Resolved
RESOLVED THAT The report be noted.
Audit Committee noted this item on Thursday 27 September 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED THAT The report be noted.
1. The committee consider the current Strategic, Change and Operational risk position as outlined in the report. 2. The committee consider the Key Risk Indicators attached in Appendix 2 and their ongoing development.
1 1. PURPOSE 1.1. This report updates Members on the highlight risk management issues identified across council services and follows changes in the reporting process to Committee to meet BS31100 requirements for Enterprise Risk Management. Effective risk management continues to help the council to achieve its objectives by ‘getting things right first time’ and is a key indicator of the ‘Corporate Health’ of the council.
2. BACKGROUND 2.1. The public sector is changing and increasingly confronted by a growing range of new areas of vulnerability, such as complex supply chains, the interconnectivity of new technology, funding reductions and civil unrest. Taken against a backdrop of a challenging global risk environment, unpredicatble severe weather and natural catastrophies and unprecendented levels of organisational flux, these scenarios pose real risks to the long term resilience of public services.
2.2The UK public services model, both in terms of operational design and funding, is under the greatest period of stress since the second world war. It is a distinct likelihood that potential incidents, crises and failures will form part of the landscape of risk over the next few years. Additionally John Hurrel the Chief Executive of the UK Risk Management association Airmic, believes that significant risks are emerging around technology and communications due to the extent of organisations dependency on the Internet.
3. TRI-BOROUGH RISK MANAGEMENT DELIVERY 3.1. H&F Risk Management has been included as a service, along with Internal Audit and Counter Fraud, in the Corporate Services Programme. The target operating model and organisational structure that will deliver the risk management service is being developed following a review of risk management arrangements in each of the three boroughs. At present each council has in place a policy, strategy, framework and approach distinct from each other.These will be reviewed and aligned following an assessment of the service and proposals accepted by the Executive and by each of the 3 councils Cabinets. Following that efficiencies will be made in the administration, training and delivery of the service.
4. TRIBOROUGH RISK & ASSURANCE REGISTERS 4.1. A review of the composition and struture of departmental risk registers in order to compare and contrast how they can be aligned has been initiated by the Principal Consultant, Risk Management. TriBorough and BiBorough departments could and should retain ownership of sovereign risks however these may be a shared responsibility for their management and going forward may start to rely on common controls. It is possible to combine existing sets of risk & assurance registers across Tri and Bi Borough services, eliminating potential duplication or triplication of administration. A
2 benefit of this exercise would be the use of risk and assurance registers from a common source to inform future internal audit plans.
5. H&F - STRATEGIC RISKS PERSPECTIVE 5.1. Risk and Assurance Registers are an expression of Departmental Governance arrangements. The Corporate Risk & Assurance Register has been remodelled as an Enterprise Wide Risk & Assurance Register to address Tri,Bi and Sovereign Borough Services risks across three perspectives Strategic, Change and Operational. This model will continue to operate as the three boroughs bring together the risk management service.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
COMBINED RISK MANAGEMENT HIGHLIGHT REPORTReport | 464 KB | DownloadRead as text |
Follow Audit Committee at Hammersmith & Fulham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Jun 2026 | Minutes and ActionsRESOLVED That the minutes of the meeting held on 16 March 2026 were agreed as accurate record. | Agreed | Open |
| 23 Jun 2026 | Statement of Accounts 2025/26 UpdateRESOLVED That the Committee noted the verbal update. | Noted | Open |
| 23 Jun 2026 | External Audit Plan (Pension Fund) 2025/26RESOLVED That the Committee agreed to note the External Audit Plan 2025/26 for the London Borough of Hammersmith & Fu... | Agreed | Open |
| 23 Jun 2026 | Annual Report of the Audit Committee for Municipal Year 2025/26RESOLVED That the Committee noted the report. | Noted | Open |
| 23 Jun 2026 | Work Programme for 2026/27RESOLVED That the Committee noted the Work Programme for 2026/27. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.