Decision taken by the Cabinet Member on: 17 February 2014 The approval be given to the element of the library refurbishment costs to be funded from the Strategic Programme Fund (SPF) of £49,112 (this one-off project cost figure excludes annual support costs).
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
1.1The refurbishment of Hammersmith Library is a key corporate priority for 2014. The scope of the project is to extend the More Than A Library brand already implemented at other LBHF libraries. The project will also relocate much of the archives and local studies collections to Hammersmith Library. As part of the refurbishment, the library’s IT facilities and networks are being renewed to provide a modern and efficient service for residents.
1.2This report seeks Cabinet Member approval for expenditure from the Strategic Programme Fund to resource this expenditure. This approach has been agreed by Finance. Contingency for the project might have been expected to resource this expenditure but is likely to be required for other elements of the project. 2. RECOMMENDATIONS
2.1The approval be given to the element of the library refurbishment costs to be funded from the Strategic Programme Fund (SPF) of £49,112 (this one- off project cost figure excludes annual support costs).
Reasons for decision
3.1The decision is required to approve expenditure already identified within the Hammersmith library refurbishment scheme, but which is being resourced from SPF.
4. INTRODUCTION AND BACKGROUND
4.1The refurbishment of Hammersmith Library is a key corporate project. Its objectives are to extend the More Than A Library brand, successfully rolled out in LBHF’s three other libraries, to the largest library, and refurbish this historic library building in a sensitive way, making it fit for purpose as a modern public library and efficient to run. Additionally, the project has been expanded to include accommodation for the LBHF archives and local studies collections which will be relocated into purpose- designed accommodation on the first floor and in basement storage.
4.2Funding of £2.69m was approved by Cabinet on 8 April 2013 in the report Hammersmith Library Refurbishment and Archives Options. Authorisation of the future spend and draw down of associated S106 monies was delegated to the Deputy Leader and Cabinet Member for Residents Services in consultation with the Executive Director for Environment, Leisure & Residents Services and the Executive Director for Finance.
4.3The expenditure proposed in this report is in addition to the overall budget as the exact amount was unknown at the time of the Cabinet Report referred to above. Project contingency would usually be expected to cover such costs but is likely to be required by other elements of the project in this case. Cabinet Member approval is therefore sought to resource this essential expenditure from another budget within the Council where resource exists.
5. PROPOSAL AND ISSUES
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Bishops Park Public Toilet ImprovementsDecision Taken by Cabinet Member on 24 June 2016: That Amey be instructed to carry out these works. It is also recomm...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.