Decision Taken by Cabinet Member on 7 April 2016 1. To fund one analyst from the interim market for a period of 5 months to free analyst capacity to focus on service development. The estimated cost of this is £38,500. 2. To fund a technical architect for five months at a cost of £53,000 to design a technical architecture for the service, develop the business case and start implementation. 3. To draw funding from underspend from the BI shared service pilot. 4. That the remaining underspend estimated at £272,500 is held, pending the delivery of a further business plan as the service develops and further income/savings are delivered.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
1.1LBHF has a proven track record in delivering benefits from intelligent use of data. In excess of £3m has been delivered over the past three years in a combination of reduced cost and increased income.
1.2There is a large potential for Business Intelligence (BI) to enable the delivery of further benefits, both cashable and non-cashable. A modest start has been made in generating commercial income from BI and there is a desire to exploit this opportunity. 1.3. To maximise the potential of the service a review and upgrade of the technical infrastructure is required. The potential benefits of this are:
Enabling end-user self- service and so freeing up scarce analyst capacity to focus on ‘higher value’ work Automation of repetitive tasks such as data extraction and load and so freeing up scarce analyst capacity to focus on ‘higher value’ work Provide a professional state-of-the-art platform that would add credibility when marketing services Deliver a secure channel to facilitate efficient collaborative working with clients and partners without spending long periods off site.
1.4The recommended approach is a six-month phase of work to:
Add analytical resource from the interim market and transfer workload from the existing team Add business change capability from within Innovation and Change Management (ICM) (already funded) Adjust roles in the Insight and Analysis (I & A) team within ICM to focus on development of the service Recruit a specialist business intelligence architect to design the technical architecture for the service, create a business case for investment in the technical solution for sign-off by appropriate governance bodies, implement the solution.
1.5The cost of this is estimated at £91,500. This can be funded from underspend from previously approved budget for the shared service BI pilot that completed at the end of September 2015.
1.6Failure to proceed with this work means that LBHF will not maximise the potential of its BI capability to meet internal demand and would reduce the potential commercial gain from the service.
Recommendations
That the cabinet member for finance agrees
2.1To fund one analyst from the interim market for a period of 5 months to free analyst capacity to focus on service development. The estimated cost of this is £38,500 2.2. To fund a technical architect for five months at a cost of £53,000 to design a technical architecture for the service, develop the business case and start implementation.
2.3To draw funding from underspend from the BI shared service pilot.
2.4That the remaining underspend estimated at £272,500 is held, pending the delivery of a further business plan as the service develops and further income/savings are delivered.
Reasons for decision
3.1LBHF has an excellent track record of delivering significant return on investment enabled by its BI service. To exploit this fully and yield significant commercial benefits a fully-fledged BI service needs to be developed from the existing I & A team.
3.2Funding is required to provide specialist knowledge and capacity to support the development of the business case as well as to exploit existing opportunities, further enabling the achievement of the MTFS and other council priorities (effective achievement of the Council’s Smarter Budgeting, the delivery plan and becoming the best council).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Bishops Park Public Toilet ImprovementsDecision Taken by Cabinet Member on 24 June 2016: That Amey be instructed to carry out these works. It is also recomm...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.