Decision made by the Cabinet Member on: 9 May 2013 That authority be given to waive the provisions of the Council Contract Standing Orders and vary the contract with Thames Reach for the provision of street outreach services for a period of up to six months from 31st May 2013.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
1.1The contract with Thames Reach for the provision of street outreach services within the borough expires on 30th May 2013. The process to retender the contract is on-going and being managed by a tender appraisal panel (TAP) made up of officers from ELRS, Community Services and FCS.
1.2Tenders are due to be assessed by the TAP on 18th March 2013 and a recommendation to award a contract shall be presented on 13th May 2013. The award of the contract to the successful tenderer will be approximately 20th May 2013. Details of the timetable for the retendering of this contract can be found in Appendix 1. 1.3. If any contractor other than the current service provider is successful in tendering for the contract they will require a mobilisation period before they can commence delivery of the service.
1.4It may be necessary to extend the existing contract for a short period to enable the new contractor to have a mobilisation period. It is therefore requested that an extension of the current contract for a period of up to six months from 31st May 2013 be granted. This will both ensure service continuity and enable a new contract to be let in accordance with the council’s constitution and procurement legislation.
Recommendations
2.1That authority be given to waive the provisions of the Council Contract Standing Orders and vary the contract with Thames Reach for the provision of street outreach services for a period of up to six months from 31st May 2013.
Reasons for decision
3.1The current street outreach contract is delivered by Thames Reach. If they are awarded the new contract then there will be no need for an extension of the current contract and the new contract will commence on 1st June 2013.
3.2If another service provider is awarded the contract they will require a mobilisation period, including time to allow for any transfer of staff under TUPE, before they can commence. The last time the contract was awarded a mobilisation period of three months was required.
3.3In order to ensure that we can deliver our statutory responsibilities during the mobilisation period we request a monthly variation of the current contract, for a period of up to six months, costed pro rata at the current contract level. This will allow Thames Reach to continue delivering the service until such time as the new provider is in a position to commence.
Equality implications
4.1None.
Legal implications
5.1Street outreach services are part B services for the purposes of the Public Contracts Regulations 2006 and the value of the extension to the current contract is below the current EU threshold for services. Nevertheless, the council should still comply with the general EU principles such as non- discrimination, transparency, proportionality and mutual recognition. 5.2. As a general rule the council should undertake a degree of advertising that is proportionate to the size and nature of the contract, even for Part B and below the threshold services. In this instance it is understood that this type of service is locally based and is therefore unlikely to be of interest to economic operators located outside the UK.
5.3It is noted that the benefits of extending the current contract include that it provides the council with a continuity of a high quality, locally based service whilst a tender exercise is carried out to let the new contract. On that basis and for the reasons set out in the body of this report, it is felt that a risk of challenge in relation to the extension of the contract is low.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Bishops Park Public Toilet ImprovementsDecision Taken by Cabinet Member on 24 June 2016: That Amey be instructed to carry out these works. It is also recomm...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.