Decision taken by the Cabinet Member on: 30 April 2014 That approval be given for the works to be procured via Amey Community Limited (ACL) in accordance with the approved Terms and Conditions of the Tri-Borough TFM contract, at an estimated cost of £48,928.00 plus a Contingency Sum of £4,892.80 and fees of £8,073, making a total cost of £61,893.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
2.1That approval be given for the works to be procured via Amey Community Limited (ACL) in accordance with the approved Terms and Conditions of the Tri-Borough TFM contract, at an estimated cost of £48,928.00 plus a Contingency Sum of £4,892.80 and fees of £8,073, making a total cost of £61,893.
Reasons for decision
3.1The works detailed in this report needs to be undertaken to eliminate any potential Health and Safety risks in the near future given the current state of the affected areas. Also these works will prolong the life of the building as the investment with retain the weather-tightness of the property.
BPM FINAL VERSION DATED : 22.04.2014 2 of 5 4. INTRODUCTION AND BACKGROUND
4.1The chapel provides and extremely important service to the local community and should, therefore, be maintained to maximise the life of the property. The areas identified as requiring repair and if not repaired, could also constitute a health and safety issue as, for example, falling stonework could be potentially fatal.
5. PROPOSAL AND ISSUES
5.1The proposed works consist of erecting appropriate scaffold to allow access to the damaged stone areas and the roof coverings and associated structure requiring repair.
5.2Funding, Cash flow and programme of works
5.2.1 The funding for this scheme will be met from the Corporate Planned Maintenance programme 2013-2014 which was approved at Cabinet on the 14th January 2013 as a key decision. This is a variation to programme and is in accordance with the agreed protocol for programme amendment and scheme substitution and has been agreed by the Director of Building and Property Management and the Executive Director of Finance and Corporate Services in consultation with the Corporate Asset Delivery Team (CADT).
5.2.2 The anticipated cash flow for these works is as follows:
2014 / 2015 2015/ 2016 TOTAL
Works £48,928 £0 £48,928
Contingency Sum £ 4,892 £0 £ 4,892
BPM Fees £ 8,073 £0 £ 8,073
TOTAL £ 61,893 £0 £61,893
5.2.3 Cost Code: 99207 PLE001 CAP005 CENV00858
5.3Programme of works
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Bishops Park Public Toilet ImprovementsDecision Taken by Cabinet Member on 24 June 2016: That Amey be instructed to carry out these works. It is also recomm...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.