Cabinet Members' Decisions, Monday 15 September 2014

Proposed Extension To The Civica Purchasing System Contract

Agreed Executive 1 paper

Cabinet Members' Decisions agreed this item on Monday 15 September 2014. Below is the council's own wording, with the papers it was decided on.

Item3

Resolved

Decision taken by the Cabinet Member on: 14 September 2014 1. Agree a one year renewal to the Civica contract on a licence only basis, at an annual cost of £60,000. 2. That approval be given for support and maintenance spend, up to a maximum of £4,000, to be charged on a time and materials basis. 3. That £45,000 of this cost is met from the underspend on the Managed Services contract budget in 2014/15, and the remaining £19,000 balance is drawn down from the Managed Services reserve.
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet Members' Decisions

Executive summary

1.1The Civica IT system is used across the Council to purchase items, through the raising of a purchase order, and the subsequent goods receipting of that order when goods or services are received. The use of this purchase ordering system allows orders to be sent electronically to suppliers, an online audit trail of ordering and approval to be kept, and no need for manual coding or authorising of invoices for payments. This brings greater efficiency and control to the Council’s purchasing. 1.2. The current Civica contract is managed via HFBP and expires on the 30th September 2014. When Managed Services goes live there will be no further need for the Civica system. Therefore no discussions about extending the contract had been entered into with Civica when the Managed Services go live was planned to be on the 1st September 2014. However, now that the go live has been delayed to the 1st April 2015, the Council needs to renew the Civica contract to ensure that it is operational until at least that date.

Recommendations

2.1Agree a one year renewal to the Civica contract on a licence only basis, at an annual cost of £60,000.

2.2That approval be given for support and maintenance spend, up to a maximum of £4,000, to be charged on a time and materials basis.

2.3That £45,000 of this cost is met from the underspend on the Managed Services contract budget in 2014/15, and the remaining £19,000 balance is drawn down from the Managed Services reserve.

Reasons for decision

3.1The Civica purchasing system is a key financial system which allows an effective and automated purchasing process. If the contract with Civica was not renewed, the Council would need to revert to an entirely manual purchasing and payment process with no online audit trail of purchasing and approval and would need to quickly re-work the means of communicating orders to suppliers.

3.2However, given that Civica will only be needed until the 1st April it is recommended that the contract is a renewed for the minimum period possible, which is one year. It is also recommended that the renewal is on a licence only basis, as the system has required almost no support from Civica over recent years, and therefore paying for a maintenance package is considered unnecessary. If required, there is an option to still purchase support and maintenance from Civica on a time and materials basis.

4. INTRODUCTION AND BACKGROUND

4.1The Civica purchasing system contract is due to expire on the 30th September 2014. Following the decision to delay the go live of Managed Services to the 1st April 2015, it is necessary to renew this contract so that the Council’s current purchasing practices can continue until that date. 4.2. This report details the options for renewing the Civica contract, with associated costs.

5. PROPOSAL AND ISSUES

5.1This report contains a number of options around the future of the Civica purchasing system, balancing the cost implications with the risks to service continuity and resilience.

6. OPTIONS AND ANALYSIS OF OPTIONS

6.1The table below outlines the options put forward by HFBP following discussions with Civica, who provide the licences for the system. During negotiations a 6 month extension was requested, but Civica were not prepared to offer less than a one year extension.

Licence, Support and Licence Maintenance (£ pa) Only (£ pa) Current Annual Cost 45,017 - I year Proposed cost 68,475 60,000 2 year Proposed cost 122,350 75,000

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Proposed Extension To The Civica Purchasing System ContractReport 214 KB DownloadRead as text

At this meeting

Whole meeting

More from Hammersmith & Fulham Cabinet Members' Decisions

All decisions
MeetingDecisionOutcome
4 Jan 2017 Contract Award Community Sexual Reproductive Health Services: Lot 1 - Sexual Health Promotion and Psychosocial Support AND Lot 2 - Contraception and Sexually Transmitted Infection Screening (E)Decision taken by the Cabinet Member for Health and Adult Social Care on 28 th October 2016: The recommendations in t... Agreed Open
4 Aug 2016 Award Of One-Off Grant To Hammersmith And Fulham MencapDecision Taken by Cabinet Member on 30 June 2016: That a one-off grant of £50,000 be awarded to Hammersmith & Fulham ... Agreed Open
4 Aug 2016 Poverty And Worklessness Commission - Interview Programme With Residents Living In Poverty And/Or WorklessnessDecision Taken by Cabinet Member on 20 July 2016: That a sum of up to £28,000, secured from Section 106 funds, is mad... Decided Open
4 Aug 2016 Proposed Registration Service Fees And Charges For 2016/17Decision Taken by Cabinet Member on 3 August 2016: To approve the proposed Registration Service fees and charges from... Approved Open
4 Aug 2016 Bishops Park Public Toilet ImprovementsDecision Taken by Cabinet Member on 24 June 2016: That Amey be instructed to carry out these works. It is also recomm... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies