CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Hammersmith & Fulham
Cabinet Members' Decisions, Monday 6 January 2014

Eel Brook Common : Post And Rail Replacement Project

Approved Executive 1 paper

Cabinet Members' Decisions approved this item on Monday 6 January 2014. Below is the council's own wording, with the papers it was decided on.

Item1

Resolved

Decision taken by the Cabinet Member on: 2 January 2014 That approval be given to appoint T. Loughman to undertake the Eel Brook Common Post and Rail Replacement Project within the contract amount stated in this report.
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet Members' Decisions

Executive summary

1.1To seek approval from the Cabinet Member for Environment, Leisure and Residents Services to appoint T. Loughman & Co. Ltd. for the supply and installation of a replacement post and rail system along the perimeter of Eel Brook Common.

1.2Cabinet approved the budget for this project as part of the Parks Capital Programme 5 March 2012. The budget has been carried forward to 2013/14 as agreed by Members. 2. RECOMMENDATION

2.1That approval be given to appoint T. Loughman to undertake the Eel Brook Common Post and Rail Replacement Project within the contract amount stated in this report.

Reasons for decision

3.1The recommendation to award the contract to T. Loughman & Co. Ltd. to undertake the Eel Brook Common post and rail replacement is based on the tender process detailed below. T. Loughman & Co. Ltd. were the only valid tender submission. The contract is to be awarded on the basis of the most economically advantageous tender.

4. INTRODUCTION AND BACKGROUND

4.1Eel Brook Common is in the Parsons Green and Walham ward of the London Borough of Hammersmith and Fulham. The Common is a valuable local green space in a densely populated area. The Common’s paths and furniture are tired and run down and would benefit greatly from enhancement as has already been achieved at Parsons Green further west.

4.2The perimeter post and rail replacement project is one of a number of improvement projects for Eel Brook Common. Originally scheduled to be completed in 2012, this project was carried forward so as not to interfere with paving and playground improvements. The completed improvements have delivered a much-needed face lift to many of the Common’s depreciating assets. The specification of the post and rail works are identical to those used for Parsons Green 3 years ago, which has been very well received.

4.3The improvements to the Eel Brook Common post and rails are necessary to remedy numerous health and safety concerns and improve the Common’s access and security. The existing posts are rotting and the rails are rusting. It is common for either of the items to dislodge causing health and safety risks. In addition to this the security of Eel Brook Common is at risk to squatters as large sections of the post and rail have been removed because of their poor state.

5. PROPOSAL AND ISSUES

5.1The project proposes to:

• Removal of the existing perimeter post and rail, which is beyond the point of repair. • Install a new timber post and steel rail system in place of the existing, including bespoke chicanes to reduce the speed of cyclists and improve safety • Remedy any disturbed areas back to its previous condition.

5.2The key issues with the project will be the timing of the removal and replacement as this will leave the Common vulnerable to travellers occupying the site. These concerns will be raised with the contractors in order to minimise this risk.

6. OPTIONS AND ANALYSIS OF OPTIONS

6.1The replacement of the post and rail surrounding Eel Brook Common has become necessary as sections of the existing depreciated beyond repair leaving large gaps of no perimeter post and rail . 6.2 Given the successful post and rail replacement project at Parsons Green results from the consultation requested that the specification for Eel Brook Common be the same.

Consultation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Eel Brook Common : Post And Rail Replacement ProjectReport 81 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 8 attended
NB
Councillor Nicholas BotterillCommittee Member, expected
GS
Councillor Greg SmithCommittee Member, expected
HB
Councillor Helen BinmoreCommittee Member, expected
ML
Councillor Mark LovedayCommittee Member, expected
MG
Councillor Marcus GinnCommittee Member, expected
AJ
Councillor Andrew JohnsonCommittee Member, expected
VB
Councillor Victoria Brocklebank-FowlerCommittee Member, expected
GC
Councillor Georgie CooneyCommittee Member, expected

On this subject at Hammersmith & Fulham

Search all
  1. Eel Brook Common : Post And Rail Replacement ProjectThis decision
  2. Eelbrook Restaurant, Eelbrook Common, New King's Road, SW6 4SU, Parsons Green And Walham 2015/00825/FULApproved

More from Hammersmith & Fulham Cabinet Members' Decisions

All decisions
MeetingDecisionOutcome
4 Jan 2017 Contract Award Community Sexual Reproductive Health Services: Lot 1 - Sexual Health Promotion and Psychosocial Support AND Lot 2 - Contraception and Sexually Transmitted Infection Screening (E)Decision taken by the Cabinet Member for Health and Adult Social Care on 28 th October 2016: The recommendations in t... Agreed Open
4 Aug 2016 Award Of One-Off Grant To Hammersmith And Fulham MencapDecision Taken by Cabinet Member on 30 June 2016: That a one-off grant of £50,000 be awarded to Hammersmith & Fulham ... Agreed Open
4 Aug 2016 Poverty And Worklessness Commission - Interview Programme With Residents Living In Poverty And/Or WorklessnessDecision Taken by Cabinet Member on 20 July 2016: That a sum of up to £28,000, secured from Section 106 funds, is mad... Decided Open
4 Aug 2016 Proposed Registration Service Fees And Charges For 2016/17Decision Taken by Cabinet Member on 3 August 2016: To approve the proposed Registration Service fees and charges from... Approved Open
4 Aug 2016 Bishops Park Public Toilet ImprovementsDecision Taken by Cabinet Member on 24 June 2016: That Amey be instructed to carry out these works. It is also recomm... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies