July. Directors will keep delivering approved savings and find more to cut reliance on £33.873m Exceptional Financial Support.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedNet spending £0.656m below profile at 31 July 2026
Money£3.608m forecast underspendAgainst a 2026/27 budget that used £33.873m EFS
What happens nextContinue savings delivery and searchReport shared with Policy and Performance Boards
Who it affectsCouncil directorates and service usersIncludes care, children's and education services

What was decided

Executive Directors will keep implementing the approved 2026/27 saving proposals set out in Appendix 4. Report P3

Executive Directors will keep looking for further spending cuts or extra income to reduce the council wide net spend position. Report P4

The report will be shared with each Policy and Performance Board so they can see the full financial picture alongside their own service areas. Report P5

Why

Forecast outturn underspend of £3.608m is a significant improvement on the £0.805m forecast at the end of May 2026, driven by changes in Children's Social Care, the Change Delivery Unit, and lower financing costs. Report 3.1, P10

The 2026/27 budget relied on £33.873m of Exceptional Financial Support from government, and any underspend reduces that ask. Report 3.2, 3.7

What happens next

Directors will keep working through the RAG rated savings in Appendix 4 and flag further reductions or income opportunities. Report 3.12, 4.2

The council will review earmarked reserves to see whether any can be released in part or in full. Report 3.19

The council will address the recommendations from the CIPFA external assurance review published on 18 August 2026. Report 3.6

The money

  • £0.656m Spending below approved budget to 31 July 2026 Report 3.1
  • £3.608m Forecast net underspend for 2026/27 Report 3.1, 4.1
  • £33.873m Exceptional Financial Support requested for 2026/27 Report 3.2, 3.7
  • £10.000m EFS used in 2024/25 Report 3.7
  • £14.700m EFS used in 2025/26 Report 3.7
  • £58.573m Total EFS used to date across 2024/25 to 2026/27 Report 3.7, 3.8
  • £35 million Capitalisation direction Government was minded to approve Report 3.5
  • £5.158m Savings approved for 2026/27 Report 3.11
  • £8.913m Total efficiency targets including agreed savings Report 3.12
  • £0.500m Contingency set aside for pay award above 3% Report 3.10
  • £1.758m Potential cost of 9 prospective children's residential placements Report 3.4, P12
  • £0.542m Approximate cost of a 1% swing in adult care demand Report 3.4, P12
  • £1.273m Forecast overspend on Adult Social Care Community Care Report P41, P122, P124
  • £0.502m Forecast overspend on Education, Inclusion and Provision Report 3.15, P51, P161
  • £5.186m General Reserve balance at 31 July 2026 Report 3.18
  • £8.584m Capital spending to 31 July 2026 Report 3.22
  • £43.380m Total 2026/27 Capital Programme assuming 20% slippage Report 3.22
  • £178.850m Dedicated Schools Grant settlement 2026/27 Report 3.23
  • £31.877m High Needs Block allocation 2026/27 Report 3.23, 3.24
  • £42.329m Forecast High Needs spending 2026/27 Report 3.24
  • £1.212m Previous years' council tax debt collected so far in 2026/27 Report 3.16, P67
  • £0.290m Previous years' business rate debt collected so far in 2026/27 Report 3.17, P69

Options considered

  • Chosen: Continue implementing approved 2026/27 savings in Appendix 4. Improves outturn position and reduces call on Exceptional Financial Support Report P3, 3.2, 4.2
  • Chosen: Directors identify further spending reductions or income. Council still in first half of year and demand could rise Report P4, 3.4, 4.3
  • Chosen: Share the report with each Policy and Performance Board. Ensure members understand the whole council position Report P5

Implications

  • Financial: The 2026/27 budget uses £33.873m of Exceptional Financial Support, and any underspend reduces that ask; the total EFS cost over the term is significant. Report 3.2, 3.7, 3.8
  • Financial: Adult Social Care Community Care is forecast to be £1.273m over budget for the year. Report P41, P122, P124
  • Financial: Education, Inclusion and Provision is forecast to overspend by £0.502m, mainly on school transport, inter authority income and supplies and services. Report 3.15, P51, P161
  • Financial: Council tax collection at 35.75% is 0.41% lower than the same point last year, while business rate collection at 42.3% is 1.61% higher. Report 3.16, 3.17
  • Risk: A 3.3% pay offer exceeds the 3% budgeted, and only £0.500m contingency is set aside for the extra cost. Report 3.10
  • Risk: The High Needs DSG deficit may fall on the General Fund from March 2028; further clarification from government is awaited.
  • Risk: Children's residential care forecast includes 9 prospective placements worth up to £1.758m that are not yet sourced. Report 3.4, P12
  • Staffing: Children and Families Department continues to face recruitment difficulty, with agency staff used to cover vacancies; a Social Work Academy and market supplements are supporting recruitment. Report 3.15, P30, P31

