Resolved
RESOLVED THAT The report be noted.
Audit Committee (2006 - 2010) noted this item on Monday 30 November 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED THAT The report be noted.
That the Committee approves the latest iteration of the corporate risk register. 1. PURPOSE
1.1This report informs Members on the overall arrangements and performance of risk management across the council. Effective risk management helps the council to achieve its objectives and is a key component of the Corporate Area Assessment and the 'Use of Resources' judgement and is also required by the Account and Audit Regulations 2003.
2.1The Finance and Corporate Services Department acts as the lead Department on risk management supported by the Principal Consultant Risk Management. Departmental Directors act as Risk Champions in their own service areas to support the process across all levels of the authority.
2.2Risk Management is intrinsically important to the council and is a process that demonstrably helps the council achieve its business objectives through the early identification, analysis and economic control of potential hazards. It achieves value for money and efficiencies by intervening at an early stage in projects through the proactive use of risk registers using mitigating techniques that contain spend and help to ensure the successful delivery of projects.
2.3Risk management is also evidence in support of producing the Annual Assurance Statement, an auditable process that seeks to determine confidence in the control mechanisms established across the operational activities of the council.
3. Building Schools for the Future
3.1Gateway Reviews are mandatory in the Building Schools for the Future (BSF) programme. The Gateway Review process in local government is managed by an organisation known as 4ps. A Gateway review of a procurement project is carried out at key decision points by a team of experienced people who are independent of the project team. The process provides assurance to a project owner that their project can progress successfully to the next stage. Gateways have been designed to support projects that procure services, construction/ property projects and IT- enabled business change projects. In the past quarter a Gateway review has been undertaken for our own BSF project.
3.2Engagement, ownership, management and delivery of risk management as part of daily business practice in such a substantial project are essential. Key documents and plans relating to the project were shared with the review team and a number of officers were interviewed. This approach sought to recognise how embedded the process is as part of the overall project.
3.3The Review Team found that the Project is fundamentally sound. They confirm evidence that a substantial amount of hard work and commitment has been instrumental in getting the Project to the point of the Gateway review. There is recognition, however, that there is still much to do and the Review Team is impressed by the willingness of the Programme Team in particular to be open to help and support and responsive to new challenges. There is widespread respect and trust in the Programme Team to deliver a successful outcome for the Borough.
3.4The Project still has its challenges, however. Affordability remains an issue as there are a number of key dependencies such as planning, abnormal and decant issues, which will inevitably put strain on the available budgets as the Authority looks to manage limited funds with its aspirations. Enhanced risk management will be key to achieving this.
3.5Overall the gateway review rated the project as amber/green where successful delivery appears probable however constant attention will be needed to ensure risks do not materialise into major issues threatening delivery.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Sumnmary of BSF Gateway Review RecommendationsAppendix 1 | 19 KB | Download |
PDF |
Corporate Risk RegisterAppendix 2 | 82 KB | Download |
PDF |
RISK MANAGEMENT PROGRESS REPORTReport | 84 KB | DownloadRead as text |
Follow Audit Committee (2006 - 2010) at Hammersmith & Fulham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Mar 2010 | Minutes and ActionsRESOLVED THAT: The minutes of the meeting of the Committee held on 30 November 2009 be agreed as a true and accurate ... | Agreed | Open |
| 23 Mar 2010 | Matters arising from the minutes of 30 november 2009RESOLVED THAT (1) Officers be requested to write to the Chairman with regard to progress on Health Inequalities; (2) ... | Noted | Open |
| 23 Mar 2010 | Audit Opinion Plan for London Borough of Hammersmith & FulhamRESOLVED THAT The report be noted. | Noted | Open |
| 23 Mar 2010 | Audit Opinion Plan For the London Borough of Hammersmith and Fulham Pension FundRESOLVED THAT The report be noted. | Noted | Open |
| 23 Mar 2010 | Grants Report 2008/09RESOLVED THAT That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.