Procurement Of A Term Contract To Carry Out Testing And Inspection Of Existing Fire Alarms & Emergency Lighting Systems Within Housing Properties - Borough-Wide
ApprovedExecutive1 paper
Cabinet Members' Decisions approved this item on Tuesday 30 December 2014. Below is the council's own wording, with the papers it was decided on.
Decision taken by the Cabinet Members on: 8 December 2014 1.1. That approval be given to procure a 5 year Term Contract with an option to extend annually for a further 3 years in accordance with procurement legislation via the restricted procedure, any such further extension being subject to satisfactory performance by the successful contractor, during the original contract term of 5 years, at an anticipated annual cost of £300k and a total contract value of up to £2,400.000. 1.2. To note that funding for the proposed works is contained within the Housing Revenue Account.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
1.1This report establishes the need for the procurement of a Term Contract to undertake testing and inspection of fire alarms, and emergency lighting systems within sheltered Accommodation, high rise blocks of flats with communal areas, hostels and HRA – funded community centres across the Council’s housing portfolio. In addition the report identifies the various procurement options considered, together with (financial & non-financial) benefits/disbenefits of adopting each option.
1.2On the basis of the options considered and the evidence gathered, the recommendation is to procure a 5 year Term Contract with an option of annual extension for a maximum period of 3 years, making a total contract period of up to 8 years. The contract would be procured in compliance with the Public Procurement Regulations. 1.3 The Council has a responsibility under the Regulatory Reform (Fire Safety) Order 2005 to maintain the fire alarm and emergency lighting installations within its premises. The works to be carried out under this contract will discharge the Council’s duties under this aspect of the regulations.
1.4The works will be carried out in accordance with the requirements of BS 5839- 1:2002 with respect to fire alarm systems and BS 5266-1:1999 with respect to emergency lighting installations. The works include quarterly testing and inspection of each fire alarm system and the testing of emergency lighting systems on a monthly basis. The fire alarm systems installed within the properties are all Gent Vigilon systems, and the works are to be undertaken by a contractor who is a suitable Gent System Integrator.
1.5The contract also includes for attending to reactive breakdown repairs to fire alarm systems. In respect of the emergency lighting installations, reactive breakdown repairs will be carried out under the existing TPC (Term Partnering Contract) Repairs Contract with MITIE.
1.6The contract management and pricing mechanism will be designed to align with the property services new lean staffing structure, ensuring that adequate Contract management controls are put in place by the Council, and that contractual remedies are robust
Recommendations
2.1That approval be given to procure a 5 year Term Contract with an option to extend annually for a further 3 years in accordance with procurement legislation via the restricted procedure, any such further extension being subject to satisfactory performance by the successful contractor, during the original contract term of 5 years, at an anticipated annual cost of £300k and a total contract value of up to £2,400.000.
2.2To note that funding for the proposed works is contained within the Housing Revenue Account.
Reasons for decision
3.1The Council has a responsibility under the Regulatory Reform (Fire Safety) Order 2005 to maintain the fire alarm and emergency lighting installations within its premises. The works to be carried out under this contract will discharge the Council’s duties under this aspect of the regulations. The existing contract for the testing and inspection of fire alarm and emergency lighting installations expires on 14th August 2015, and the proposed new contract is required in order that the Council continues to discharge its statutory obligations.
4. INTRODUCTION AND BACKGROUND
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Procurement Of A Term Contract To Carry Out Testing And Inspection Of Existing Fire Alarms & Emergency Lighting Systems Within Housing Properties: Borough-WideReport
11Procurement Of A Term Contract To Carry Out Testing And Inspection Of Existing Fire Alarms & Emergency Lighting Systems Within Housing Properties - Borough-WideThis decision
Bishops Park Public Toilet ImprovementsDecision Taken by Cabinet Member on 24 June 2016: That Amey be instructed to carry out these works. It is also recomm...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.