That the report be noted 1 Lean Programme Context
1.1H&F has a vision to become a “lean organisation” with lean systems thinking a core principle of transformational change over the short and medium term.
1.2As a first step towards achieving this vision, H&F has initiated a lean programme consisting of 2 pathfinder projects designed to prove the lean concept and create a critical mass of H&F resource with the capability and experience to initiate further roll outs as required. One of these two pathfinder projects is focussing on H&F Direct (specifically the Revenues and Benefits service) with a view to improving existing performance levels in a service that has reduced staffing levels by 35% over the last 5 years, whilst workloads have increased due to the recession.
2 Project Context
2.1The Revenues and Benefits services were merged into a single service in 2008. Pre-2008, the revenues services was a strong performing service against other London authorities, however, the Benefits service had experienced declining performance levels and an overspend of c.£1m per annum in 2006 which had been rectified in 2007/8.. The service has experienced an operating budget reduction of 45% between 06/07 and 11/12 resulting in significant operational strain and a steadily increasing ‘backlog’ of work.
2.2The project is required to ensure the sustainability of service delivery now and over the next 3 years to 13/14. It is not anticipated that this project will release additional cashable savings in the short term.
3 Project Scope
3.1The project has the following scope: • Council Tax Collection Processes • Council Tax Benefit Processes • Housing Benefit Processes
4 Skills Transfer to H&F
4.1The project is being supported by Ernst &Young who will ensure H&F Direct staff involved in project delivery are given the formal training, coaching and experiential learning required to deliver similar projects within H&F Direct or elsewhere in the Council. Project team members are following an Ernst & Young lean curriculum and each have their own skills transfer contracts to monitor and assure progress. The H&F OD service are acting as independent monitors of team members skills transfer contracts.
5 Timeline and Methodology
5.1The project is 4 months in duration and is scheduled to finish September 23rd at which point full implementation of the recommendations and solutions will begin.
5.2The project methodology is set out below:
Design (5 Identify (2 wks) Diagnose (5 wks) Deliver (4 wks) wks)
Baseline Test and capability and Demand Design Stabilise Project performance Root and the Lean mobilisation cause Set up custome future Readiness and core validatio test env. r state Business case training n analysis Map the flow and service development and identify the w aste implementation planning
6 Progress and Findings to Date
6.1The project is currently in the ‘Deliver’ stage which will run to the 23rd September 2011.
6.2There is one aspect of the ‘Design’ phase that has yet to be completed (see below), but it was decided it would be more beneficial to continue with the pilot team phase as planned.
6.3The project has currently delivered:
Identify Phase: • Core team (H&F staff to be involved in project delivery) selected an mobilised • 2 day lean training course delivered by Ernst & Young to all core team members • Project scope agreed and PID signed off • Skills transfer contracts agreed
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
H & F Direct Lean Pathfinder ProjectReport | 73 KB | DownloadRead as text |
Follow Audit Committee at Hammersmith & Fulham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Jun 2026 | Minutes and ActionsRESOLVED That the minutes of the meeting held on 16 March 2026 were agreed as accurate record. | Agreed | Open |
| 23 Jun 2026 | Statement of Accounts 2025/26 UpdateRESOLVED That the Committee noted the verbal update. | Noted | Open |
| 23 Jun 2026 | External Audit Plan (Pension Fund) 2025/26RESOLVED That the Committee agreed to note the External Audit Plan 2025/26 for the London Borough of Hammersmith & Fu... | Agreed | Open |
| 23 Jun 2026 | Annual Report of the Audit Committee for Municipal Year 2025/26RESOLVED That the Committee noted the report. | Noted | Open |
| 23 Jun 2026 | Work Programme for 2026/27RESOLVED That the Committee noted the Work Programme for 2026/27. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.