Hampshire Fire and Rescue Authority approved this item on Wednesday 22 July 2020. Below is the council's own wording, with the papers it was decided on.
a) The accounts for 2019/20, including the use of reserves set out in paragraph 24 and Appendix D of the report were approved by Hampshire Fire and Rescue Authority b) The carry forward requests totalling £763,000 as set out in paragraph 13 of this report were approved by Hampshire Fire and Rescue Authority. c) The changes to the capital payments reserve in 2019/20 and the impact on the capital spend profile going forward as set out in Appendices B and C were approved by Hampshire Fire and Rescue Authority. d) The financing for capital payments as set out in paragraph 16 were approved by Hampshire Fire and Rescue Authority. e) The annual treasury outturn report set out in Appendix E of the report was approved by Hampshire Fire and Rescue Authority.
Word for word from the decision Hampshire published for this meeting.Source: democracy.hants.gov.uk
1. The final year end position for 2019/20 is an underspend of £0.912m against budget. Carry forward requests totalling £0.763m have been put forward, and provisionally agreed by the Chairman of the Fire Authority, which would leave a balance of £0.149m to be transferred to reserves.
2. This report requests Members of the Authority to review the figures as laid out in the appendices and recommends that the outturn report, including carry forwards, reserves and capital financing are approved, along with the annual treasury outturn for 2019/20.
Background
3. This is an annual report which sets out the financial position at the end of 2019/20 as per the draft Statement of Accounts.
4. The Covid-19 pandemic started right at the end of the 2019/20 financial year and as such there is no direct impact on the finances of the authority reflected in the figures presented in this report.
REVENUE EXPENDITURE 2019/20
5. The revenue outturn position is shown in functional and subjective summary at Appendix A.
6. Within the overall outturn position there are a number of variances to budget which can broadly be broken down into 3 main elements. These are:
(a) Overspend on operational budgets - £1.936m (b) Underspends across non-operational budgets – (£1.594m) (c) Underspends against central budgets – (£1.254m) 7. The overspend on operational budgets is due to a number of factors. The most significant are the cost of the RDS Support Officers (£492,000), which were unbudgeted but remained in post for the full year as there was a need to continue to push for recruitment and retention of Retained Duties Firefighters.
8. In addition, there was a recruits’ intake (£335,000), for which salaries were unbudgeted. Crewing at Southsea Station was overspent by £324,000 as a result of a delay in the acquisition of new vehicles which prevented the introduction of the new crewing model. The remainder of the overspend is made up of PPE requirements and reduced levels of income.
9. It is pleasing to note that the majority of these overspends were known about in year and decisions were taken to meet the costs from savings declared elsewhere. Furthermore, all these areas of concern are being addressed and action put in place to prevent further overspending in 2020/21, albeit separate provision will need to be made for any further recruitment exercises planned to take place next year.
10. Underspends across non-operational areas were largely due to vacant posts across the service as a whole. This is partly due to the restructuring across the Service in the early part of the year, which then required recruitment to take place in order to fill the roles.
11. Underspends against central budgets were mainly as a result of unused pay allowances and additional grant received from the Government in respect of pension costs following the increase in contribution rates notified previously.
12. The outturn balance also includes £3.905m contribution to the Capital Payments Reserve, £1.474m contribution to the Transformation Reserve and £0.344m net contribution to the Equipment Reserve in line with the Medium Term Financial Plan.
CARRY FORWARD REQUESTS
13. Requests have been received from Property Services and ICT Services to carry forward budget allocated in 2019/20 for work which was unable to be completed in the year. These are:
(a) Alteration and improvement works (£706,000) – this work could not be completed in year due to staffing vacancies and other significant delays. This work still needs to be carried out and will take place in 2020/21 providing the funding is made available.
(b) Firewall replacement (£45,000) – this is essential work for ICT security and was scheduled to be completed in late 2019/20 but was delayed due to COVID-19.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.