London Borough of Hammersmith & Fulham
Full Council, Wednesday 26 February 2025 at 7.00pm

Four Year Capital Programme 2025-29 and Capital Strategy 2025/26

Approved Committee 1 paper

Full Council approved this item on Wednesday 26 February 2025. Below is the council's own wording, with the papers it was decided on.

Item6.4

Resolved

To approve the four-year General Fund Capital Programme budget at £103.8m for the period 2025/26-2028/29 (presented in Table 2 and Appendix 1). 2. T o approve the continuation of rolling programmes for 2025/26 funded from the Council’s mainstream resources. For financial modelling purposes, these programmes are assumed to continue at the same level until 2028/29: £m Corporate Planned Maintenance 2.400 Footways and Carriageways 2.030 Column Replacement 0.346 Total 4.776 To delegate approval of the detailed programmes for use of the rolling programmes, in recommendation 2, to the relevant SLT Director in consultation with the Executive Director, Finance and Corporate Services and the relevant Lead Cabinet Member To approve the four-year Housing (HRA) Capital Programme at £428.5m for the period 2025/26-2028/29 as set out in Table 6 and Appendix 1. To approve the Capital Strategy 2025/26, as set out in the report. To approve the annual Minimum Revenue Provision policy statement for 2025/26, as set out in Appendix 2. To note the potential financial impact of a number of development schemes not included in the current programme but being in the various predevelopment stages.
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Full Council

Summary

This report presents the Council’s Capital Strategy 2025/26 and four-year Capital Programme for the period 2025 to 2029.

The council is investing £532.3m over the next four financial years to develop and enhance its assets (including council housing), to meet its strategic objectives and provide better outcomes for its residents, businesses, and visitors. Key schemes within the programme include:

 Significant investment in the major repairs and health and safety compliance of the council’s 12,000 dwellings  Investment in housing development schemes to provide additional affordable accommodation across the borough  Public CCTV equipment purchases and installation  School maintenance programme  Investment in energy efficient lighting and decarbonisation schemes.  Hammersmith Bridge pre-restoration works, with funding from the Department of Transport and Transport for London  Civic Campus programme/ refurbishment of Hammersmith Town Hall  Investment in the council’s public realm including column replacement, footways, and carriageways

The council is required by the CIPFA Prudential Code for Capital Finance and statutory guidance to prepare certain capital related strategies and policies. The Capital Strategy and Minimum Revenue Provision (MRP) Policy are included in this report. The Treasury Management Strategy Statement 2025/26 will also be presented to Cabinet and Full Council in February 2025 under a separate agenda item.

In accordance with the requirements of the Prudential Code for Capital Finance, local authorities are required to maintain several prudential indicators. These are set out in the Treasury Management Strategy Statement 2025/26. The indicator used to reflect the underlying need of an authority to borrow for a capital purpose is the Capital Financing Requirement (CFR) which is set out within this report. RECOMMENDATIONS

1. To approve the four-year General Fund Capital Programme budget at £103.8m for the period 2025/26-2028/29 (presented in Table 2 and Appendix 1).

2. To approve the continuation of rolling programmes for 2025/26 funded from the Council’s mainstream resources. For financial modelling purposes, these programmes are assumed to continue at the same level until 2028/29:

£m Corporate Planned Maintenance 2.400 Footways and Carriageways 2.030 Column Replacement 0.346 Total 4.776

3. To delegate approval of the detailed programmes for use of the rolling programmes, in recommendation 2, to the relevant SLT Director in consultation with the Executive Director, Finance and Corporate Services and the relevant Lead Cabinet Member.

4. To approve the four-year Housing (HRA) Capital Programme at £428.5m for the period 2025/26-2028/29 as set out in Table 6 and Appendix 1.

5. To approve the Capital Strategy 2025/26, as set out in the report.

6. To approve the annual Minimum Revenue Provision policy statement for 2025/26, as set out in Appendix 2.

7. To note the potential financial impact of a number of development schemes not included in the current programme but being in the various predevelopment stages.

Wards Affected: All

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Four Year Capital Programme 2025-29 and Capital Strategy 2025/26Report 1.1 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

43 of 50 attended
JA
Councillor Jose AfonsoCommittee Member, present
AA
Councillor Aliya Afzal-KhanCommittee Member, present
PA
Councillor Paul AlexanderCommittee Member, present
AA
Councillor Adronie AlfordCommittee Member, present
SA
Councillor Stala AntoniadesCommittee Member, present
JB
Councillor Jackie BorlandCommittee Member, present
VB
Councillor Victoria Brocklebank-FowlerCommittee Member, present
DB
Councillor Daryl BrownDeputy Mayor, present
TC
Councillor Trey Campbell-SimonCommittee Member, present
FC
Councillor Florian Chevoppe-VerdierCommittee Member, present
LC
Councillor Liz CollinsCommittee Member, present
SC
Councillor Stephen CowanCommittee Member, present

All 50 on the meeting page

On this subject at Hammersmith & Fulham

Search all
  1. Four Year Capital Programme 2025-29 and Capital Strategy 2025/26This decision
  2. Four Year Capital Programme 2026-30 and Capital Strategy 2026/27Approved
  3. Four Year Capital Programme 2026-30 and Capital Strategy 2026/27Approved
  4. Four Year Capital Programme 2025-29 and Capital Strategy 2025/26Approved
  5. Four Year Capital Programme 2024-28 And Capital Strategy 2024/25Agreed
  6. Four Year Capital Programme 2024-28 and Capital Strategy 2024/25Approved

More from Hammersmith & Fulham Full Council

All decisions
MeetingDecisionOutcome
15 Jul 2026 Review of the ConstitutionRESOLVED 1. That Full Council approve the updates to the departmental Registers of Authorities detailed in Appendix 1... Approved Open
15 Jul 2026 Markets and Street Trading Licensing PolicyRESOLVED That Full Council adopt the , at Appendix 1 of the report and agree that it comes into effect on the 1 Augus... Approved Open
15 Jul 2026 Special Motion 2 - 10 Year anniversary of EU referendumRESOLVED This Council recognises the damage that Brexit has done to the economy, businesses and living standards in H... Decided Open
21 May 2026 Election of the MayorRESOLVED That Councillor Sharon Holder was duly elected Mayor of the London Borough of Hammersmith & Fulham for the 2... Decided Open
21 May 2026 Honorary Aldermen and Honorary AlderwomenRESOLVED That the Council confer the title “Honorary Alderwoman of the London Borough of Hammersmith and Fulham” on [... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies