Resolved
Decision taken by the Cabinet Member on: 15 January 2014 That approval be given to undertake the scheme set out in this report.
Cabinet Members' Decisions approved this item on Wednesday 15 January 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision taken by the Cabinet Member on: 15 January 2014 That approval be given to undertake the scheme set out in this report.
1.1The report seeks approval for a sustainable drainage and greening scheme for a site in the borough, at Imperial Square. This is inline with the Council’s priorities to implement SuDS on a wide-scale across the borough to reduce the risk and impact of flooding.
2.1That approval be given to undertake the scheme set out in this report.
3.1There is a push within the Council to implement green infrastructure for a number of reasons, including the use of green projects as sustainable drainage schemes to reduce the risk and impact of flooding, as well as environmental improvements and as enhancements to public spaces to improve health and wellbeing of people using the space.
4. STRATEGIC OBJECTIVES
4.1The proposals detailed in this report relate to the Council’s aspirations to implement more Sustainable Drainage Systems (SuDS) within the borough to reduce the risk and impact of flooding, particularly that associated with surface water as well as provide improvements to the urban environments.
5. INTRODUCTION AND BACKGROUND
5.1The Council has committed to implementing more SuDS projects to help reduce the amount of surface water draining into the combined sewerage system to reduce the risk of flooding to properties within the borough. These systems will also provide additional benefits such as public space improvements and environmental benefits.
5.2A number of sites have been identified to trial different SuDS techniques, one of which is covered in this report. The site has previously been identified in a Cabinet Member Briefing report on 14th October 2013. This sites is in addition to the larger SuDS schemes currently at design stage and will be used to showcase methods suitable for smaller sites and will ensure that something can be delivered ahead of the larger schemes. This will act as pilot studies for future Greening projects within the Borough. A meeting has taken place with Professor Robert Bray, the UK’s leading Urban Water Management expert with over 15 years of experience in his portfolio of completed projects. Robert Bray has advised on a number of SuDS designs across the borough, including the site covered by this report.
5.3The scheme includes input from a number of different departments within the borough and will act as a flagship for joined up working on Greening projects in the future.
6. PROPOSALS, COSTS AND PROGRAMME
6.1This site is part of a series of smaller, ‘quick win’ projects that can be used to trial a number of sustainable drainage measures to provide enhanced urban greening and a better management of surface water.
6.2These have been identified by H&F and through discussion with Professor Bob Bray. Small scale feasibility assessments would be required for this scheme to identify what measures would be suitable for each site but the early indications are: Imperial Square
6.3This area is currently a neglected residential hard landscaped square, to be converted into a meadow intended to hold water, as shown on the attached figure
6.4From the discussion with the design consultants, indications are that the project would cost in the region of £30-£40k. This cost is subject to further feasibility assessments and design which will be undertaken as part of the project.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix: Imperial Square ConceptAppendix | 232 KB | Download |
PDF |
Imperial Square SuDS schemeReport | 51 KB | DownloadRead as text |
Follow Cabinet Members' Decisions at Hammersmith & Fulham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Jan 2017 | Contract Award Community Sexual Reproductive Health Services: Lot 1 - Sexual Health Promotion and Psychosocial Support AND Lot 2 - Contraception and Sexually Transmitted Infection Screening (E)Decision taken by the Cabinet Member for Health and Adult Social Care on 28 th October 2016: The recommendations in t... | Agreed | Open |
| 4 Aug 2016 | Award Of One-Off Grant To Hammersmith And Fulham MencapDecision Taken by Cabinet Member on 30 June 2016: That a one-off grant of £50,000 be awarded to Hammersmith & Fulham ... | Agreed | Open |
| 4 Aug 2016 | Poverty And Worklessness Commission - Interview Programme With Residents Living In Poverty And/Or WorklessnessDecision Taken by Cabinet Member on 20 July 2016: That a sum of up to £28,000, secured from Section 106 funds, is mad... | Decided | Open |
| 4 Aug 2016 | Proposed Registration Service Fees And Charges For 2016/17Decision Taken by Cabinet Member on 3 August 2016: To approve the proposed Registration Service fees and charges from... | Approved | Open |
| 4 Aug 2016 | Bishops Park Public Toilet ImprovementsDecision Taken by Cabinet Member on 24 June 2016: That Amey be instructed to carry out these works. It is also recomm... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.