Who and where

  • All Halton Borough Council directorates, which must keep finding savings Report P3, P4, 3.12
  • Adult social care service users in residential, nursing, domiciliary and direct payment services Report P42, P47, P49
  • Children in care, including those placed in residential and fostering settings Report P35, P36, P37
  • SEN pupils and families using school transport Report P52, P53
  • Council taxpayers and business rate payers in Halton Report 3.16, 3.17
  • Policy and Performance Board members receiving the report Report P5

Timeline

  • 23 February 2026: Government letter confirming it was minded to approve a capitalisation direction of up to £35 million Report 3.5
  • March 2026: Council approved £5.158m of savings for 2026/27 Report 3.11
  • Spring 2026: CIPFA external assurance review undertaken Report 3.6
  • 4 March 2026: Council approved the 2026/27 Capital Programme Report 3.21
  • 18 June 2026: Capital Programme update taken to Executive Board Report 3.21
  • 31 July 2026: Date of the spending figures in this report Report 3.1, 3.22
  • 18 August 2026: CIPFA external assurance review published Report 3.6
  • September 2026: Charges begin for all telehealthcare users; new specialist dementia unit at St Luke's expected to be operational Report P194, P197
  • April 2027: Planned implementation of restructures within Open Spaces in Community and Greenspaces Report P204
  • March 2028: Earliest point the High Needs DSG deficit could fall on the council's General Fund

Plain English for the jargon

  • EFS: Exceptional Financial Support: government permission to treat revenue spending as capital, used here to balance the 2026/27 budget
  • DSG: Dedicated Schools Grant: ring fenced government funding for schools, broken into Schools, Central Schools Services, High Needs and Early Years blocks
  • High Needs block: Part of the DSG that funds SEND support for children and young people with complex needs
  • CIPFA: Chartered Institute of Public Finance and Accountancy, which carried out the external assurance review
  • IFA: Independent Fostering Agency, used where in house foster carers are not available
  • EHCP: Education, Health and Care Plan for children and young people with special educational needs
  • UASC: Unaccompanied Asylum Seeking Children, whose costs are excluded from the residential care trend analysis
  • RAG rating: Red, Amber, Green progress rating used to track delivery of agreed savings
  • IATE: In Addition to the Establishment, where staff are paid over and above the funded establishment
  • Better Care Fund (BCF): Pooled budget between the council and NHS to join up health and social care
  • Section 74 charges: Charges levied on utility companies for overrunning or non compliant street works permits
  • MARS: Mutually Agreed Resignation Scheme referenced for the Open Spaces restructure
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item27

Resolved

That 1) Executive Directors continue to implement the approval 2026/27 saving proposals as detailed in Appendix 4; 2) Executive Directors continue to identify areas where they can further reduce their directorate’s spending or generate income, in order to reduce the council wide net spend position; and 3) this report be shared with each Policy and Performance Board, in order to ensure they have a full appreciation of the council wide financial position, in addition to their specific areas of responsibility.
Word for word from the decision Halton published for this meeting. Source: moderngov.halton.gov.uk

Follow this further

Built from Halton's papers

What the report saysPro

Report to Executive Board, 69 pages

Purpose of report

1.1To report the Council’s overall revenue net spend position as at 31 July 2026 together with a 2026/27 forecast outturn position.

2.0RECOMMENDED: That;

(i) Executive Directors continue to implement the approved 2026/27 saving proposals as detailed in Appendix 4;

(ii) Executive Directors continue to identify areas where they can further reduce their directorate’s spending or generate income, in order to reduce the council wide net spend position

(iii) This report be shared with each Policy and Performance Board, in order to ensure they have a full appreciation of the councilwide financial position, in addition to their specific areas of responsibility.

3.0SUPPORTING INFORMATION

Revenue Spending

3.1Appendix 1 presents a summary of spending against the operational revenue budget up to 31 July 2026 and Appendix 2 provides detailed figures for each individual Department. In overall terms, net Council spending as at 31 July 2026 is £0.656m below the approved budget. The outturn forecast for the year estimates that net spending will be under budget by £3.608m based on known information.

3.2The forecast presents a positive position for the Council, alongside this it should be remembered that in setting a budget for 2026/27 Council requested Exceptional Financial Support of £33.873m, to provide a balanced position. Any underspend against budget in the current year will reduce the EFS ask, therefore continued action should be taken to review areas where the Council net forecast spend position can be further reduced. 3.3 The forecast outturn underspend position of £3.608m represents a significant improvement on the forecast underspend of £0.805 calculated at the end of May 2026. This is largely linked to three areas:

 Children’s Social Care – A re-focussed forecast of costs against staffing and residential care.  Change Delivery Unit – Reduced forecast relating to supplies and services across the unit. It is forecast costs will be in the region of £0.040m against a budget of £0.297m.  Financing costs relating to historical spend on the capital programme will be approximately £0.500m lower than forecast at the end of May 2026.

3.4The financial forecast outturn at 31 July 2026 continues to represent a prudent position given the Council is still in the first half of the financial year and any increase in demand or costs at this point will have a material impact on the rest of the year. There are a number of areas where there is a possibility spend for the year will be less than forecast but it will only be later in the year before confirming this when there is greater confidence in the forecast position. Prudence has been applied within the following areas:

 Projection of children in residential care includes 9 prospective placements which are yet to be sourced and agreed, which equates to £1.758m potential cost if placed.  Community Care demand has been factored into the forecast at 3% for residential, domiciliary care and direct payments. It is estimated on current prices a 1% swing in demand equates to approximately £0.542m. The demand growth isn’t currently being seen but there is the risk as autumn and winter months approach there will be an increase in demand. In applying a prudent position for the current it is important to also be mindful of the risk to complexity of care and the increased cost this brings.

3.5On 23 February 2026 Government issued a letter to the Council confirming it was minded to approve a capitalisation direction of a total not exceeding £35 million covering financial year 2026/27.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2026/27 Spending as at 31 July 2026Report 69 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 18 attended
AB
Councillor Angela BallChair, present
NC
Councillor Neil ConnollyMember, present
ED
Councillor Eddie DourleyMember, present
RL
Councillor Rosie LeckMember, present
TM
Councillor Tom McInerneyMember, present
PN
Councillor Paul NolanMember, present
DT
Councillor Dave ThompsonMember, present
MW
Councillor Mike WhartonMember, present
VY
Vicki YarwoodCouncil Staff, expected
MR
Mark ReaneyOfficer, expected
ED
Ed DawsonOfficer, expected
TG
Tim GibbsOfficer, expected

All 18 on the meeting page

On this subject at Halton

Search all
  1. 2026/27 Spending as at 31 July 2026This decision
  2. 25/26 Councilwide Spending as at 31 July 2025 (Minute EXB 32 refers)Approved
  3. 2025/26 Councilwide Spending as at 31 July 2025Approved
  4. 2024/25 Spending as at 31 July 2024 and Medium Term Financial Forecast - EXB25Approved
  5. 2024/25 Spending as at 31 July 2024 and Medium Term Financial ForecastApproved

More from Halton Executive Board

All decisions
MeetingDecisionOutcome
22 Oct 2026 Halton Housing Trust Annual ReportThe Board thanked Halton Housing for the presentation and noted the report. Noted Open
22 Oct 2026 Highway Asset Management Plan (HAMP)That 1) approves the Highway Asset Management Plan (HAMP) 2026-2029 (contained in Appendix A) for adoption and public... Approved Open
22 Oct 2026 Waste Management and Recycling Contract - Key DecisionThat 1) Members approve the continued delegation of defined elements of the Council’s Waste Disposal Authority functi... Approved Open
22 Oct 2026 Waste Strategy and Household Waste Collection PolicyThat 1) Members approve the draft Waste Management Strategy and the draft Household Waste & Recycling Collection Poli... Approved Open