Wormwood Scrubs Charitable Trust Committee agreed this item on Tuesday 14 July 2020. Below is the council's own wording, with the papers it was decided on.
RESOLVED 1. That the Trust supported in principle option 2 and working with KDFC to deliver a hybrid pitch, but that redevelopment opportunities for the Stadium must not be limited at this stage and this should be reflected in any property agreements with KDFC. 2. That the Trust delegated authority to officers to: · Review with KDFC and the business case consultants the inclusion of the KDFC proposals, the impact of this on any of the business case options, and reflect this in the final business case report to the Committee in September · Ensure that the terms of the lease does not limit any future redevelopment proposals or opportunities · Advise KDFC that if proposals for redevelopment of the stadium site are approved and move forward in the future they may be required to move from the proposed location, and that the property terms will reflect this · Secure commitments from KDFC for an enhanced community use offer and develop a service ... view the full minutes text for item 3.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
Report to Wormwood Scrubs Charitable Trust Committee
Background
3. At the meeting of 29th January 2020, the Committee requested that officers investigate potential funding, including Section 106 (S106), that could be used to meet the request from KDFC for the Trust to provide £350,000 partnership funding for the proposal.
4. The S106 board has confirmed that S106 funding would not be available as: The board does not want to use generic s.106 for this purpose The board needs an overall borough strategy to understand where this proposal fits into the sports priorities of the borough
The proposal
5. KDFC wish to build a new Hybrid Grass pitch within the Stadium grounds. This would be for their own use at a peppercorn rent and would allow them to play football at a higher level. Draft heads of terms have been agreed and a certificate of Lawfulness has been agreed by LBHF.
6. Appendix 1 shows the Hybrid Grass pitch, labelled ‘full size grass pitch’ and the reorientation of the all-weather pitches (AWP’s) and the loss of a small part of the play area to accommodate this. The all-weather pitches will be refurbished as part of the proposal.
7. The proposal should foster a higher level of football at the scrubs with associated increase in bookings of the all-weather pitches. For illustrative purposes only Appendix 2 shows an estimate by KDFC of income from hire of all-weather pitches. This assumes 75% utilisation of peak hours and 50% utilisation of off peak. The income from the AWP’s would belong to the Trust.
8. KDFC are a charity and can also provide a range of community engagement activities such as the two days of schools use for the Hybrid grass pitch in the Heads of terms.
Existing all weather pitches
9. The AWP’s are the largest area of AWP’s in the borough. They were built in 2005 using grant funding and include an obligation to keep the pitches in a playable condition for at least another five years. 10. Repairs to the AWP’s is from a limited revenue budget. The current condition is declining, and the pitches will need some refurbishment before the five years are complete. A report commissioned by KDFC estimated the cost of refurbishment at £372,450.
Linford Christie Business Case Process
11. Consultants have been appointed by the Trust to deliver an outline business case on the options for Linford Christie Outdoor Sports Stadium. The Trust wishes to see the re-provision of high-quality athletics and sports equipment, but currently lacks the revenue and capital resources to achieve this.
12. The Consultants will produce a business case report that enables the Trust Committee to make a decision on a preferred option or options to achieve the objective above. This will be presented to the Trust Committee in September, and includes options for a range of intervetions from a moderate investment to a major redevelopment of the stadium area.
13. KDFC have been consultated as part of the business case process. The KDFC proposal may have an effect on the business case options and subsequent proposals, which will have to be considered further. The Trust will have to consider the impact of KDFC’s proposals on these options.
14. A major redevelopment might fund a future relocation of the pitch, but moderate or minimal interventions might not be able to afford the considerable cost, limiting development opportunity. For any of the options below to proceed KDFC, IPW the business case consultants and Trust officers will need to work together to review the impact on any business case proposals.
Options
15. Option 1: The committee could continue as present with minimal intervention. The condition of the AWP’s is deteriorating. No decision is made this will be the default position.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Wormwood Scrubs Charitable Trust Committee at Hammersmith & Fulham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.