London Borough of Hammersmith & Fulham
Community Safety and Environment Policy and Accountability Committee Minutes Tuesday 18 June 2019
PRESENT
Committee members: Councillors Bora Kwon (Chair), Iain Cassidy, David Morton, Ann Rosenberg and Victoria Brocklebank-Fowler
Other Councillors: Councillors Stephen Cowan (the Leader of the Council), Wesley Harcourt (Cabinet Member for the Environment) and Patricia Quigley
Officers: David Chapot (Prevent Manager), Chris Bainbridge (Head of Transport Policy), Sharon Lea (Strategic Director of Residents’ Services), Bram Kainth (Chief Officer Highways), Dan Levene (Media Manager), Valerie Simpson (Head of Environmental Health), Matt Hooper (Chief Officer - Safer Neighbourhood), Kim Smith (Chief Executive)
External: Linda Moss & Iain Killingbeck (TfL), Casey Abaraonye (HF Cyclists), Annabel Clarke (Hammersmith Society)
1. MINUTES
RESOLVED: THAT the minutes of the meeting held on 27 March 2019 were approved as a correct record and signed by the Chair.
2. APOLOGIES FOR ABSENCE
Apologies for absence were received from Councillor Sue Fennimore.
3. DECLARATIONS OF INTEREST
There were no declarations of interest.
4. HAMMERSMITH BRIDGE
_____________________________________________________________________________________________________ Minutes are subject to confirmation at the next meeting as a correct record of the proceedings and any amendments arising will be recorded in the minutes of that subsequent meeting. Chris Bainbridge, Head of Transport Policy and Network Management, provided a presentation of the Councils plans to fully restore Hammersmith Bridge. He showed slides that provided a brief history of the bridge, including a sketch of the original drawings and plans. The bridge was originally designed to move and flex to absorb shock and vibration. In the post war period, weather and vibration damaged the suspension system, Preventing it from flexing. As a result, this stressed the iron, creating small cracks in the casings surrounding the bridge’s pedestals.
In 2012, the Council spent £250,000 on decking however, no plan to fully test the structural integrity or fully refurbish the bridge existed until 2015. It was noted that between 2015 to the current date the Council and Transport for London (TfL) had undertaken £5.35 million of works so far, including weekly safety checks. Furthermore, state of the art sensors had also been installed. Detailed safety checks had revealed 5 micro-fractures so far. World-class, specialist engineers were monitoring the bridge on a daily basis and dismantling the casings around the micro-fractures to identify the repairs needed.
The Council was working in collaboration with TfL to re-open the bridge and restoring it to its former Victorian splendour as soon as possible. It was noted that a full diagnostic would be carried out by mid-August and a more precise timescale would be available, however this might be as long as three years.
Councillor Victoria Brocklebank-Fowler said that the condition of the bridge was previously discussed at the Community Safety and Environment PAC in December 2018. However, she felt that immediate action was not taken by the Council which had led to an emergency closure. Therefore, she queried why funding negotiations with TfL had not progressed sooner.
Councillor Stephen Cowan (the Leader of the Council) explained that the Council needed to review the overall detail to determine a suitable solution to refurbish the 132-year-old suspension bridge. In 2015, the Council commissioned a full structural integrity assessment to check all aspects of the bridge’s structure. The safety checks revealed that works needed to be carried out to repair the decking and refit the bolts. TfL had committed £25 million towards the repair of the bridge; however, the work was delayed.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MinutesMinutes | 245 KB | DownloadRead as text |
Follow Community Safety and Environment PAC at Hammersmith & Fulham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Mar 2021 | MinutesThat the minutes of the meeting held on 11 th November 2020 and 25 th January 2021 were approved. | Approved | Open |
| 16 Mar 2021 | Future MeetingsThat, the Committee noted the future meeting dates. | Noted | Open |
| 11 Nov 2020 | Update on Council's Use of Investigatory Powers (RIPA and IPA)That the Committee noted and commented on the report. | Noted | Open |
| 20 Jul 2020 | Minutes of the Previous MeetingRESOLVED THAT, the minutes of the meeting held on 28 th January and 10 th February were approved as a correct record. | Approved | Open |
| 28 Jan 2020 | Work Programme and Dates of Future MeetingsRESOLVED That the Committee noted the work programme. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.