Property Services: Major Programmes Update

Approved Committee 1 paper

Buildings, Land and Procurement Panel approved this item on Tuesday 26 March 2019. Below is the council's own wording, with the papers it was decided on.

Item67

Resolved

That the Panel notes the progress of each of the programmes. 2. That the Panel recommends to the Executive Member for Policy and Resources that the project appraisal for the Elizabeth II Court South Heating Improvement Works project, to be funded from the Policy and Resources Energy Performance Programme budget be approved at an estimated value of £355,000.
Word for word from the decision Hampshire published for this meeting. Source: democracy.hants.gov.uk

Follow this further

Built from Hampshire's papers

What the report saysPro

Report to Buildings, Land and Procurement Panel

Recommendations

1.1That the Buildings, Land and Procurement Panel notes the progress of each of the programmes.

1.2That the Panel recommends to the Executive Member for Policy and Resources that the project appraisal for the Elizabeth II Court South Heating Improvement Works project, to be funded from the Policy and Resources Energy Performance Programme budget be approved at an estimated value of £355,000. 2. Summary

2.1The purpose of this report is to provide an update on the major programmes, projects and issues currently being progressed relating to:

 Adult Health and Care Programme  Children’s Services Programme  Health and Safety management in the built estate  Office Accommodation Efficiency Programme  Carbon and Energy Reduction Programme  Construction Frameworks Update

3. Adult Health and Care Programme

3.1Property Services continues to support the County Council’s Adult Health and Care (AHC)service to deliver property outcomes for a number of existing and emerging transformation programmes. An update on each of these programmes is provided below:

Adults Health & Care Strategic Bed Based Programme

3.2An initial allocation of capital funds was added to the capital programme in July 2018 as part of the Medium-Term Financial Strategy for the Adults Health & Care Bed Based Programme. A study has been completed to identify the care provision required by the County Council over the medium to longer term which has taken account of predicted market capacity and conditions, as well as forecast demand and a future need analysis.

3.3Based on the outcome of the above study a high level review of existing and vacant sites has been completed by Property Services. The aim of the review was to identify potential options for addressing growth, future suitability and condition requirements across the AHC estate. The results of the study are currently being shared with AHC colleagues with a view to shaping the future investment proposals.

Adults with a Disability Housing Programme

3.4In April 2016, the Executive Member for Policy and Resources approved the Strategic Business Case for the Adults with Disability Housing Strategy. A decision was taken to support around 600 services users with a learning and/or physical disability to transition from a traditional care home setting into either a shared house or groups of individual flats to achieve independent living with 24/7 care and support available and commissioned by the County Council subject to the needs of each resident.

3.5Property Services has led on the design and delivery of the new build element of the strategy which will deliver around 95 extra care units on County Council owned sites. The units are being delivered through a two-phase programme, Phase 1 comprises of four projects and a further two projects will be delivered in Phase 2.

3.6The majority of schemes in Phase 1 of the new build programme (Jellicoe Court, Fernhill Court and Mulberry Lodge), have been completed and handed over. AHC, in partnership with the landlord and care provider, have been managing a phased occupation by residents from summer 2018 onwards. The remaining Phase 1 project (Apex Court) in Aldershot has been rescheduled and was due to be handed over to AHC in February 2019.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Property Services: Major Programmes UpdateAppendix 140 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 8 attended
MK
Councillor Mel KendalChairman, present
BW
Councillor Bill Withers Lt Col (Retd)Vice-Chairman, present
AC
Councillor Adrian CollettCommittee Member, apologies, sent representative
AG
Councillor Andrew GibsonCommittee Member, absent
KH
Councillor Keith HouseCommittee Member, present
RV
Councillor Rhydian Vaughan MBECommittee Member, present
AJ
Councillor Andrew JoyConservative Deputy
JP
Councillor Jackie PorterLiberal Democrats Deputy, present as substitute

On this subject at Hampshire

Search all
  1. Property Services: Major Programmes UpdateThis decision
  2. Property Services – design and delivery of building projectsNoted
  3. Property Services Operations: Response to Covid - PresentationAgreed
  4. Property Services Commercial Decisions ReportApproved
  5. Property Services: Major Programmes UpdateNoted
  6. Property Services Business ReviewDecided

More from Hampshire Buildings, Land and Procurement Panel

All decisions
MeetingDecisionOutcome
12 Oct 2022 Managing Hampshire’s Built EstateThat the Buildings, Land and Procurement Panel recommends that the Executive Member for Commercial Strategy, Estates ... Approved Open
14 Jun 2022 Managing Hampshire’s Built EstateThat the Buildings, Land and Procurement Panel recommends that the Executive Member for Commercial Strategy, Estates ... Approved Open
14 Jun 2022 Business Services Group – 2021/22 Annual Report and AccountsThat the Buildings, Land and Procurement Panel recommend to the Executive Member for Commercial Strategy, Estates and... Approved Open
14 Jun 2022 Exclusion of the press and publicThe press and public were excluded from the meeting during the following item of business, as it was likely, in view ... Decided Open
6 Apr 2022 Managing Hampshire’s Built EstateThat the Buildings, Land and Procurement Panel recommends that the Executive Member for Commercial Strategy, Estates ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies