Planning and Growth - Approval of Discretionary Fees and Services 2016

Approved Executive 2 papers

Cabinet Members' Decisions approved this item on Monday 7 March 2016. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

Decision taken by the Cabinet Member on: 18 January 2016 The changes to charges and services outlined in this report be approved and come into effect on 1st April 2016 unless an earlier date is agreed with the relevant Cabinet Member.
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet Members' Decisions

Executive summary

1.1The Council’s planning services provide a mixture of statutory and discretionary services. Fees for statutory services are currently set nationally whereas fees for discretionary services are within the remit of the authority to set taking into account the services that they wish to provide.

1.2The Planning Service is committed to delivering the best possible services for residents, businesses and all other users of the service. However in order to resource this and maintain high levels of customer satisfaction, it is necessary to charge appropriately. 1.3 This report seeks authority to implement changes to the paid for Pre-application advice system, duty officer system as well as to implement additional charges for discretionary services currently not charged for, but which cost the Council to provide, including accessing historic application files, consideration of withdrawal of enforcement notices and processing applications to a timescale that enables residents to complete property transactions without delay.

Recommendations

2.1The changes to charges and services outlined in this report be approved and come into effect on 1st April 2016 unless an earlier date is agreed with the relevant Cabinet Member.

Reasons for decision

3.1The report is being presented for decision because the changes represent a significant change to how the service is provided, some new charges are involved, and some charges are increased by more than 1.1%.

4. PROPOSALS

4.1Pre-Application Advice

4.2The Council provides informal pre-application advice to potential applicants on their proposals. This service has operated for many years and has proved popular both with applicants, because they are able to get some clarity at an early stage in the process, and with officers, who are able to discourage any obviously unacceptable schemes at a very early stage.

4.3The scheme was last updated in 2013, and currently operates providing 3 tiers of service;

 Level 1 – high level generic advice  Level 2 – Exchange of Letters  Level 3 – Meeting

Having operated this scheme for two years, it is clear that the Level 1 advice has not proven popular nor had the effect of reducing demand on other areas the service. Instead, applicants prefer to seek detailed advice.

4.4In light of this it is proposed to move to a simpler two tier advice system:

 Level A – Exchange of Letters  Level B – Meeting with a follow-up Outcomes Note

The principal changes are that the previous level of generic advice is removed, and all pre-application advice is to be given on the basis of specific proposals put forward to the Council. The lowest level of fee (level 1) shown for the 2015- 16 pre-application scheme is removed, and fees would commence from what was previously Level 2. A copy of the proposed changes to the schedule of Fees, compared to those currently in use, is set out in appendix 1 to this report. The fees which have changed or are new are identified in bold.

4.4Planning Duty Officer Service

4.5The Council at present provides a Planning Duty Officer service 4 afternoons a week, where general support can be provided to residents and applicants about the planning process. This service is provided face to face as well as over the telephone. However, it is not designed provide pre-application advice.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Planning Service Fees and Charges tableAppendix 1 120 KB Download
PDF
Planning and Growth: Approval of Discretionary Fees and Services 2016Report 213 KB DownloadRead as text

At this meeting

Whole meeting
1Back Scanning Housing Management Files (North Of The Borough)Decided 2Resources Required For Zero Based Budgeting To Deliver OutcomesApproved 3H&F programme management for the remaining duration of the ICT transition programmeApproved 4Appointment Of A Council Representative To Old Oak And Park Royal Development Corporation (Planning Committee)Approved 5Determination Of The Admission Arrangements For Hammersmith & Fulham Community Primary Schools For 2017/18Approved 6Appointment Of La Governor - St John Xxiii Catholic Primary SchoolDecided 7Appointment Of LA Governor - Old Oak Primary SchoolDecided 8Appointment Of La Governor - St Mary's Catholic Primary SchoolDecided
9Planning and Growth - Approval of Discretionary Fees and Services 2016This decision
10Masterplanning Services For Hammersmith Town CentreApproved 11Method For Charging Western Riverside Waste Authority Costs Of Waste Disposal To BoroughsDecided 12Licensing Pre-Application Advice For Extra Large Public EventsAgreed 13Travel Care And Support Contract For Jack Tizard SchoolPrivate 14Options Day Centre - 280 Goldhawk Road W12 9pf - Lift Shaft Repair & Lift ReplacementPrivate 15Prior Approval To Waive The Contract Standing Orders In Order For Cabinet To Subsequently Directly Award A Contract For The Provision Of Older People's Floating Support To Notting Hill Housing GroupPrivate 16Contract Award Decision For Health Check SoftwarePrivate 17Approval To Utilise The First Of Two Extension Periods Available And Modify The Thomas Pocklington Trust Accommodation Contract For People With Visual ImpairmentsPrivate 18Approval For A Modification To The St Mungo's Broadway Hope Gardens Contract To Pilot The Housing First Service ModelPrivate 19Approval To Utilise The First Of Two Extension Periods Available And Modify The London Cyrenians Shepherds House Accommodation Contract For Rough Sleepers With Complex NeedsPrivate 20Contract Award - Shared Lives Pilot ProjectPrivate 21Leasehold Buildings Insurance Contract - ConsultationPrivate 22Malvern Court - Rowberry Close - Swanbank Court Sheltered Housing Accommodation: The Modernisation Of The Existing Passenger Lifts & Associated WorksPrivate 23Business IntelligencePrivate

Who was there

0 of 10 attended
SM
Councillor Sue MacmillanCommittee Member, expected
SC
Councillor Stephen CowanCommittee Member, expected
SF
Councillor Sue FennimoreCommittee Member, expected
WH
Councillor Wesley HarcourtCommittee Member, expected
LH
Councillor Lisa HomanCommittee Member, expected
AJ
Councillor Andrew JonesCommittee Member, expected
VL
Councillor Vivienne LukeyCommittee Member, expected
MC
Councillor Michael CartwrightCommittee Member, expected
MS
Councillor Max SchmidCommittee Member, expected
BC
Councillor Ben ColemanCommittee Member, expected

More from Hammersmith & Fulham Cabinet Members' Decisions

All decisions
MeetingDecisionOutcome
4 Jan 2017 Contract Award Community Sexual Reproductive Health Services: Lot 1 - Sexual Health Promotion and Psychosocial Support AND Lot 2 - Contraception and Sexually Transmitted Infection Screening (E)Decision taken by the Cabinet Member for Health and Adult Social Care on 28 th October 2016: The recommendations in t... Agreed Open
4 Aug 2016 Award Of One-Off Grant To Hammersmith And Fulham MencapDecision Taken by Cabinet Member on 30 June 2016: That a one-off grant of £50,000 be awarded to Hammersmith & Fulham ... Agreed Open
4 Aug 2016 Poverty And Worklessness Commission - Interview Programme With Residents Living In Poverty And/Or WorklessnessDecision Taken by Cabinet Member on 20 July 2016: That a sum of up to £28,000, secured from Section 106 funds, is mad... Decided Open
4 Aug 2016 Proposed Registration Service Fees And Charges For 2016/17Decision Taken by Cabinet Member on 3 August 2016: To approve the proposed Registration Service fees and charges from... Approved Open
4 Aug 2016 Bishops Park Public Toilet ImprovementsDecision Taken by Cabinet Member on 24 June 2016: That Amey be instructed to carry out these works. It is also recomm... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies