Decision made by the Cabinet Member on: 4 June 2013 1. That approval be given to waive Contract Standing Orders in relation to the compilation of the shortlist from which tenders were invited and under which the procurement was run 2. To award the contract for the refurbishment of 9 classrooms to Bell Building for a contract sum of £39,610 + associated costs and fees.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
2.1That approval be given to waive Contract Standing Orders in relation to the compilation of the shortlist from which tenders were invited and under which the procurement was run
2.2To award the contract for the refurbishment of 9 classrooms to Bell Building for a contract sum of £39,610 + associated costs and fees.
Reasons for decision
3.1In order to facilitate the relocation of the French Lycée school from Munster Road in to the former Peterborough School, Clancarty Road as part of the bi-lingual provision project, it is necessary to undertake a programme of minor decoration to 9 classrooms so that they are operational for September 2013.
4. INTRODUCTION AND BACKGROUND
4.1On the 14th January 2013 Cabinet approved the 2012/13 Schools Organisation Strategy. Contained within that report was the delegation of authority to the Cabinet Member for Children’s Services, in conjunction with the Executive Director of Children’s Services, to agree disbursement of resources, within the overall cash envelope, for all proposed new Schools of Choice schemes approved by this report as required by design development, up to a cash limit of £4.5 million, to progress the procurement and delivery of the 2012/13Capital programme.
4.2Complications relating to the execution of original project plan for the bi- lingual project means that an interim facility needs to be provided for the academic year 2013-4.
4.3The former Peterborough school has been identified as an interim solution subject to the completion of necessary refurbishment works. 5. PROPOSAL AND ISSUES
5.1As the expansion of the Lycée cannot be accommodated with in the current site and it has not been possible to identify any alternatives it is proposed to redevelop Peterborough school to accommodate the current provision, subject to the necessary works.
6. OPTIONS AND ANALYSIS OF OPTIONS
6.1Consideration was given to alternative locations but once it became clear that the overall project was delayed and that it would not be possible to identify alternative locations in time for September 2013, works wer specified and put out to tender.
6.2The Council contracts 3BM Limited, a mutual established by former employees of the tri-borough councils to advise on the management of the Hammersmith & Fulham school estate. 3BM Limited ran a procurement and sought and received competitive quotations (exclusive of VAT) from the following:
ASBC Contractors £52,104.00
Bell Building £39,610.00
Fairlane Ltd £48,650.00
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Bishops Park Public Toilet ImprovementsDecision Taken by Cabinet Member on 24 June 2016: That Amey be instructed to carry out these works. It is also recomm...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.