RESOLVED An extension of time until 31 December 2020 was agreed for the satisfactory completion of the Deed of Variation to the Section 106 agreement for permission 19/10066 to transfer the Section 106 [S106] legal obligations relating to planning permission 07/90183, to secure: · lorry routing agreement restricting the use of Harbridge Drove and the B3081 northwards, except for local deliveries; · Management Agreement for Nature Conservation and the provision of footpaths/access for public recreation (including amendments to enhance the scheme of environmental compensation); and · off-site heathland works within Plumley Wood. This also required extensions of time until the same date for the determination of planning applications 19/10064 and 19/10063, as these were both dependant on the prior granting of 19/10066. Upon completion of the Deed of Variation authority was agreed to be delegated to the Director of Economy, Transport and Environment to grant permission in all other respects in accordance with the resolution for planning applications 19/10066, 19/10064 and 19/10063 made at the meeting held on 17 April 2019. Voting: Favour: 14 (unanimous)
Word for word from the decision Hampshire published for this meeting.Source: democracy.hants.gov.uk
1. That an extension of time until 31 December 2020 is agreed for the satisfactory completion of the Deed of Variation to the Section 106 agreement for permission 19/10066 to transfer the Section 106 [S106] legal obligations relating to planning permission 07/90183, to secure:
lorry routing agreement restricting the use of Harbridge Drove and the B3081 northwards, except for local deliveries; Management Agreement for Nature Conservation and the provision of footpaths/access for public recreation (including amendments to enhance the scheme of environmental compensation); and off-site heathland works within Plumley Wood.
2. This also requires extensions of time until the same date for the determination of planning applications 19/10064 and 19/10063, as these are both dependant on the prior granting of 19/10066.
3. Upon completion of the Deed of Variation authority be delegated to the Director of Economy, Transport and Environment to grant permission in all other respects in accordance with the resolution for planning applications 19/10066, 19/10064 and 19/10063 made at the meeting held on 17 April 2019.
Background
4. This report relates to planning applications 19/10066, 19/10064 and 19/10063 at Blue Haze Landfill Site, Verwood Road, Somerley.
5. Planning application 19/10066 seeks to vary Conditions 1 (Phasing), 3 (Completion date) and 4 (Working programme) of planning permission 07/90183 at Blue Haze Landfill Site, Verwood Road, Somerley to extend the time to complete the importation of waste to the landfill by 10 years until 2029, revise the landfill phasing and phasing of restoration, and the completion of landfill restoration by 2031.
6. The applicant also submitted further planning applications (19/10064 and 19/10063), seeking to regularise ancillary developments on the Blue Haze Landfill Site by extending their temporary planning permissions in line with that sought for the overall landfill site. As the determination of the two remaining ancillary applications are dependent on the determination of the overarching planning application 19/10066, all three were considered at the Regulatory Committee meeting held on 17 April 2019 for determination.
7. At the Regulatory Committee meeting it was resolved that planning permission be granted for the three applications, subject to the completion of a Deed of Variation to link the obligations in the original Section 106 agreement applying to planning permission 07/90183 to 19/10066.
8. The Regulatory Committee gave officers delegated authority to grant planning permission, subject to conditions, on completion of the Section 106 agreement or, if necessary, to refuse planning permission if the agreement was not completed by 30 September 2019.
9. At the 16 October 2019 Regulatory Committee meeting, it was agreed that a further four-month period from 30 September 2019, until 31 January 2020, was given for the satisfactory completion of the Section 106 agreement.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Update to the Validation GuidanceRESOLVED That the Committee note the contents of the draft Planning Application Validation Guidance and approve the d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.