Wormwood Scrubs Charitable Trust Committee agreed this item on Tuesday 19 June 2018. Below is the council's own wording, with the papers it was decided on.
That the Committee agreed for the Council to approach the market and procure contracts on behalf of the Scrubs for the design of Alternative Ecological Mitigation (AEM) and conservation management plan (CMP) proposals for Wormwood Scrubs Park. (the Scrubs).
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
Report to Wormwood Scrubs Charitable Trust Committee
Executive summary
1.1This report is seeking Wormwood Scrubs Charitable Trust Committee permission to approach the market and procure contracts for the design of Alternative Ecological Mitigation (AEM) and conservation management plan (CMP) proposals for Wormwood Scrubs Park. (the Scrubs)
1.2The requirement for the Council to produce a design for the AEM is set out in the agreement dated 20th October 2016 (Agreement) between The Sec. of state for Transport (the Promotor) and the Mayor and Burgess of the London Borough Hammersmith and Fulham (the Council) relating to ‘High Speed Rail, London West Midland, Bill and ecological mitigation for wormwood scrubs’. 1.3. A Design Timetable within the Agreement sets out the plan to commission consultants to develop a conservation management plan (CMP), detailed draft proposals and Specification for the AEM works
1.4The Detailed Draft Proposal and Specification for the CMP and AEM works will be approved by the Promotor, or nominated undertaker (HS2), and will then be used to procure a works contractor to implement the AEM proposals and subsequently a grounds maintenance contractor to maintain the CMP and AEM works. The appointed consultant will also prepare a 10 year management plan for the works and update this throughout the 10 year period at intervals to be agreed.
1.5HS2 will reimburse the Council for the costs to design, implement and maintain the AEM proposals and management plans together with any reasonable costs properly incurred by the Council.
1.6The outputs from the AEM will include a management plan which will closely align with a hierarchy of plans including; the London Plan, the Old Oak and Park Royal Development Corporation (OPDC) Local Plan and the Councils Open Spaces Strategy. These plans will positively and directly contribute to improving the quality of life of all our residents.
1.7The appendices to this report provide additional information and implications in connection with the main report.
Recommendations
2.1To approve the Business Case & Procurement Strategy for the 2.1.1. appointment of a consultant to develop: 2.1.1.1. a conservation management plan; and 2.1.1.2. detailed draft proposal and specification for the Alternative Ecological Mitigation works; and 2.1.1.3. a 10 year management plan with updates throughout the 10 year period; and 2.1.2. the appointment of related cost consultants to overview the process. as set out in Appendix 1, attached to the report
2.2That delegated authority be granted to the Director of Transport, Highways Parks & Leisure, in consultation with the Cabinet Member for the Environment, , to award the contract for the conservation management plan and development and design of the AEM proposals and specification to the successful tenderer and the appointment of the cost consultant to oversee the process.
Reasons for recommendations
3.1To comply with the requirements contained in Contract Standing Orders which requires approval before a regulated procurement exercise is commenced and to comply with the Promotors requirement to achieve value for money 4. PROPOSAL AND ISSUES
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Wormwood Scrubs Charitable Trust Committee at Hammersmith & Fulham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.