Cabinet Members' Decisions, Thursday 26 March 2015

H&F ICT Transition Programme Management

Approved Executive 1 paper

Cabinet Members' Decisions approved this item on Thursday 26 March 2015. Below is the council's own wording, with the papers it was decided on.

Item1

Resolved

Decision taken by the Cabinet Member on: 10 March 2015 That approval be given to the costs of delivering Phase 1 programme management for the transition to new providers during 2015/16. Approval is sought for a total of £39,843 to be funded from the IT Enablers fund.
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet Members' Decisions

Executive summary

1.1The Hammersmith and Fulham Bridge Partnership (HFBP) service desk provides online self-service and telephone support to H&F users for support and resolution of reported ICT incidents, problems, fulfilment of service requests and deals with security incidents, among other things.

1.2The HFBP distributed computing function provides desktop services; devices, MySmartDesktop Bring Your Own Device and other related services.

1.3HFBP also provide data centre services ie a secure resilient environment for the desktop services, all 120 major applications and other services including the ability to login, security and firewalling, telephony. 1.4. In December 2013, Shared Services ICT awarded three framework contracts for ICT; the distributed computing and data centre contracts to BT Global Services Ltd and the service desk contract to Agilisys Ltd.

1.5Westminster City Council (WCC) have already called off from the three frameworks. The transition was smooth and WCC users report themselves as more satisfied with the current service.

1.6By changing these three services to new service providers earlier than end of contract, H&F will be able to reduce the effort, costs and risk in the transition and will provide the opportunity for a single service desk providing a consistent user experience for staff, particularly H&F staff, leading to a more integrated service and consequently higher council staff productivity.

1.7An early transition of the HFBP service desk will reduce the effort, cost and risk associated with a full transition of ICT services at the end of the HFBP service contract on 31 October 2016. It will also allow H&F to offer improved levels of service and availability for H&F users earlier than originally planned. Transition of the other two services will be less visible to users but will have the effect of achieving the council’s saving targets.

1.8This paper proposes that, in order for H&F to call off Lot 1 Distributed computing; Lot 2 service desk; Lot 3 data centres from the ICT frameworks and move the service to new service providers, Agilisys and BT, over the next 18 months, programme management is procured.

1.9Phase 1 consists of programme definition work to be done in collaboration with HFBP and will take up to three months, around 57 person days at a cost of £39,843, after which the transition activity should be better defined.

1.10This role in Phase 1 will therefore set out the high level resource plan for the council. This will allow the programme to set out the wider resource need in early 2015/16, based on the council having developed a high-level business case by April 2015.

Recommendations

2.1That approval be given to the costs of delivering Phase 1 programme management for the transition to new providers during 2015/16. Approval is sought for a total of £39,843 to be funded from the IT Enablers fund.

Consultation

3.1This approach has been discussed at the Shared Services ICT Divisional Leadership Team (DLT) board.

Equality implications

4.1This report is requesting funding of £39,843 to provide a programme management resource to the proposed project. There are no direct equalities impacts on any protected group resulting from the proposals made by this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
H&F ICT Transition Programme ManagementReport 171 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Hammersmith & Fulham

Search all
  1. H&F ICT Transition Programme ManagementThis decision
  2. H&F programme management for the remaining duration of the ICT transition programmeApproved
  3. H&F Bridge Partnership Performance 2015/2016 and ICT Transition Progress ReportNoted

More from Hammersmith & Fulham Cabinet Members' Decisions

All decisions
MeetingDecisionOutcome
4 Jan 2017 Contract Award Community Sexual Reproductive Health Services: Lot 1 - Sexual Health Promotion and Psychosocial Support AND Lot 2 - Contraception and Sexually Transmitted Infection Screening (E)Decision taken by the Cabinet Member for Health and Adult Social Care on 28 th October 2016: The recommendations in t... Agreed Open
4 Aug 2016 Award Of One-Off Grant To Hammersmith And Fulham MencapDecision Taken by Cabinet Member on 30 June 2016: That a one-off grant of £50,000 be awarded to Hammersmith & Fulham ... Agreed Open
4 Aug 2016 Poverty And Worklessness Commission - Interview Programme With Residents Living In Poverty And/Or WorklessnessDecision Taken by Cabinet Member on 20 July 2016: That a sum of up to £28,000, secured from Section 106 funds, is mad... Decided Open
4 Aug 2016 Proposed Registration Service Fees And Charges For 2016/17Decision Taken by Cabinet Member on 3 August 2016: To approve the proposed Registration Service fees and charges from... Approved Open
4 Aug 2016 Bishops Park Public Toilet ImprovementsDecision Taken by Cabinet Member on 24 June 2016: That Amey be instructed to carry out these works. It is also recomm... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies