that the Hammersmith and Fulham Bridge Partnership Performance Annual Report and the importance of IT is a key enabler for transformation and tri-borough working be noted. that , under Section 100A (4) of the Local Government Act 1972, the public and press be excluded from the meeting during the consideration of the following items of business, on the grounds that they contain the likely disclosure of exempt information, as defined in paragraph 3 of Schedule 12A of the said Act, and that the public interest in maintaining the exemption currently outweighs the public interest in disclosing the information. A separate report on an exempt Overview and Scrutiny Board agenda provided information relating to the financial or business affairs of HFBP and the Council.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
OVERVIEW AND SCRUTINY BOARD DATE TITLE Wards 7 December 2011 H&F Bridge Partnership performance annual report All
SYNOPSIS This report sets out the performance of H&F Bridge Partnership in both service and financial terms and establishes its value for money to the council over the period 2010/2011.
IT is critical to service delivery improvements for the council. The IT service provided by H&F Bridge Partnership (HFBP) is of a high calibre as demonstrated by industry standard benchmarking. Nonetheless, active management of HFBP is required to ensure value for money is maintained and improved.
A separate report on the exempt Scrutiny Board agenda provides information relating to the financial or business affairs of HFBP and the Council.
CONTRIBUTORS RECOMMENDATION(S):
Susan Rossam The Overview and Scrutiny Select Board is Partnership Director asked to note the report. and Katrine Nowicki Operations Manager, H&F Bridge Partnership
CONTACT NEXT STEPS
Jackie Hudson HFBP performance is used in the planning Assistant Director process for Continuous Service Improvement. Procurement and IT strategy, SmartSpace HTH, ext. 2946 1. INTRODUCTION 1.1 This report is being submitted to ensure that the council is satisfied with the value for money to the council and performance, both service and financial, of H&F Bridge Partnership.
2. BACKGROUND 2.1 In 2004, the Council initiated a programme for Customer First and Service Transformation, to improve services to residents in a cost effective way. Invest to Save funding was available to fund the first phases of the work but a balance of £8m was needed to fund the full implementation of H&F Direct, H&F Advice and other strategic programmes including Business Continuity. In order to achieve the required funding, the council agreed in July 2006 that a Joint Venture Company, H&F Bridge Partnership (HFBP), be set up between the council and its strategic partner, Agilisys.
2.2HFBP was established to deliver a good IT service to the council, while making efficiency savings from the inherited operation in order to fund the strategic programmes. It offers the ability to innovate, economies of scale through shared services, access to private sector expertise, the transfer of delivery risk, potential for new business opportunities in the public sector across London and the capacity to manage major change cost effectively across the Council.
2.3The operation of HFBP is governed by a Joint Venture Agreement and Service Agreement, both operative for ten years from 1 November 2006.
2.4Since the start of the contract, new services have been added into it and its performance management regime including the council’s contact centre (March 2009), the Children’s Services IT service (September 2008), the Out of Hours service and the Project Management resources of the Business Transformation team (April 2011).
2.5Governance arrangements were put in place to ensure its management fitted within the council’s existing decision-making system, including an EMT and HFBP strategic partnership board that takes place on a quarterly basis which has proved a useful seed bed for service transformation ideas.
2.6The Council is currently represented on the HFBP Board by the Leader, Councillor Stephen Greenhalgh, and Nigel Pallace, Director of Environment Services. Jane West, Director of Finance and Corporate Governance, also attends these meetings in a non-voting capacity.
3. FINANCIALS 3.1 Shareholding in HFBP is split 80.1% Agilisys and 19.9% Council but, to maintain balance, the Council has a right of veto over a number of key control issues, including change of ownership, issuing of shares and entry into major contracts. The Council is thus able to exercise a degree of influence over HFBP without falling foul of technical accountancy and procurement requirements which might otherwise limit the practical financial and commercial benefits of the HFBP option.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.